IPO fund utilisation in Bangladesh: what companies promised to spend IPO money on, against what they reported
IPO money in Bangladesh: 52.8% was promised to machinery and expansion, and 14 of 43 IPOs whose deadline had passed spent it in time
Prospectus use-of-proceeds tables for 128 DSE IPOs of 2010-2024 set against the companies' later utilisation statements, auditor certificates, extensions and BSEC actions.
For information only, not investment advice. AnalystBro accepts no responsibility for decisions made on it. Full disclaimer.
- Of BDT 85.64bn in 115 prospectus tables, 52.8% was promised to capex, 20.7% to loan repayment and 19.4% to investments. →
- Loan repayment's share fell from 37.5% (2010-2014 listings) to 13.6% (2020-2024). →
- Where timing can be measured, 14 of 43 IPOs (32.6%) used the money by the prospectus deadline. →
- 8 IPOs reported BDT 2.64bn still unspent in statements dated 2025 or 2026. →
- BSEC fined directors of three companies over non-compliance 'in connection with utilization of IPO proceeds'. →
74 of 128 IPOs have both a promised split and a later utilisation statement in our filings
Every Bangladeshi IPO prospectus has a use-of-proceeds table: how much of the money goes to machinery, buildings, loan repayment, working capital and IPO costs, and by when [2]. Companies then report how much they have spent: in quarterly or monthly auditor-certified statements to BSEC and the exchanges, in their annual reports, and in DSE news posts when the board extends the time or changes the plan [3][4]. We read the prospectus table for 128 companies that listed on the DSE from 2010 to 2024 and whose prospectus is in our corpus, and set it against the latest statement each company published [1].
115 prospectuses gave a split we could total (BDT 85.64bn); 77 companies have a later statement saying whether the money was spent; 74 have both [1]. Of the 77 with a statement, 50 say the money was fully used and 27 still showed money unspent at their latest statement [1]. For the rest we found nothing on the IPO money after listing in their reports or on the DSE, or only a one-line compliance remark; this is a partial record. We do not say a company misused money unless an auditor or BSEC said so; where they did, we quote them.
Related: every Bangladesh IPO since 2015 and how each performed, IPO lottery odds, the IPO investing guide and the IPO list.
Capex took 52.8% of promised IPO money; loan repayment 20.7%
Across the 115 tables, companies promised 52.8% of the money to machinery, buildings and expansion, 20.7% to repaying bank loans, 19.4% to investments (mainly banks and insurers buying government securities, FDRs and shares, or lending), 1.9% to working capital and 3.2% to IPO costs [1][2]. 64 of the 115 IPOs promised at least some loan repayment [1].
The mix changed. In 2010-2014 listings, loan repayment took 37.5% of the promised money; in 2015-2019 16.9%; in 2020-2024 13.6% [1]. Investments rose to 42.0% in 2020-2024, when banks and insurers made up much of the money raised; two bank IPOs of 2022, Union Bank and Global Islami Bank, account for BDT 8.53bn [1].
| Listing years | IPOs with split | Promised (BDT bn) | Capex | Loan repayment | Working capital | Investments | IPO costs |
|---|---|---|---|---|---|---|---|
| Listed 2010-2014 | 35.00 | 21.64 | 48.5% | 37.5% | 5.8% | 5.3% | 2.8% |
| Listed 2015-2019 | 44.00 | 27.51 | 71.6% | 16.9% | 1.5% | 0.6% | 3.7% |
| Listed 2020-2024 | 36.00 | 36.49 | 41.3% | 13.6% | 0.0% | 42.0% | 3.1% |
| All, 2010-2024 | 115.00 | 85.64 | 52.8% | 20.7% | 1.9% | 19.4% | 3.2% |
| Listing year | IPOs in scope | With promised split | Promised total, split IPOs (BDT) | Capex (BDT) | Loan repayment (BDT) | Working capital (BDT) | Investments (BDT) | IPO costs (BDT) | Other + not itemised (BDT) | Capex share | Loan repayment share | Working capital share | Investments share | IPO costs share | With reported data |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2010 | 6 | 2 | 390,000,000 | 0 | 0 | 283,966,500 | 90,000,000 | 0 | 16,033,500 | 0 | 0 | 1 | 0 | 0 | 0 |
| 2011 | 3 | 1 | 294,140,000 | 224,440,000 | 50,200,000 | 19,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | 0 | 1 |
| 2012 | 10 | 6 | 4,172,728,000 | 1,078,750,000 | 2,211,919,000 | 255,999,000 | 500,000,000 | 126,060,000 | 0 | 0 | 1 | 0 | 0 | 0 | 2 |
| 2013 | 11 | 10 | 8,757,646,500 | 4,594,319,016 | 3,196,245,768 | 168,746,562 | 565,066,500 | 209,882,654 | 23,386,000 | 1 | 0 | 0 | 0 | 0 | 3 |
| 2014 | 16 | 16 | 8,027,741,500 | 4,589,267,686 | 2,648,653,949 | 517,382,765 | 0 | 272,437,100 | 0 | 1 | 0 | 0 | 0 | 0 | 6 |
| 2015 | 12 | 12 | 9,654,721,200 | 5,463,139,990 | 1,972,137,667 | 401,764,794 | 0 | 307,888,749 | 1,509,790,000 | 1 | 0 | 0 | 0 | 0 | 10 |
| 2016 | 7 | 5 | 4,999,800,000 | 4,656,250,096 | 40,000,000 | 15,427,654 | 172,466,000 | 115,656,250 | 0 | 1 | 0 | 0 | 0 | 0 | 3 |
| 2017 | 7 | 7 | 2,442,500,000 | 1,585,507,111 | 728,385,716 | 0 | 0 | 111,217,173 | 17,390,000 | 1 | 0 | 0 | 0 | 0 | 4 |
| 2018 | 11 | 11 | 5,010,000,000 | 3,894,690,192 | 857,061,644 | 0 | 0 | 258,248,164 | 0 | 1 | 0 | 0 | 0 | 0 | 10 |
| 2019 | 9 | 9 | 5,400,000,000 | 4,107,918,502 | 1,045,000,000 | 0 | 0 | 232,081,498 | 15,000,000 | 1 | 0 | 0 | 0 | 0 | 6 |
| 2020 | 7 | 7 | 7,678,723,340 | 6,593,600,701 | 470,603,373 | 0 | 395,061,500 | 199,881,766 | 19,576,000 | 1 | 0 | 0 | 0 | 0 | 5 |
| 2021 | 13 | 13 | 10,460,000,000 | 3,736,756,493 | 2,288,155,282 | 0 | 4,033,111,260 | 401,976,966 | 0 | 0 | 0 | 0 | 0 | 0 | 12 |
| 2022 | 9 | 9 | 10,886,220,100 | 1,145,900,000 | 461,800,000 | 0 | 9,025,514,692 | 253,005,408 | 0 | 0 | 0 | 0 | 1 | 0 | 8 |
| 2023 | 2 | 2 | 860,000,000 | 0 | 0 | 0 | 813,101,545 | 46,898,455 | 0 | 0 | 0 | 0 | 1 | 0 | 2 |
| 2024 | 5 | 5 | 6,610,000,000 | 3,583,760,895 | 1,736,076,461 | 0 | 1,049,700,000 | 240,462,644 | 0 | 1 | 0 | 0 | 0 | 0 | 5 |
| 2010-2024 | 128 | 115 | 85,644,220,640 | 45,254,300,682 | 17,706,238,860 | 1,662,787,275 | 16,644,021,497 | 2,775,696,827 | 1,601,175,500 | 1 | 0 | 0 | 0 | 0 | 77 |
| 2010-2014 | 46 | 35 | 21,642,256,000 | 10,486,776,702 | 8,107,018,717 | 1,245,594,827 | 1,155,066,500 | 608,379,754 | 39,419,500 | 0 | 0 | 0 | 0 | 0 | 12 |
| 2015-2019 | 46 | 44 | 27,507,021,200 | 19,707,505,891 | 4,642,585,027 | 417,192,448 | 172,466,000 | 1,025,091,834 | 1,542,180,000 | 1 | 0 | 0 | 0 | 0 | 33 |
| 2020-2024 | 36 | 36 | 36,494,943,440 | 15,060,018,089 | 4,956,635,116 | 0 | 15,316,488,997 | 1,142,225,239 | 19,576,000 | 0 | 0 | 0 | 0 | 0 | 32 |
From the By year tab of the model.
14 of 43 IPOs whose deadline had passed spent the money in time
Each prospectus gives an implementation schedule, usually 'within N months of receiving the IPO fund'; the windows we found run from one month (loan repayment) to 24 months (new plants) [2]. The 2015 Rules require that schedule in the prospectus [6]. The 2025 Rules add that the issuer must report utilisation to BSEC 'duly audited by a panel of auditors of the Commission within 10 (ten) days of the end of each quarter' with a confirmation that the money was used as the prospectus said [5].
We take the deadline as the listing date plus the longest window in the schedule (or the deadline the company or its auditor printed, for three IPOs), and compare it with the date a statement says the money was fully used [1]. That is measurable for 47 IPOs. 14 finished by the deadline; 11 finished after it, a median 16.8 months late; 18 still had money unspent in a statement dated after the deadline, a median 11.8 months past it at that statement (16 with a measurable gap); and for 4 the deadline had not passed at the latest statement [1]. So 14 of the 43 whose deadline had passed (32.6%) were on time. For the other 81 IPOs there was no statement, no schedule we could read, or only a report-date that says the money was used without saying when.
27 IPOs recorded at least one board, shareholder or BSEC decision to extend the time [1][4]. Some extended repeatedly: Aman Cotton Fibrous (ACFL) moved its deadline several times and at 30 June 2025 still reported BDT 717.5m unspent of BDT 800m [7]; JHRML's shareholders revised the plan and timeline at two AGMs, in 2023 and 2024 [17].
8 IPOs reported BDT 2.64bn unspent in statements dated 2025 or 2026
The latest statements we found from 8 companies, dated 2025 or 2026, show BDT 2.64bn of IPO money not yet used [1]. Global Islami Bank reported BDT 738.2m unspent at 30 June 2025 and BSEC approved a change of use with more time to November 2026 [8]. Asiatic Laboratories' board proposed on 1 November 2026 another 18 months to use BDT 649.4m for its Tongi factory, subject to BSEC approval [9]. Technodrugs had BDT 355.4m unspent at 30 June 2025, within its 24-month window [17].
| IPO | Listing year | Promised (BDT m) | Unspent (BDT m) | Unspent share | Statement date | Extension decisions | Source |
|---|---|---|---|---|---|---|---|
| GIB | 2,022.0 | 4,250.0 | 738.2 | 17.4% | 30-Jun-2025 | 3.0 | announcement 20006 (statement for quarter ended 30 June 2025) |
| ACFL | 2,018.0 | 800.0 | 717.5 | 89.7% | 30-Jun-2025 | 3.0 | ACFL_ANNUAL_2025 p.66 |
| ASIATICLAB | 2,024.0 | 950.0 | 649.4 | 68.4% | 01-Nov-2026 | 1.0 | DSE post id 6171 (1-Nov-2026) |
| TECHNODRUG | 2,024.0 | 1,000.0 | 355.4 | 35.5% | 30-Jun-2025 | 0.0 | TECHNODRUG_ANNUAL_2025 p.100 and p.68 |
| LRBDL | 2,021.0 | 1,500.0 | 131.0 | 8.7% | 30-Jun-2025 | 0.0 | LRBDL_ANNUAL_2025_2 p.2 (auditor's report) |
| SILVAPHL | 2,018.0 | 300.0 | 28.2 | 9.4% | 30-Jun-2025 | 3.0 | SILVAPHL_ANNUAL_2025 p.44,45 |
| NAVANAPHAR | 2,022.0 | 750.0 | 22.3 | 3.0% | 30-Jun-2025 | 1.0 | NAVANAPHAR_ANNUAL_2025_3 p.235 |
| JHRML | 2,022.0 | 750.0 | 1.7 | 0.2% | 30-Sep-2025 | 4.0 | JHRML_ANNUAL_2025 p.43 |
Adding older statements, the 27 IPOs not fully used at their latest statement showed BDT 5.19bn unspent, but several of those statements are years old and later reports did not give a figure, so we do not treat that as money outstanding today [1].
41 IPOs recorded a change of purpose, approved by shareholders, BSEC or both
41 IPOs recorded at least one change to what the money was for: a different machine, a new site, loan repayment instead of a project, or unspent money moved to working capital [1][4]. Most went to an AGM or EGM and then to BSEC. BSEC approved Runner Automobiles' revised plan in February 2020 on the condition that 'the company shall not issue any bonus share prior to proper utilization of IPO proceeds in accordance with revised utilization plan' [16]. It rejected Ring Shine Textiles' application to release USD 1.00m of IPO money in July 2025 [4][10].
Some changes were made before approval. Queen South Textile's auditor wrote that the company 'has purchased natural gas engine generator set instead of purchasing 1 set of Yarn Package Drying Machine' and that the revised plan was 'yet to be approved by the Bangladesh Securities and Exchange Commission (BSEC)' [13]. Lovello's auditor wrote that 'BSEC has not approved the rectification and extension of time till to date' [15].
Auditors qualified or flagged IPO-fund use in at least nine companies; BSEC fined directors of three
These are the regulator and auditor statements on IPO money we found, quoted as printed [1]:
- Aman Cotton Fibrous, auditor's qualified opinion for August 2020: 'FDR of Tk. 73 crore made from IPO Proceeds is pledged as security for credit facilities enjoyed by other entities.' [7]
- Lub-rref (Bangladesh), auditor FY2025: 13.10 crore of IPO proceeds 'remains unspent ... This non-utilization of funds is a material non-compliance' [11]
- Ring Shine Textiles, auditor's certificate 2023-24: 'the company has surpassed its deadline of full utilization of IPO funds as per the approved Prospectus on April 05, 2021' and 'Management has changed the purposes of use of funds but the approval form the shareholders in AGM is yet to be received.' [10]
- S.K. Trims, auditor FY2020: 'The company should have utilized Tk.300, 000,000 but as per evidence collected, the company utilizes Tk.147, 889,570(49.29%).' [14]
- Queen South Textile, auditor's qualified opinion June 2020 (generator bought instead of a drying machine) [13]
- Argon Denims, auditor 2013: 'We observed over adjustment of short term loan from IPO proceeds beyond the prospectus amount.' [4]
- Dominage Steel, auditor FY2023: 'The total IPO Fund was not utilized within the stipulated time' [3]
- BSEC penalties on directors for non-compliance with securities laws 'in connection with utilization of IPO proceeds': Dragon Sweater and Spinning (Tk 5 lakh each, March 2018), Pacific Denims (Tk 3 lakh each, January 2019) and Kattali Textile (Tk 50 lakh each and Tk 1 crore on the managing director, August 2020) [12]
| IPO (DSE code) | By | Quote (verbatim) | Source |
|---|---|---|---|
| ARGONDENIM | auditor | a) We observed over adjustment of short term loan from IPO proceeds beyond the prospectus amount. We observed excess payment of IPO related expenses. c) Liabilities from IPO fund found adjusted against bridge finance and short term loan earlier undisclosed in the prospectus. d) We also observed that significant amount was made to various suppliers and contractors against purchase of construction materials from IPO proceeds for expansion project in cash instead of cheque. | announcements 111723/111721/111722 (2014-05-12, emphasis of matter, year ended 31 Dec 2013, note 36.1) |
| MATINSPINN | auditor | In Note: 4 to the financial statements, management explains about the use of two diesel generators which were purchased with the fund from IPO proceeds for the MÂlange unit of the company. | announcement 94860 (2017-01-01), Emphasis of Matter FY2016 |
| DSSL | BSEC | BSEC has imposed fine of Tk. 5.00 lac each to the following Sponsors & Directors of the Company namely Mr. Mostafa Quamrus Sobhan (Chairman), Mr. Mostafa Golam Quddus (Managing Director), Mrs. Fazlutun Nessa (Director), Mrs. Fauzia Quamrun Tania (Director), Mrs. Tasnia Quamrun Anika (Director) and Mrs. Shafia Sobhan Chowdhury (Director) for noncompliance of Securities laws in connection with utilization of IPO proceeds. | announcement 85733 (2018-03-11, DSE news citing BSEC) |
| PDL | BSEC | BSEC has imposed penalty of Tk. 3.00 lac each of the following Directors of the Company; namely Mr. Md. Shadequl Alam (Yeasin), Chairman; Mr. Shafiul Azam (Mohsin), Managing Director; Mr. Md. Sohel Khan, Director and Mr. M. A. Kamal Bhuiyan (nominated Director from Disney Properties Ltd.) for noncompliance with Securities laws in connection with utilization of IPO proceeds. | announcement 185197 (2019-01-08) |
| SHEPHERD | auditor | IPO proceeds have been utilized in line with the conditions as stipulated in the BSEC’s Consent letter for the IPO and revised IPO Utilization plan as approved in the 17 AGM which is yet to be approved by the Bangladesh Securities and Exchange Commission (BSEC) | SHEPHERD_DOC_2019_3 p.2 |
| ACFL | auditor | According to IPO Utilization Audit Reports as of June 30 2025, the company has Un- utilized IPO proceeds amounting BDT. 717,498,337 and the shareholders of Aman Cotton Fibrous PLC has approved the revised time line for fund utilization of IPO proceed up to 31 December 2028. | ACFL_ANNUAL_2025 p.66 |
| ACFL | auditor | FDR of Tk. 73 crore made from IPO Proceeds is pledged as security for credit facilities enjoyed by other entities. | announcement 172877 (2020-10-13, Qualified Opinion on Utilization of IPO Fund, month of Aug 2020) |
| INTRACO | auditor | We draw attention to note # 33 of the financial statements, which describes the utilization of IPO proceeds up to 30 June 2020 as certified by independent auditor, Shiraz Khan Basak & Co, Chartered Accountants. Our opinion is not modified in respect of this matter. | announcement 171098 (2020-11-24, Emphasis of Matter) |
| KTL | BSEC | BSEC has imposed penalty of Tk. 50.00 lac each of the following Directors of the Company; namely Mr. Md. Anwarul Haque Chowdhury (Director), Mr. Md. Mokarrom Anwar Chowdhury (Director), Eian Apparels Ltd. (Director) Lucky Corner (Director), Ms. Nasreen Hoque (Chairman) and Tk. 1.00 crore on Mr. Md. Emdadul Hoque Chowdhury (Managing Director) for noncompliance with Securities laws in connection with utilization of IPO proceeds. | announcement 78315 (2020-08-25) |
| MLDYEING | DSE | Rest amount BDT. 130,397,512 of IPO fund has been utilized according to the decided purpose exceeding the time duration of IPO declaration due to the global impact of COVID-19 Pandemic. | announcement 77525 (2020-12-29, company statement) |
| QUEENSOUTH | auditor | The revised IPO Utilization plan is yet to be approved by the Bangladesh Securities and Exchange Commission (BSEC) | QUEENSOUTH_DOC_2020_4 p.2 |
| QUEENSOUTH | auditor | The company has purchased natural gas engine generator set instead of purchasing 1 set of Yarn Package Drying Machine | announcement 174349 (2020-07-23, Qualified Opinion) |
| SKTRIMS | auditor | The company should have utilized Tk.300, 000,000 but as per evidence collected, the company utilizes Tk.147, 889,570(49.29%). | SKTRIMS_ANNUAL_2020 p.50 |
| RINGSHINE | auditor | the company has surpassed its deadline of full utilization of IPO funds as per the approved Prospectus on April 05, 2021. | RINGSHINE_DOC_2024_12 p.3 |
| RINGSHINE | auditor | Management has changed the purposes of use of funds but the approval form the shareholders in AGM is yet to be received. | RINGSHINE_DOC_2024_12 p.3 |
| RUNNERAUTO | BSEC | the company shall not issue any bonus share prior to proper utilization of IPO proceeds in accordance with revised utilization plan. | announcement 176047 (2020-02-25) |
| DOMINAGE | auditor | The total IPO Fund was not utilized within the stipulated time and the company has taken further time extension from Bangladesh securities exchange commission. | DOMINAGE_ANNUAL_2023 p.2 (Emphasis of Matter 2) |
| DOMINAGE | auditor | The tetal IPO Fund was not utilized within the stipulated time and the company has applied further time extension to Bangladesh securities exchange commission up to December 2024. | DOMINAGE_ANNUAL_2024 p.2 (Emphasis of Matter; OCR typo 'tetal' as printed) |
| BPPL | auditor | IPO Expenses includes Tk. 7,877,215 that has been utilized for normal course of business which remained un-utilized for IPO expenses due to change of IPO process like, allocation of share by pro-rata basis instead of conducting lottery and others as estimated while preparing published prospectus. | BPPL_DOC_2021_12 p.1 |
| LOVELLO | auditor | BSEC has not approved the rectification and extension of time till to date | LOVELLO_ANNUAL_2025 p.63 |
| LOVELLO | auditor | The expenses/utilization has been made in line with the provision of Initial Public Offering (IPO) documents except Tk. 10,337,854 | LOVELLO_ANNUAL_2025 p.63 |
| LRBDL | auditor | As on date an amount of 13.10 Crore from the IPO proceeds remains unspent and held in Social Islami Bank PLC which has outstanding balance of 19.87 Crore including profit accrued thereon. This non-utilization of funds is a material non-compliance with the stated purpose of the IPO as disclosed in Paragraph- a of chapter-XXII of the said prospectus. | LRBDL_ANNUAL_2025_2 p.2 |
| NRBCBANK | auditor | IFO Tk. 8,845,414 higher than proposed expenses mentioned in the documents due to processing of more than expected application cost, Eligible Investor Data processing cost by DSE and additional CDBL Charge | NRBCBANK_DOC_2021_2 p.3 (OCR) |
| SIPLC | auditor | using the proceeds of the IPO funds as consented by the BSEC, for which the company will take approval in the Annual General Meeting (AGM). However, our opinion is not modified in respect of these matters. | announcement 51553 (2023-03-15, Emphasis of Matter, partial text) |
| UNIONBANK | DSE | Due to unavoidable circumstances the remaining amount of Investment in Capital Market could not be properly utilized within the timeline as per Prospectus. | announcement 34235 (2024-06-30, company statement) |
| SICL | auditor | The company took IPO fund from the share market previous year and it was given 03 months to utilized this fund which yet to be done. | SICL_ANNUAL_2025 p.3 (read from page image) |
From the Remarks tab of the model.
Method: 128 prospectuses read, 74 matched to a utilisation statement
- Scope: IPOs listed on the DSE from 2010 to 2024 whose prospectus is in our filings corpus (128); qualified investor offers (SME board), draft and duplicate prospectuses are excluded. Union Bank's prospectus could not be read; its promised split is the 'as per prospectus' column of its FY2023 annual report.
- Promised: the prospectus use-of-proceeds table, read from extracted page text; four tables with damaged text were read from the page image. Categories (capex, loan repayment, working capital, investments, IPO costs, other) are ours; the printed labels are in the model notes.
- Reported: the latest utilisation statement, auditor certificate or company statement in later annual, quarterly and price-sensitive reports, and DSE news posts on IPO proceeds to 1-Nov-2026.
- Deadline: listing date plus the longest implementation window printed in the prospectus, or the deadline printed by the company or auditor where one exists (Ring Shine, Lovello, S.K. Trims). The money arrives a few weeks before listing; this deadline is therefore slightly generous to the company. Dominage Steel and S.K. Trims count as unspent after the deadline on their auditors' statements, without a months-late figure.
- Completion: the date the statement says the money was fully used. Where a report only says the money 'has been utilised' without a date, we treat the timing as not measurable unless the company also recorded an extension.
- Gaps: 13 IPOs had no usable split and 51 no statement we found. Monthly auditor reports posted on the DSE site are linked, not quoted in the news text; many companies' latest figures may be newer than what we show.
| IPO (DSE code) | Listing date | Listing year | Promised total (BDT) | Capex (machinery, buildings, expansion) (BDT) | Loan repayment (BDT) | Working capital (BDT) | Investments (securities, FDRs, lending) (BDT) | IPO costs (BDT) | Other (BDT) | Not itemised on the page (BDT) | Items check (sum less total) | Capex share | Loan repayment share | Working capital share | Investments share | Promised source | Promised window (months) | Printed deadline (company/auditor) | Auditor says deadline missed (Y) | Deadline (listing + window, or printed) | Latest statement date | Utilised at latest statement (BDT) | Unspent at latest statement (BDT) | Fully utilised (Y/N) | Completion evidence date | Completion evidence type | Reported source | Status vs deadline | Months late (completion or latest statement) | Extension decisions recorded | Changes of purpose recorded | Auditor/BSEC remarks recorded | Extensions and changes: sources | Listing date source | Note | Has promised split (1/0) | Has reported data (1/0) | Unspent share of promised | Helper: months late, completed after deadline | Helper: months past deadline, unspent |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ACTIVEFINE | 40,504 | 2,010 | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Packet has no prospectus pages and no reported hits (docs list empty); nothing extractable. | 0 | 0 | — | — | — |
| BEACONPHAR | 40,402 | 2,010 | 300,000,000 | 0 | 0 | 283,966,500 | 0 | 0 | 0 | 16,033,500 | 0 | 0 | 0 | 1 | 0 | BEACONPHAR_PROSPECTUS_2010 p.26 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs. | 1 | 0 | — | — | — |
| DHAKAINS | 40,227 | 2,010 | 108,000,000 | — | — | — | — | — | — | — | — | — | — | — | — | DHAKAINS_PROSPECTUS_2009 p.14 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs. | 0 | 0 | — | — | — |
| MALEKSPIN | 40,392 | 2,010 | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 1 | 0 | CHG 2010-12-27 (AGM 27 Dec 2010): Shareholders approved revised investment programme in lieu of IPO proceeds investment in N [announcements 140896, 140892 (2011-04-04)] | first DSE trading day in day-end prices | Only prospectus page 36 (financial discussion) in packet, not the use-of-proceeds table; prospectus says capex only via equity subscription in subsidiary NewAsia Synthetics Ltd per use of proceeds (investment). No reported-utilisation reports in packet. | 0 | 0 | — | — | — |
| PROVATIINS | 40,196 | 2,010 | 90,000,000 | 0 | 0 | 0 | 90,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | PROVATIINS_PROSPECTUS_2009 p.14 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No itemised use of proceeds, no reported utilisation or announcements in packet. | 1 | 0 | — | — | — |
| RAKCERAMIC | 40,342 | 2,010 | — | — | — | — | — | — | — | — | — | — | — | — | — | RAKCERAMIC_PROSPECTUS_2010 p.56 | 3 | — | — | 40,434 | — | — | — | — | — | — | — | no statement found | — | 0 | 1 | 0 | CHG 2011-01-30 (Board; subject to shareholders approval (AGM 20.03.11)): Board decided to invest unutilized IPO proceeds of Tk. 1,328.93 million (=1,328,930,000) i [announcement 142300] | first DSE trading day in day-end prices | IPO size not printed in packet; unutilised proceeds 1,328.93 million after IPO per announcement suggests proceeds were not applied to loans as planned. | 0 | 0 | — | — | — |
| CROWNCEMNT | — | 2,011 | — | — | — | — | — | — | — | — | — | — | — | — | — | CROWNCEMNT_PROSPECTUS_DRAFT_2011 p.14 | — | — | — | — | 45,107 | — | 0 | Y | — | — | CROWNCEMNT_ANNUAL_2023 p.97 | completed, timing not measurable | — | 0 | 0 | 0 | — | approximate: prospectus year (eod code history starts later) | Draft prospectus; final IPO amount not stated in the packet page (project cost, not necessarily IPO amount). Many PSIs/annual reports exist (22 docs) that may carry utilisation statements. | 0 | 1 | — | — | — |
| MJLBD | 40,720 | 2,011 | — | — | — | — | — | — | — | — | — | — | — | — | — | MJLBD_PROSPECTUS_2011 p.20 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Only one page in packet; no use-of-proceeds allocation table or total; no reported utilisation/announcements. | 0 | 0 | — | — | — |
| RDFOOD | 40,875 | 2,011 | 294,140,000 | 224,440,000 | 50,200,000 | 19,500,000 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | RDFOOD_PROSPECTUS_2011 p.16 | 7 | — | — | 41,088 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Total 294.14 million exceeds face-value amount 163,414,000, implying premium; IPO expenses not listed. No reported/announcements in packet. | 1 | 0 | — | — | — |
| AAMRATECH | 41,094 | 2,012 | 517,728,000 | 128,750,000 | 358,519,000 | 0 | 0 | 30,459,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | AAMRATECH_PROSPECTUS_2012 p.17 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Later reports in packet (2024 annual) only show compliance 5(5)(m) 'Not applicable'; no utilisation statement. | 1 | 0 | — | — | — |
| BSCPLC | — | 2,012 | 1,085,000,000 | 0 | 783,400,000 | 244,600,000 | 0 | 57,000,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | BSCPLC_PROSPECTUS_2012 p.17 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | approximate: prospectus year (eod code history starts later) | No reported docs in packet. | 1 | 0 | — | — | — |
| ENVOYTEX | 41,252 | 2,012 | 900,000,000 | — | — | — | — | — | — | — | — | — | — | — | — | ENVOYTEX_PROSPECTUS_2012 p.20, p.21 | 9 | — | — | 41,526 | 41,455 | — | 0 | Y | 41,394 | stated completion date | ENVOYTEX_ANNUAL_2013 p.37 | completed by deadline | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | completion: 'November 2012 to April 2013' | 0 | 1 | 0 | — | — |
| GBBPOWER | 41,073 | 2,012 | 820,000,000 | 0 | 770,000,000 | 11,399,000 | 0 | 38,601,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | GBBPOWER_PROSPECTUS_2012 p.26 (page image) | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Garbled table; loan amount unreliable. No reported docs. | 1 | 0 | — | — | — |
| GENNEXT | 41,248 | 2,012 | 300,000,000 | 0 | 300,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | GENNEXT_PROSPECTUS_2012 p.20 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs. | 1 | 0 | — | — | — |
| GPHISPAT | 41,018 | 2,012 | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No prospectus pages in packet (0 candidate pages out of 90); reported hits are only compliance checklists (no utilisation statement). Nothing extractable. | 0 | 0 | — | — | — |
| GSPFINANCE | 41,008 | 2,012 | 500,000,000 | 0 | 0 | 0 | 500,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | GSPFINANCE_PROSPECTUS_2012 p.21 | 12 | — | — | 41,373 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Reported hits only mention audit committee declaration item 3.3(x); no utilisation figures. Financial institution. | 1 | 0 | — | — | — |
| PADMALIFE | 41,017 | 2,012 | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Packet has no prospectus pages, no reported hits and no announcements for PADMALIFE_PROSPECTUS_2012. | 0 | 0 | — | — | — |
| SAIHAMCOT | 41,084 | 2,012 | 950,000,000 | 950,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SAIHAMCOT_PROSPECTUS_2012 p.17 | 12 | — | — | 41,449 | 45,838 | — | — | — | — | — | SAIHAMCOT_ANNUAL_2025 p.25 | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | — | 1 | 0 | — | — | — |
| UNIQUEHRL | 41,092 | 2,012 | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | 43,646 | — | — | Y | 42,855 | stated completion date | UNIQUEHRL_ANNUAL_2019 p.109 | completed, timing not measurable | — | 1 | 1 | 0 | EXT 2014-04-08: EGM (with AGM 08.04.2014) to extend time for implementation/utilization schedule of IPO fu [announcement 113677 (2014-03-09)] | CHG 2016-12-22 (15th AGM 22.12.2016 (Extra Ordinary resolution)): Resolution at 15th AGM: purchase about 2,04,494 sft of floor space of the Acropolis projec [announcement 95275] | first DSE trading day in day-end prices | completion: 'fully utilized on 30 April 2017'; No prospectus pages in packet (use-of-proceeds table missing); reported only one-line statement. | 0 | 1 | — | — | — |
| APOLOISPAT | 41,632 | 2,013 | 2,167,646,500 | 636,000,000 | 1,531,646,500 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | APOLOISPAT_PROSPECTUS_2013 p.22, p.26 | 6 | — | — | 41,814 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs in packet. | 1 | 0 | — | — | — |
| ARGONDENIM | 41,324 | 2,013 | 1,050,000,000 | 848,000,000 | 164,000,000 | 0 | 0 | 38,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ARGONDENIM_PROSPECTUS_2012 p.19 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 1 | — | first DSE trading day in day-end prices | No reported utilisation statement docs in packet; auditor emphasis of matter FY2013 only. | 1 | 0 | — | — | — |
| BENGALWTL | 41,380 | 2,013 | 400,000,000 | 194,741,719 | 100,000,000 | 81,704,781 | 0 | 23,553,500 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | BENGALWTL_PROSPECTUS_2013 p.24 | 9 | — | — | 41,655 | 41,547 | 284,515,678 | 115,484,322 | N | — | — | BENGALWTL_PSI_2013 p.13 | unspent, deadline not yet passed at statement | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | — | 1 | 1 | 0 | — | — |
| FAMILYTEX | 41,443 | 2,013 | 340,000,000 | 0 | 332,120,565 | 0 | 0 | 7,879,435 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | FAMILYTEX_PROSPECTUS_2013 p.26 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 1 | 0 | CHG 2013-12-09 (Board proposal; EGM 10.01.2014 and BSEC pending): Board proposed approval of deviation of utilisation of IPO fund between prospectus estimat [announcement 115332] | first DSE trading day in day-end prices | No reported docs in packet. | 1 | 0 | — | — | — |
| FAREASTFIN | 41,534 | 2,013 | 450,000,000 | 0 | 0 | 0 | 450,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | FAREASTFIN_PROSPECTUS_2013 p.30 | 12 | — | — | 41,899 | 43,465 | — | — | Y | 42,004 | report date only | FAREASTFIN_ANNUAL_2018 p.27 | completed, timing not measurable | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | completion: 'completed ... in the year 2014'; Financial institution; no item amounts. | 1 | 1 | — | — | — |
| GHAIL | 41,337 | 2,013 | 750,000,000 | 388,135,297 | 338,478,703 | 0 | 0 | 0 | 0 | 23,386,000 | 0 | 1 | 0 | 0 | 0 | GHAIL_PROSPECTUS_2012 p.30 | 12 | — | — | 41,702 | — | — | — | — | — | — | — | no statement found | — | 1 | 1 | 0 | EXT 2014-10-28: Board decided to hold EGM (15.12.2014) to approve excess IPO expenses, extended time for I [announcement 109239] | CHG 2014-10-28 (EGM 15.12.2014 (proposed)): Proposal for investment of IPO fund in its subsidiary company and excess IPO expenses (det [announcement 109239] | first DSE trading day in day-end prices | No reported docs in packet. Later (2025-2026) announcements are about Rights Share issue proceeds utilisation, not the IPO. | 1 | 0 | — | — | — |
| GHCL | 41,339 | 2,013 | 240,000,000 | 220,455,500 | 0 | 0 | 0 | 19,544,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | GHCL_PROSPECTUS_2012 p.21 | — | — | — | — | — | — | — | Y | — | — | GHCL_ANNUAL_2022 p.26 | completed, timing not measurable | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No amounts in reported hits. | 1 | 1 | — | — | — |
| ORIONPHARM | 41,353 | 2,013 | 2,400,000,000 | 2,306,986,500 | 0 | 0 | 0 | 93,013,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ORIONPHARM_PROSPECTUS_2014 p.20 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Itemised table likely on adjacent page not in packet. No reported/announcements in packet. | 1 | 0 | — | — | — |
| PREMIERCEM | 41,336 | 2,013 | — | — | — | — | — | — | — | — | — | — | — | — | — | PREMIERCEM_PROSPECTUS_2012 p.21 | — | — | — | — | 41,820 | — | — | — | — | — | PREMIERCEM_ANNUAL_2014_4 p.28 | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Promised table is a project fund-requirement table (IPO only pays part of LC value of 4th unit). IPO amount not printed. | 0 | 0 | — | — | — |
| PTL | 41,597 | 2,013 | 840,000,000 | 0 | 730,000,000 | 87,041,781 | 0 | 22,958,219 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | PTL_PROSPECTUS_2013 p.27 | 6 | — | — | 41,778 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported utilisation/announcements in packet. | 1 | 0 | — | — | — |
| SUNLIFEINS | 41,305 | 2,013 | 120,000,000 | 0 | 0 | 0 | 115,066,500 | 4,933,500 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | SUNLIFEINS_PROSPECTUS_2012 p.21 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported utilisation or announcements in packet. | 1 | 0 | — | — | — |
| AFCAGRO | 41,643 | 2,014 | 109,041,500 | 109,041,500 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | AFCAGRO_PROSPECTUS_2013 p.22 | 6 | — | — | 41,824 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs in packet. Total gross IPO 120,000,000. | 1 | 0 | — | — | — |
| EMERALDOIL | 41,643 | 2,014 | 200,000,000 | 0 | 120,000,000 | 65,000,000 | 0 | 15,000,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | EMERALDOIL_PROSPECTUS_2014 p.19 | 4 | — | — | 41,763 | 41,820 | — | 0 | Y | 41,820 | stated completion date | EMERALDOIL_ANNUAL_2014 p.17 | completed after deadline | 2 | 0 | 0 | 0 | — | first DSE trading day in day-end prices | completion: table to 30 Jun 2014 | 1 | 1 | 0 | 2 | — |
| FARCHEM | 41,648 | 2,014 | 120,000,000 | 106,790,553 | 0 | 0 | 0 | 13,209,447 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | FARCHEM_PROSPECTUS_2014 p.27 | 13 | — | — | 42,044 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs in packet. | 1 | 0 | — | — | — |
| FEKDIL | 41,648 | 2,014 | 675,000,000 | 106,549,298 | 540,292,599 | 0 | 0 | 28,158,103 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | FEKDIL_PROSPECTUS_2014 p.25 | 6 | — | — | 41,829 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs. | 1 | 0 | — | — | — |
| HFL | 41,977 | 2,014 | 1,050,000,000 | 722,000,000 | 303,490,000 | 0 | 0 | 24,510,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | HFL_PROSPECTUS_2014 p.22 | 12 | — | — | 42,342 | 43,281 | — | — | Y | — | — | HFL_ANNUAL_2018 p.13; HFL_ANNUAL_2017 p.10 | completed, timing not measurable | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | — | 1 | 1 | — | — | — |
| HWAWELLTEX | 41,645 | 2,014 | 215,000,000 | 200,000,000 | 0 | 0 | 0 | 15,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | HWAWELLTEX_PROSPECTUS_2014 p.21 | — | — | — | — | 45,838 | — | — | Y | 42,308 | stated completion date | HWAWELLTEX_ANNUAL_2025 p.27 | completed, timing not measurable | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | completion: 'fully utilized by October 2015'; Printed prospectus total 215,000,000 vs 'Tk. 20 crore' IPO in annual reports. | 1 | 1 | — | — | — |
| KBPPWBIL | 41,961 | 2,014 | 200,000,000 | 152,051,500 | 19,634,950 | 15,365,050 | 0 | 12,948,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | KBPPWBIL_PROSPECTUS_2014 p.25 | 7 | — | — | 42,173 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Reported hits (annual 2019-2025) only mention audit committee reviewing IPO proceeds utilisation; no statement. | 1 | 0 | — | — | — |
| KPPL | 41,648 | 2,014 | 105,000,000 | 0 | 0 | 87,164,500 | 0 | 17,835,500 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | KPPL_PROSPECTUS_2014 p.20 | 6 | — | — | 41,829 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Reported: later annual reports (2018-2022) only say IPO fund utilization was presented in relevant years; no statement in packet. Auditor qualified opinion on going concern mentioned in FY2021/22 reports (not IPO-specific). | 1 | 0 | — | — | — |
| MATINSPINN | 41,645 | 2,014 | 1,261,700,000 | 1,230,257,270 | 0 | 0 | 0 | 31,442,730 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | MATINSPINN_PROSPECTUS_2014 p.29 | — | — | — | — | 43,281 | — | 0 | Y | 43,281 | report date only | MATINSPINN_ANNUAL_2018 p.55 | completed, timing not measurable | — | 0 | 1 | 1 | CHG 2017-11 (AGM (agenda item 7, FY2017 notice)): AGM agenda: approve utilization of interest income from IPO Fund of Tk. 9,282,690 as Worki [MATINSPINN_ANNUAL_2017 p.8] | first DSE trading day in day-end prices | completion: balance nil at 30 Jun 2018; Announcement 94860 emphasis of matter also covers non-installation of some fixed assets purchased with IPO fund (in CWIP at 30 June 2016). | 1 | 1 | 0 | — | — |
| MHSML | 41,643 | 2,014 | 275,000,000 | 0 | 261,495,000 | 0 | 0 | 13,505,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | MHSML_PROSPECTUS_2013 p.19 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported utilisation/announcements in packet. | 1 | 0 | — | — | — |
| PENINSULA | 41,648 | 2,014 | 1,650,000,000 | 1,480,526,766 | 132,973,234 | 0 | 0 | 36,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | PENINSULA_PROSPECTUS_2014 p.19 (page image) | — | — | — | — | 45,838 | — | — | Y | 45,260 | stated completion date | PENINSULA_ANNUAL_2025 p.24; PENINSULA_ANNUAL_2023 p.22 | completed, timing not measurable | — | 0 | 5 | 0 | CHG 2015-03-02 (EGM (2 Mar 2015; board decision)): EGM to change mode of utilization of IPO proceeds and implementation schedule [announcement 107672] | CHG 2016-12-04 (EGM 4 Dec 2016 (board decision; subject to shareholder approval)): EGM/AGM to change mode of utilization of IPO proceeds and implementation schedule [announcement 96832] | CHG 2018-10-30 (EGM 30 Oct 2018 (board decision)): EGM to change mode of utilization of IPO proceeds and its implementation schedule [announcement 82117] | CHG 2020-12-14 (EGM 14 Dec 2020 (board decision)): 8th EGM called for changes in the mode of utilization of IPO proceeds and its implementati [announcement 172354] | CHG 2022-06-23 (EGM 23 Jun 2022 (board decision)): EGM for approval of changes in the mode of utilization of IPO Proceeds and its implementat [announcement 63076] | first DSE trading day in day-end prices | completion: fully utilised as on 30 Nov 2023; Prospectus table garbled; repeated board/EGM decisions to change use and schedule (outcomes/approval not in packet). | 1 | 1 | — | — | — |
| RSRMSTEEL | 41,649 | 2,014 | 1,000,000,000 | 0 | 750,000,000 | 230,000,000 | 0 | 20,000,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | RSRMSTEEL_PROSPECTUS_2014 p.23 | 3 | — | — | 41,739 | 44,377 | — | 0 | Y | 44,012 | report date only | RSRMSTEEL_ANNUAL_2021 p.35 | completed, timing not measurable | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | completion: same statement in FY2020 report | 1 | 1 | 0 | — | — |
| SAIFPOWER | 41,649 | 2,014 | 360,000,000 | 280,752,465 | 0 | 66,163,215 | 0 | 13,084,320 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SAIFPOWER_PROSPECTUS_2014 p.16-17 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Only FY2017 audit-committee boilerplate in reported hits; no utilisation statement or announcements in packet. | 1 | 0 | — | — | — |
| SHURWID | 41,649 | 2,014 | 140,000,000 | 85,798,334 | 43,768,166 | 0 | 0 | 10,433,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SHURWID_PROSPECTUS_2014 pp.17-18 (page image) | 12 | — | — | 42,014 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Prospectus table incomplete/scrambled; no reported/announcements in packet. | 1 | 0 | — | — | — |
| SPCL | 41,681 | 2,014 | 317,000,000 | 0 | 317,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | SPCL_PROSPECTUS_2014 p.15 | 1 | — | — | 41,709 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported utilisation or announcements in packet. | 1 | 0 | — | — | — |
| TUNGHAI | 41,648 | 2,014 | 350,000,000 | 115,500,000 | 160,000,000 | 53,690,000 | 0 | 20,810,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | TUNGHAI_PROSPECTUS_2014 p.22 | 6 | — | — | 41,829 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported utilisation or announcements in packet. | 1 | 0 | — | — | — |
| AMANFEED | 42,248 | 2,015 | 720,000,000 | 350,000,000 | 50,538,633 | 299,176,867 | 0 | 20,284,500 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | AMANFEED_PROSPECTUS_2015 p.24 | — | — | — | — | — | — | — | N | — | — | AMANFEED_ANNUAL_2016 p.66 | unspent, deadline not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | No utilisation figures in packet hits. | 1 | 1 | — | — | — |
| BSRMLTD | 42,121 | 2,015 | 612,500,000 | 387,510,000 | 204,000,000 | 0 | 0 | 20,990,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | BSRMLTD_PROSPECTUS_2015 p.23 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported doc BSRMLTD_ANNUAL_2017 p.53 only lists heading 'Use of IPO Proceeds & Stages of Utilization' without numbers in the hit. | 1 | 0 | — | — | — |
| CNATEX | 42,025 | 2,015 | 450,000,000 | 123,147,996 | 308,762,254 | 0 | 0 | 18,089,750 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | CNATEX_PROSPECTUS_2015 p.24 | 18 | — | — | 42,572 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported hit (annual 2016 p.14) is unrelated risk text; no utilisation statement. | 1 | 0 | — | — | — |
| IFADAUTOS | 42,040 | 2,015 | 637,500,000 | 506,780,031 | 93,283,969 | 0 | 0 | 37,436,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | IFADAUTOS_PROSPECTUS_2015 p.25 | 12 | — | — | 42,405 | 42,916 | — | — | Y | 42,916 | stated completion date | IFADAUTOS_ANNUAL_2017 p.37; IFADAUTOS_ANNUAL_2016 p.38 | completed after deadline | 17 | 1 | 1 | 0 | EXT 2015-12-07: Extension of time period of utilisation of IPO proceeds approved with the re-allotment (wi [IFADAUTOS_ANNUAL_2016 p.38] | CHG 2015-12-07 (AGM (27th, 7 Dec 2015)): Re-allotment of IPO proceeds among Land Development, Building & Structure (Body Fabricatio [IFADAUTOS_ANNUAL_2016 p.38] | ipo_stats.csv listing_date | completion: FY2017: 'fully completed'; Revised-plan table is column-misaligned in OCR; revised amounts approximate. | 1 | 1 | — | 17 | — |
| KDSALTD | 42,292 | 2,015 | 240,000,000 | 150,000,000 | 70,000,000 | 0 | 0 | 20,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | KDSALTD_PROSPECTUS_2015 p.24 | — | — | — | — | 42,916 | — | — | Y | 42,621 | stated completion date | KDSALTD_ANNUAL_2017_DUP6594 p.6 | completed, timing not measurable | — | 0 | 1 | 0 | CHG 2016-09-01 (AGM (25th, 1 Sep 2016)): Remaining IPO account balance Tk 5,266,533 used to pay off bank liabilities (to reduce fin [KDSALTD_ANNUAL_2017_DUP6594 p.6] | ipo_stats.csv listing_date | completion: balance used 08 Sep 2016 | 1 | 1 | — | — | — |
| NFML | 42,023 | 2,015 | 180,000,000 | 81,790,000 | 71,262,811 | 9,408,689 | 0 | 17,538,500 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NFML_PROSPECTUS_2015 p.24 | — | — | — | — | 42,551 | — | 0 | Y | 42,551 | stated completion date | NFML_ANNUAL_2016 p.12; NFML_ANNUAL_2024_7 p.28 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 100% at 30 Jun 2016 | 1 | 1 | 0 | — | — |
| OAL | 42,180 | 2,015 | 200,000,000 | 185,500,000 | 0 | 0 | 0 | 14,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | OAL_PROSPECTUS_2015 p.25 | 18 | — | — | 42,729 | 42,643 | — | 0 | Y | 42,643 | stated completion date | OAL_ANNUAL_2016 p.13; OAL_ANNUAL_2017 p.13 | completed by deadline | — | 0 | 1 | 0 | CHG None (12th AGM): Revised allocation: construction of building Tk 154.28 million, machinery & equipment Tk 3 [OAL_ANNUAL_2016 p.13] | ipo_stats.csv listing_date | completion: fully utilised by 30 Sep 2016 | 1 | 1 | 0 | — | — |
| REGENTTEX | 42,352 | 2,015 | 1,250,000,000 | 1,223,183,482 | 0 | 0 | 0 | 26,816,518 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | REGENTTEX_PROSPECTUS_2015 p.20 | 18 | — | — | 42,900 | 44,012 | — | 0 | Y | 44,377 | report date only | REGENTTEX_ANNUAL_2020 p.58 (Annexure-M) | completed after deadline | 48 | 4 | 0 | 0 | EXT 2017-11-01: Board decided special resolution to extend IPO fund utilization time for BMRE up to Octobe [announcement 88705] | EXT 2018-11-04: Board decided special resolution to extend IPO fund utilization time up to June 2019 with [announcement 80416] | EXT 2019-07-02: Board decided EGM (29.08.2019) to revise and extend IPO proceeds utilization time up to De [announcement 181626] | EXT 2020-07-12: Board decided EGM (27.08.2020) special resolution to revise and extend IPO proceeds utiliz [announcement 174665] | ipo_stats.csv listing_date | completion: FY2021 report: fund utilised; Extensions are board decisions put to EGM; shareholder/BSEC approval outcomes not in packet. | 1 | 1 | 0 | 48 | — |
| SHASHADNIM | 42,068 | 2,015 | 1,750,000,000 | 1,540,000,000 | 182,290,000 | 0 | 0 | 27,710,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SHASHADNIM_PROSPECTUS_2015 p.23 | — | — | — | — | 45,838 | — | — | Y | — | — | SHASHADNIM_ANNUAL_2025 p.98 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported utilisation is a one-line compliance remark; no extensions/changes in packet. | 1 | 1 | — | — | — |
| SIMTEX | 42,331 | 2,015 | 600,000,000 | 316,229,000 | 200,000,000 | 65,271,000 | 0 | 18,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SIMTEX_PROSPECTUS_2015 p.26 | 12 | — | — | 42,697 | 43,281 | — | — | Y | 43,281 | stated completion date | SIMTEX_ANNUAL_2019 p.33; SIMTEX_ANNUAL_2018 p.13 | completed after deadline | 19 | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'utilized within 30.06.2018' | 1 | 1 | — | 19 | — |
| TOSRIFA | 42,172 | 2,015 | 638,721,200 | 598,999,481 | 0 | 0 | 0 | 19,931,719 | 19,790,000 | 0 | 0 | 1 | 0 | 0 | 0 | TOSRIFA_PROSPECTUS_2015 p.28 | — | — | — | — | 42,674 | — | 0 | Y | 43,010 | stated completion date | TOSRIFA_ANNUAL_2016_2 p.33 | completed, timing not measurable | — | 0 | 1 | 0 | CHG None (14th AGM): Utilisation by proper expense heads as per 14th AGM approved agenda (details not in packet [announcement 89902 / TOSRIFA_PSI_2017 p.1] | ipo_stats.csv listing_date | completion: board 2 Oct 2017: 'already utilized'; Total utilised figure stale (Oct 2016); full utilisation by Oct 2017 stated by company. | 1 | 1 | 0 | — | — |
| UPGDCL | 42,099 | 2,015 | 2,376,000,000 | 0 | 792,000,000 | 27,908,238 | 0 | 66,091,762 | 1,490,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | UPGDCL_PROSPECTUS_2014 p.28 | 3 | — | — | 42,190 | 42,551 | 2,044,922,352 | 331,077,648 | N | — | — | UPGDCL_ANNUAL_2016_2 p.43 | unspent after deadline | 12 | 0 | 1 | 0 | CHG 2016-12 (AGM special resolution (notice in FY2016 annual report, special business item 5)): Special resolution: unutilised IPO proceeds of Tk 331,077,648 to be used for financing wor [UPGDCL_ANNUAL_2016_2 p.93] | ipo_stats.csv listing_date | AGM resolution outcome/BSEC approval not in packet. | 1 | 1 | 0 | — | 12 |
| ACMELAB | 42,528 | 2,016 | 4,312,800,000 | 4,244,500,000 | 0 | 0 | 0 | 68,300,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ACMELAB_PROSPECTUS_2016 p.270 | 24 | — | — | 43,258 | 45,107 | — | — | Y | 44,592 | stated completion date | ACMELAB_ANNUAL_2023_2 p.52, p.63 | completed after deadline | 44 | 1 | 1 | 0 | EXT None: 46th AGM approved API project completion within June 2024 (originally June 2022) [ACMELAB_ANNUAL_2023_2 p.63] | CHG None (AGM (44th)): BDT 606,132,545 of IPO proceeds allocated only for civil construction of Active Pharmaceut [ACMELAB_ANNUAL_2023_2 p.63] | ipo_stats.csv listing_date | completion: 'entire fund duly utilized within January 2022'; Prospectus use-of-proceeds is for three pharma projects; later reallocated to API park per annual report. Item-level utilisation not extracted. | 1 | 1 | — | 44 | — |
| BNICL | 42,481 | 2,016 | 177,000,000 | 0 | 0 | 0 | 172,466,000 | 4,534,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | BNICL_PROSPECTUS_2016 p.22 | 3 | — | — | 42,572 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Prospectus identical for BNICL and BNIPLC (same document, duplicate key; ticker likely renamed). No reported docs in packet. Insurance company. | 1 | 0 | — | — | — |
| DOREENPWR | 42,466 | 2,016 | 558,980,000 | — | — | — | — | — | — | — | — | — | — | — | — | DOREENPWR_PROSPECTUS_2016 p.25, p.27 (also DOREENPWR_DOC_2024 p.25) | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Head-wise table not in packet pages; reported hits are the same prospectus text found in DOREENPWR_DOC_2024 (not utilisation statements). 9 PSI/annual docs listed but no statements extracted. | 0 | 0 | — | — | — |
| DSSL | 42,452 | 2,016 | 400,000,000 | — | — | — | — | — | — | — | — | — | — | — | — | DSSL_PROSPECTUS_2016 p.23, p.26 | 11 | — | — | 42,789 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 1 | — | ipo_stats.csv listing_date | Head-wise amounts missing from packet; no reported docs. Page-image check of prospectus pp.24-25 recommended. | 0 | 0 | — | — | — |
| ETL | 42,568 | 2,016 | 170,000,000 | 139,871,846 | 0 | 15,427,654 | 0 | 14,700,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ETL_PROSPECTUS_2016 p.137, p.143 | 18 | — | — | 43,117 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported hits (ETL annual 2017/2018) are unrelated notes; no utilisation statement. | 1 | 0 | — | — | — |
| FORTUNE | 42,663 | 2,016 | 220,000,000 | 202,340,000 | 0 | 0 | 0 | 17,660,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | FORTUNE_PROSPECTUS_2016 p.139 | 18 | — | — | 43,210 | 43,281 | — | — | Y | 43,281 | stated completion date | FORTUNE_ANNUAL_2018 p.13, p.62 | completed after deadline | 2 | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'completed in 2018'; reports till 30 Jun 2018; Reported amounts garbled; page-image check of FORTUNE_ANNUAL_2018 p.62 if figures needed. | 1 | 1 | — | 2 | — |
| ITC | 42,379 | 2,016 | 120,000,000 | 69,538,250 | 40,000,000 | 0 | 0 | 10,461,750 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ITC_PROSPECTUS_2016 p.25 | — | — | — | — | 45,838 | — | — | Y | — | — | ITC_ANNUAL_2025 p.87 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | — | 1 | 1 | — | — | — |
| AAMRANET | 43,010 | 2,017 | 562,500,000 | 346,874,345 | 185,921,482 | 0 | 0 | 29,704,173 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | AAMRANET_PROSPECTUS_2017 p.170 (text; image font unreadable) | 12 | — | — | 43,375 | 43,008 | — | — | — | — | — | AAMRANET_ANNUAL_2017 p.34 | no statement found | — | 0 | 2 | 0 | CHG 2018-10-24 (Board (AGM/BSEC pending)): Board decided to freeze unutilised Tk 3,952,298 (Tk 1,512,298 saved in BMRE/Data Center/Wi [announcement 80953] | CHG 2019-02-12 (BSEC): BSEC approved transfer of unutilised Tk 3,952,298 of IPO proceeds to head 'BMRE for infras [announcement 184184] | ipo_stats.csv listing_date | Digit-dropped OCR in proceeds table; reported statement is only the first-month (Sep 2017) one in packet. | 1 | 0 | — | — | — |
| BBSCABLES | 42,947 | 2,017 | 200,000,000 | 142,610,000 | 40,000,000 | 0 | 0 | 0 | 0 | 17,390,000 | 0 | 1 | 0 | 0 | 0 | BBSCABLES_PROSPECTUS_2017 p.160 | — | — | — | — | — | — | — | Y | — | — | BBSCABLES_ANNUAL_2024_3 p.44 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | — | 1 | 1 | — | — | — |
| NAHEEACP | 43,093 | 2,017 | 150,000,000 | 97,762,000 | 40,000,000 | 0 | 0 | 12,238,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | NAHEEACP_PROSPECTUS_2017 p.165 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported: FY2017 annual says IPO allotment 23 Oct 2017, fund not utilised at 30 Jun 2017; FY2024/2025 reports say no IPO fund for utilisation during the year. No utilisation statement in packet. Announcement 185104 (2019-01-14): company says it raised Tk 15.00 crore in 2017 for term loan repayment, | 1 | 0 | — | — | — |
| NURANI | 42,887 | 2,017 | 430,000,000 | 293,345,000 | 118,000,000 | 0 | 0 | 18,655,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | NURANI_PROSPECTUS_2017 p.147 (printed page 128) | — | — | — | — | 43,404 | — | — | Y | 43,404 | stated completion date | NURANI_ANNUAL_2020 p.12 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: by 31 Oct 2018 | 1 | 1 | — | — | — |
| OIMEX | 43,045 | 2,017 | 150,000,000 | 85,000,000 | 50,000,000 | 0 | 0 | 15,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | OIMEX_PROSPECTUS_2017 p.111 | 6 | — | — | 43,226 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported: FY2018/2019 annual reports only say IPO fund was utilised ("after proper utilization of IPO fund"); no numbers/dates in packet. | 1 | 0 | — | — | — |
| PDL | 42,773 | 2,017 | 750,000,000 | 479,380,000 | 250,000,000 | 0 | 0 | 20,620,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | PDL_ANNUAL_2017 p.57 (prospectus table not in packet) | — | — | — | — | 44,012 | — | 0 | Y | 44,012 | stated completion date | PDL_ANNUAL_2020 p.26 | completed, timing not measurable | — | 0 | 0 | 1 | — | ipo_stats.csv listing_date | completion: utilised up to 30 Jun 2020 per auditor; Machinery vs building split differs from prospectus-based promised (utilised 200,178,553 machinery vs 181,006,277; building 279,201,447 vs 298,373,723): possible reallocation, no approval documented in packet. | 1 | 1 | 0 | — | — |
| SHEPHERD | 42,802 | 2,017 | 200,000,000 | 140,535,766 | 44,464,234 | 0 | 0 | 15,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SHEPHERD_PROSPECTUS_2017 p.161 | 18 | — | — | 43,351 | 43,524 | 199,740,000 | 260,000 | N | — | — | SHEPHERD_DOC_2019_2 p.1,3 (auditor report Ahmed Zaker & Co.) | unspent after deadline | 6 | 1 | 1 | 1 | EXT 2018-12-19: 17th AGM approved revised IPO utilization plan with full-utilisation deadline extended to [SHEPHERD_DOC_2019_3 p.2; DOC_2019_2 p.3] | CHG 2017-11-07 (Board proposal; shareholders in general meeting (17th AGM 19 Dec 2018) and BSEC): Board proposed revised use of unutilised IPO funds Tk 114,576,375 (building 28,140,524; ET [announcement 88526] | ipo_stats.csv listing_date | 65 reported hits (monthly auditor reports); latest in packet is Feb 2019 statement. | 1 | 1 | 0 | — | 6 |
| ACFL | 43,318 | 2,018 | 800,000,000 | 663,375,000 | 101,625,000 | 0 | 0 | 35,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ACFL_PROSPECTUS_2018 p.173 | 6 | — | — | 43,502 | 45,838 | — | 717,498,337 | N | — | — | ACFL_ANNUAL_2025 p.66 | unspent after deadline | 77 | 3 | 0 | 2 | EXT 2021-11-16: Shareholders approved revised timeline for utilisation of IPO proceeds up to 31 August 202 [announcement 168401 / 55869] | EXT None: Shareholders approved extension of time for utilisation of unutilised fund to AGM of 2028 [ACFL_ANNUAL_2025 p.63] | EXT 2025-06-30: Shareholders approved revised timeline for fund utilisation up to 31 December 2028 [ACFL_ANNUAL_2025 p.66] | ipo_stats.csv listing_date | Earlier extension chain (to Aug 2023, then to Dec 2028) from announcements; qualified opinion on FDR pledge from IPO proceeds. | 1 | 1 | 1 | — | 77 |
| ADVENT | 43,202 | 2,018 | 200,000,000 | 181,500,000 | 0 | 0 | 0 | 18,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ADVENT_ANNUAL_2021 p.18 (as per prospectus; prospectus p.189 has only the schedule) | 18 | — | — | 43,750 | 44,377 | — | 0 | Y | 44,012 | stated completion date | ADVENT_ANNUAL_2021 p.18, p.77 | completed after deadline | 9 | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: utilised in full up to 30 Jun 2020 per auditor | 1 | 1 | 0 | 9 | — |
| BPML | 43,283 | 2,018 | 2,000,000,000 | 1,350,000,000 | 600,000,000 | 0 | 0 | 50,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | BPML_ANNUAL_2019 p.34 (schedule as in Prospectus dated 01/04/2018 p.211; prospectus page not in packet) | 24 | — | — | 44,014 | 43,343 | — | 0 | Y | 43,343 | stated completion date | BPML_ANNUAL_2019 p.34; BPML_PSI_2019 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 100% by August 2018 | 1 | 1 | 0 | — | — |
| IBP | 43,391 | 2,018 | 200,000,000 | 183,300,000 | 0 | 0 | 0 | 16,700,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | IBP_PROSPECTUS_2018 p.173 | 24 | — | — | 44,122 | 44,012 | — | 0 | Y | 44,012 | stated completion date | IBP_ANNUAL_2020 p.39, p.90 | completed by deadline | — | 1 | 1 | 0 | EXT None: Fund utilisation period for construction and other civil works extended from 18 to 24 mont [IBP_ANNUAL_2020 p.39] | CHG 2020-01-06 (AGM (5th)): Proposal at 5th AGM to use Tk 58,580,000 of IPO proceeds to purchase machineries instead o [announcement 177127] | ipo_stats.csv listing_date | completion: 'fully utilized ... up to June 30, 2020' | 1 | 1 | 0 | — | — |
| INTRACO | 43,237 | 2,018 | 300,000,000 | 279,600,000 | 0 | 0 | 0 | 20,400,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | INTRACO_PROSPECTUS_2018 p.198 (item amounts from INTRACO_DOC_2020 p.21 'as per prospectus') | — | — | — | — | 44,104 | 341,759,160 | — | — | — | — | INTRACO_DOC_2020 p.21 | no statement found | — | 0 | 2 | 1 | CHG 2018-10-29 (Board; AGM 23.12.2018): Change of project location: LPG bottling plant at Patenga, Chittagong instead of Gojaria, [announcement 80648] | CHG 2019-10-28 (AGM (12th, 24.12.2019)): Board changed earlier decision (Patenga bottling plant) and decided to purchase a newly bu [announcement 179185] | ipo_stats.csv listing_date | Many INTRACO docs; later (2021+) utilisation statement not in packet hits. Prospectus head-wise table page not in packet pages. | 1 | 0 | — | — | — |
| KTL | 43,416 | 2,018 | 340,000,000 | 295,876,000 | 25,000,000 | 0 | 0 | 19,124,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | KTL_PROSPECTUS_2018 p.141 | 24 | — | — | 44,147 | 44,377 | 126,063,875 | 213,936,125 | N | — | — | KTL_ANNUAL_2021 p.15 | unspent after deadline | 8 | 1 | 0 | 1 | EXT 2021-11-23: Board decided to apply to BSEC for time extension of IPO fund utilization; shareholder app [announcement 69072] | ipo_stats.csv listing_date | — | 1 | 1 | 1 | — | 8 |
| MLDYEING | 43,360 | 2,018 | 200,000,000 | 178,300,000 | 0 | 0 | 0 | 21,700,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | MLDYEING_PROSPECTUS_2018 p.173 (printed page 158) | — | — | — | — | 45,838 | — | 0 | Y | 44,194 | stated completion date | MLDYEING_ANNUAL_2025 p.23 | completed, timing not measurable | — | 0 | 1 | 1 | CHG None (AGM (18th)): Revised utilization of IPO fund approved at 18th AGM (details not in packet) [announcement 77526] | ipo_stats.csv listing_date | completion: DSE post 29 Dec 2020: rest utilised; Announcement amounts (69,602,488 / 130,397,512) differ slightly from annual report (69,587,488 / 130,412,512) due to LC refund treatment. | 1 | 1 | 0 | — | — |
| QUEENSOUTH | 43,172 | 2,018 | 150,000,000 | 130,656,084 | 6,343,916 | 0 | 0 | 13,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | QUEENSOUTH_PROSPECTUS_2018 p.193 | 12 | — | — | 43,537 | 43,890 | 69,371,787 | 80,628,213 | N | — | — | QUEENSOUTH_DOC_2020_4 p.1,2 and DOC_2020_3 p.3 | unspent after deadline | 12 | 2 | 1 | 2 | EXT 2018-12-27: Time frame for utilization of IPO proceeds extended (1st time) up to 31 October 2019 [QUEENSOUTH_DOC_2020_4 p.2 (16th AGM 27 Dec 2018)] | EXT 2019-12-22: Time frame extended (2nd time) up to 30 June 2020 [QUEENSOUTH_DOC_2020_4 p.2 (17th AGM)] | CHG 2019-12-22 (17th AGM 22 Dec 2019; BSEC approval pending per auditor): Revised IPO utilization plan: purchased natural gas engine generator set instead of 1 set [announcements 174349, 179108; QUEENSOUTH_DOC_2020_4 p.2] | ipo_stats.csv listing_date | — | 1 | 1 | 1 | — | 12 |
| SILVAPHL | 43,383 | 2,018 | 300,000,000 | 178,500,000 | 99,000,000 | 0 | 0 | 22,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SILVAPHL_PROSPECTUS_2018 p.235 (printed page 218) | — | — | — | — | 45,838 | 271,817,362 | 28,182,638 | N | — | — | SILVAPHL_ANNUAL_2025 p.44,45 | unspent, deadline not measurable | — | 3 | 2 | 0 | EXT 2022-12-29: 21st AGM approved extension of IPO proceeds utilization up to December 31, 2023 (reason CO [announcement 54139] | EXT 2023-12-28: Board (13 Nov 2023) decided to extend utilization time up to December 31, 2024, subject to [announcements 41982, 41981] | EXT 2024-12: 23rd AGM extended time for utilization of IPO proceeds up to December 31, 2025 [announcement 27383 (2025-01-01)] | CHG 2025-11-16 (EGM 30.12.2025 and BSEC (proposed)): Board decisions subject to EGM 30.12.2025 and BSEC: change of company name, post-facto app [announcement 16471; SILVAPHL_ANNUAL_2025 p.45] | CHG None (18th AGM): Revised estimated amounts per 18th AGM: civil construction 58,058,526; IPO expenses 20,441 [SILVAPHL_ANNUAL_2025 p.44] | ipo_stats.csv listing_date | Company later renamed (EGM 30.12.2025). | 1 | 1 | 0 | — | — |
| SKTRIMS | 43,296 | 2,018 | 300,000,000 | 276,180,000 | 0 | 0 | 0 | 23,820,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SKTRIMS_PROSPECTUS_2018 p.200 (printed page 183) | 18 | 44,087 | Y | 44,087 | 44,012 | 147,889,570 | 152,110,430 | N | — | — | SKTRIMS_ANNUAL_2020 p.20,50 | unspent after deadline | — | 2 | 1 | 1 | EXT 2019-12-29: First revision at 5th AGM: last date reset from December 13, 2019 to September 13, 2020 (2 [SKTRIMS_ANNUAL_2020 p.51] | EXT 2020-09-13: Board decided to extend IPO fund utilization period up to 30 June 2021 (deadline of 13 Sep [SKTRIMS_ANNUAL_2020 p.20] | CHG 2020-11-30 (Board; subject to AGM approval): Tk. 127,267,972 under Acquisition of machineries and equipment to be used for capital mach [announcement 77658; SKTRIMS_ANNUAL_2020 p.20] | ipo_stats.csv listing_date | printed deadline: SKTRIMS_ANNUAL_2020 pp.20, 50; deadline missed per auditor: SKTRIMS_ANNUAL_2020 p.50 | 1 | 1 | 1 | — | — |
| VFSTDL | 43,352 | 2,018 | 220,000,000 | 177,403,108 | 25,092,728 | 0 | 0 | 17,504,164 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | VFSTDL_PROSPECTUS_2018 p.146 (printed page 130) and p.154 | 18 | — | — | 43,899 | 45,838 | — | 0 | Y | 43,465 | stated completion date | VFSTDL_ANNUAL_2025 p.19 (same in FY2018-FY2024 reports) | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'started and completed in 2018' | 1 | 1 | 0 | — | — |
| COPPERTECH | 43,682 | 2,019 | 200,000,000 | 120,000,000 | 65,000,000 | 0 | 0 | 0 | 0 | 15,000,000 | 0 | 1 | 0 | 0 | 0 | COPPERTECH_PROSPECTUS_2019 p.110 | 12 | — | — | 44,048 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported hits (2021-2025 annuals) only show compliance checklist 5(5)(m) 'Not applicable'; no utilisation statement. | 1 | 0 | — | — | — |
| ESQUIRENIT | 43,564 | 2,019 | 1,500,000,000 | 1,435,611,500 | 0 | 0 | 0 | 64,388,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ESQUIRENIT_PROSPECTUS_2019 p.249, p.227 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 1 | 0 | 0 | EXT 2020-07-30: Board decided EGM (14.09.2020) to enhance IPO fund utilisation schedule time and amend fun [announcement 174121] | ipo_stats.csv listing_date | Annual report utilisation statement not in packet hits. | 1 | 0 | — | — | — |
| GENEXIL | 43,502 | 2,019 | 200,000,000 | 123,000,000 | 60,000,000 | 0 | 0 | 17,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | GENEXIL_PROSPECTUS_2019 p.181 | — | — | — | — | 44,012 | — | — | Y | 43,646 | report date only | GENEXIL_ANNUAL_2020 p.56; GENEXIL_ANNUAL_2019 p.57 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'fully utilized in the previous year' (FY2019) | 1 | 1 | — | — | — |
| NEWLINE | 43,612 | 2,019 | 300,000,000 | 194,065,650 | 90,000,000 | 0 | 0 | 15,934,350 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | NEWLINE_PROSPECTUS_2019 p.159 | — | — | — | — | 44,377 | 208,672,547 | 91,327,453 | N | — | — | NEWLINE_ANNUAL_2021 p.27 | unspent, deadline not measurable | — | 0 | 1 | 0 | CHG 2019-12-10 (AGM 30 Dec 2019 and BSEC letter BSEC/CFD/95/2020/64 dated July 05, 2020): Revised IPO utilization plan (details not in packet); board 10 Dec 2019, shareholders appr [NEWLINE_ANNUAL_2021 p.26] | ipo_stats.csv listing_date | Delays attributed by company to Covid lockdowns. | 1 | 1 | 0 | — | — |
| RINGSHINE | 43,811 | 2,019 | 1,500,000,000 | 964,000,000 | 500,000,000 | 0 | 0 | 36,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | RINGSHINE_PROSPECTUS_2019 p.275 (printed page 260) | — | 44,291 | — | 44,291 | 45,473 | 1,219,397,757 | 280,602,243 | N | — | — | RINGSHINE_DOC_2024_12 p.2,3,5 (auditor yearly certificate Jul 2023-Jun 2024) | unspent after deadline | 39 | 1 | 4 | 2 | EXT 2024-12-18: 27th AGM accorded extension of time of 1 more year for utilizing the IPO fund from date of [RINGSHINE_DOC_2024_8 p.1] | CHG 2021-05-20 (BSEC (letter 20 May 2021); AGM post-facto approval): BSEC approved withdrawal of BDT 40 crore of IPO proceeds from BRAC Bank PLC for amended pu [announcement 74783; RINGSHINE_DOC_2024_7 p.1; RINGSHINE_DOC_2024_12 p.3] | CHG 2023-04-18 (BSEC letter BSEC/SRMIC/153/2019/108 to BRAC Bank PLC dated April 18, 2023): BSEC allowed withdrawal of BDT 18.40 crore of remaining IPO fund (fourth approval) [RINGSHINE_DOC_2024_12 p.3] | CHG 2024-12-18 (27th AGM 18 Dec 2024): AGM approved changed/amended purposes for withdrawing USD 3.6 Million from BRAC Bank PLC w [RINGSHINE_DOC_2024_8 p.1] | CHG 2025-07-20 (BSEC (rejection)): BSEC rejected the application for releasing IPO fund of USD 1.00 Million [announcement 21162] | ipo_stats.csv listing_date | printed deadline: RINGSHINE_DOC_2024_12 p.3; Large packet (74 hits). Latest statement used is the Jul 2023-Jun 2024 yearly certificate; later quarterly reports not examined in detail. One point: the auditor wording says the company failed to provide copy of an application/approval letter for one approval. | 1 | 1 | 0 | — | 39 |
| RUNNERAUTO | 43,606 | 2,019 | 1,000,000,000 | 630,000,000 | 330,000,000 | 0 | 0 | 40,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | RUNNERAUTO_PROSPECTUS_2019 p.212 | — | — | — | — | 44,012 | — | — | — | — | — | RUNNERAUTO_ANNUAL_2020 p.86; RUNNERAUTO_ANNUAL_2019 p.139 | no statement found | — | 1 | 1 | 1 | EXT 2021-11-11: Board (163rd meeting) decided to extend time for utilization of IPO proceeds up to Decembe [announcement 70134] | CHG 2019-12-17 (Board 28 Oct 2019; 6th EGM 17 Dec 2019; BSEC approval 24 Feb 2020): Revised use of IPO proceeds BDT 63 crore (chassis welding line 12.18 crore, body welding l [announcements 179111, 176047, 173284] | ipo_stats.csv listing_date | Promised table amounts (330m loan + 40m expenses + 630m expansion) consistent with auditors. Conversion: 63 crore = 630,000,000. | 1 | 0 | — | — | — |
| SEAPEARL | 43,662 | 2,019 | 150,000,000 | 133,487,300 | 0 | 0 | 0 | 16,512,700 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SEAPEARL_PROSPECTUS_2019 p.187 | — | — | — | — | 44,027 | — | 0 | Y | 44,027 | stated completion date | SEAPEARL_ANNUAL_2021 p.37,133; SEAPEARL_ANNUAL_2022 p.41 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: completed by 15 Jul 2020 | 1 | 1 | 0 | — | — |
| SILCOPHL | 43,629 | 2,019 | 300,000,000 | 278,321,552 | 0 | 0 | 0 | 21,678,448 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SILCOPHL_PROSPECTUS_2019 p.178 (printed page 165) | 20 | — | — | 44,240 | 44,377 | — | 0 | Y | 44,196 | stated completion date | SILCOPHL_ANNUAL_2021 p.18 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'completed in the year of 2020'; Inconsistency: FY2020 says utilisation completed in 2020 but only 60.9m utilised at 30 Jun 2020; FY2021 says full 300m utilised by 30 Jun 2021; FY2022 says nearly completed. | 1 | 1 | 0 | — | — |
| SSSTEEL | 43,482 | 2,019 | 250,000,000 | 229,432,500 | 0 | 0 | 0 | 20,567,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SSSTEEL_PROSPECTUS_2018 p.240 | — | — | — | — | 44,592 | 71,627,824 | 178,372,176 | N | — | — | SSSTEEL_DOC_2022_14 p.4,5 (auditor Shiraz Khan Basak & Co, 17 Feb 2022); Feb 2022 certificate SSSTEEL_DOC_2022_15 p.4 shows same IPO expenses and building figures | unspent, deadline not measurable | — | 2 | 1 | 0 | EXT 2020-09-06: Board proposed extension of IPO proceeds utilization/implementation schedule up to April 2 [announcement 173458] | EXT 2021-06-20: Board resolution extended utilization time to October 2021 (per auditor) [SSSTEEL_DOC_2022_14 p.5] | CHG 2022-07-12 (EGM proposed 3 Sep 2022): Board decided EGM (03.09.2022) for proposed revision of utilization plan of unutilized IPO [announcement 61535] | ipo_stats.csv listing_date | Packet for SSSTEEL_PROSPECTUS_2018 and SSSTEEL_PROSPECTUS_2019 are identical (95 reported hits); unutilised funds remained large at Feb 2022, later annual reports (FY2022-2024) not examined in detail. | 1 | 1 | 1 | — | — |
| ADNTEL | 43,836 | 2,020 | 570,000,000 | 419,896,627 | 120,603,373 | 0 | 0 | 29,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ADNTEL_PROSPECTUS_2019 p.209 | 12 | — | — | 44,202 | 44,742 | 385,036,911 | 184,963,089 | N | — | — | ADNTEL_ANNUAL_2022 p.8, p.42 | unspent after deadline | 18 | 3 | 1 | 0 | EXT 2020-10-28: Board decided to hold EGM to extend IPO fund utilisation timeline (EGM/AGM 24.12.2020) [announcement 172276] | EXT 2021-04-13: BSEC approved alteration of use and time extension: Data Center balance BDT 32,632,813 ext [announcement 75795; ADNTEL_ANNUAL_2022 p.42] | EXT 2022-12-07: 19th AGM approved extension of BMRE-related unutilised IPO proceeds to 31 December 2023 [announcements 54756/54757] | CHG 2022-12-07 (AGM (19th, 7 Dec 2022), subject to BSEC): Unutilised BMRE allocation rearranged from BDT 184,963,089 to BDT 84,963,089; of remaining [announcements 54757, 54756, 57381] | ipo_stats.csv listing_date | — | 1 | 1 | 0 | — | 18 |
| AOL | 44,129 | 2,020 | 150,000,000 | 110,556,500 | 20,000,000 | 0 | 0 | 19,443,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | AOL_PROSPECTUS_2020 p.141, p.144 | 24 | — | — | 44,859 | 44,742 | 111,848,532 | 38,151,468 | N | — | — | AOL_ANNUAL_2022 p.80 (Annexure-03) | unspent, deadline not yet passed at statement | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | 16 announcements in packet are routine auditor-report notices (no extension/change news). | 1 | 1 | 0 | — | — |
| CRYSTALINS | 44,186 | 2,020 | 160,000,000 | 0 | 0 | 0 | 149,271,500 | 10,728,500 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | CRYSTALINS_PROSPECTUS_2020 p.219, p.221 | 3 | — | — | 44,276 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | No reported docs in packet. Insurance company. | 1 | 0 | — | — | — |
| DOMINAGE | 44,167 | 2,020 | 300,000,000 | 280,424,000 | 0 | 0 | 0 | 0 | 0 | 19,576,000 | 0 | 1 | 0 | 0 | 0 | DOMINAGE_PROSPECTUS_2020 p.148, p.152 | 24 | — | Y | 44,897 | 45,473 | 164,406,000 | — | N | — | — | DOMINAGE_ANNUAL_2024 p.2 (auditor: 'not utilized within the stipulated time'); last figures DOMINAGE_PSI_2022 p.1 (BDT 138,663,251 unspent at 31-Oct-2022) | unspent after deadline | — | 2 | 1 | 2 | EXT 2022-11-19: Company applied to BSEC for 15 months extension (to March 2024) for utilisation of remaini [DOMINAGE_PSI_2022 p.1-2] | EXT 2023-06-30: Further time extension taken from BSEC (per auditor); by FY2024 audit report company appli [DOMINAGE_ANNUAL_2023 p.2; DOMINAGE_ANNUAL_2024 p.2] | CHG 2021-12-23 (AGM (15th) and concerned authorities, subject to approval): Change of use of net IPO proceeds: total changed from BDT 280,424,000 to BDT 285,493,250; [announcement 68061] | first DSE trading day in day-end prices | deadline missed per auditor: DOMINAGE_ANNUAL_2024 p.2; Reported 'promised' amounts are rescheduled (not original prospectus). | 1 | 1 | — | — | — |
| EIL | 44,067 | 2,020 | 260,790,000 | 0 | 0 | 0 | 245,790,000 | 15,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | EIL_PROSPECTUS_2020 p.179, p.181 | 9 | — | — | 44,340 | 44,196 | — | — | Y | 44,196 | report date only | EIL_ANNUAL_2020 p.28 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'within the scheduled time'; Annual 2020 p.27 vs p.28 mildly contradictory on utilisation. Insurance company. | 1 | 1 | — | — | — |
| ROBI | 44,189 | 2,020 | 5,237,933,340 | 5,157,723,574 | 0 | 0 | 0 | 80,209,766 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ROBI_PROSPECTUS_2020 p.247 (printed page 230) | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 1 | 0 | CHG 2021-12-09 (EGM proposed (24 Jan 2022)): Board decided to hold EGM (24.01.2022) for approval of amendment of IPO proceeds utilizati [announcement 68488] | ipo_stats.csv listing_date | Reported: FY2021/2023 reports say Audit Committee reviewed utilisation of IPO proceeds; no amounts in packet. Prospectus timeline not in packet. | 1 | 0 | — | — | — |
| WALTONHIL | 44,097 | 2,020 | 1,000,000,000 | 625,000,000 | 330,000,000 | 0 | 0 | 45,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | WALTONHIL_PROSPECTUS_2020 p.406 | 24 | — | — | 44,827 | 45,838 | — | — | Y | — | — | WALTONHIL_ANNUAL_2025 p.315 (also FY2024 p.285) | completed, timing not measurable | — | 0 | 1 | 0 | CHG 2021-07-14 (EGM 14 July 2021 (shareholders), BSEC letter dated May 11, 2021): Rearrangement of BMRE use of IPO proceeds: new machinery list (Annexure-B); BMRE funds 625 [announcements 74201, 169290; WALTONHIL_DOC_2021 p.2] | ipo_stats.csv listing_date | — | 1 | 1 | — | — | — |
| ACMEPL | 44,514 | 2,021 | 300,000,000 | 226,499,000 | 55,000,000 | 0 | 0 | 18,501,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ACMEPL_PROSPECTUS_2021 p.145 | 24 | — | — | 45,244 | 46,112 | — | — | N | — | — | ACMEPL_QUARTERLY_Q3_2026 p.27 | unspent after deadline | 28 | 3 | 0 | 0 | EXT 2024-06-06: Board decided to extend time of utilisation of IPO proceeds up to June 30, 2025 subject to [announcement 34751 (2024-06-09)] | EXT 2025-06-23: Board to consider BSEC consent letter extending time for IPO proceeds utilisation from 1 J [announcement 21876] | EXT 2025-12-22: Company submitted PSI with EGM resolution regarding further extension of time for utilisat [announcement 14155] | ipo_stats.csv listing_date | Reported utilised amounts not cleanly readable (garbled table) in packet. | 1 | 1 | — | — | 28 |
| BPPL | 44,392 | 2,021 | 2,250,000,000 | 0 | 748,725,000 | 0 | 1,443,300,000 | 57,975,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | BPPL_PROSPECTUS_2021 p.166 | 6 | — | — | 44,576 | 44,469 | — | 0 | Y | 44,469 | stated completion date | BPPL_DOC_2021_12 p.1 | completed by deadline | — | 0 | 0 | 1 | — | ipo_stats.csv listing_date | completion: auditor statement to 30 Sep 2021 | 1 | 1 | 0 | — | — |
| DGIC | 44,284 | 2,021 | 160,000,000 | 0 | 0 | 0 | 150,433,500 | 9,566,500 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | DGIC_PROSPECTUS_2021 p.231, p.232 | 3 | — | — | 44,376 | 45,291 | — | — | Y | 45,291 | report date only | DGIC_ANNUAL_2023 p.50 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: FY2023: 'fully utilized'; Insurance company. | 1 | 1 | — | — | — |
| EGEN | 44,250 | 2,021 | 150,000,000 | 98,389,000 | 34,000,000 | 0 | 0 | 17,611,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | EGEN_PROSPECTUS_2021 p.177, p.181 | 24 | — | — | 44,980 | 44,377 | 51,427,663 | — | N | — | — | EGEN_ANNUAL_2021 p.88 | unspent, deadline not yet passed at statement | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | — | 1 | 1 | — | — | — |
| EPGL | 44,215 | 2,021 | 1,500,000,000 | 959,868,493 | 500,000,000 | 0 | 0 | 40,131,508 | 0 | 0 | 1 | 1 | 0 | 0 | 0 | EPGL_PROSPECTUS_2021 p.243, p.247 | 18 | — | — | 44,761 | 44,592 | — | — | Y | 44,592 | stated completion date | EPGL_ANNUAL_2025 p.39 (same table repeated in annual 2024 p.35) | completed by deadline | — | 0 | 1 | 0 | CHG 2021-07-15 (Board; subject to BSEC approval (final approval not in packet)): Board agreed to import readily available empty LPG cylinders with standard valve instead o [announcement 168669] | ipo_stats.csv listing_date | completion: table as on 31 Jan 2022; Reported statement is dated Jan 2022 but printed in annual 2024/2025; the unit is overall fully utilised. | 1 | 1 | — | — | — |
| INDEXAGRO | 44,293 | 2,021 | 500,000,000 | 475,000,000 | 0 | 0 | 0 | 25,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | INDEXAGRO_PROSPECTUS_2021 p.178 | — | — | — | — | 45,127 | — | 268,795,244 | N | — | — | INDEXAGRO_PSI_2023_3 / PSI_2023_5 | unspent, deadline not measurable | — | 1 | 2 | 0 | EXT 2023-05-25: Board decided to extend 12 more months from current expiry for utilising unspent IPO proce [announcement 48558; INDEXAGRO_PSI_2023_5] | CHG 2021-12-09 (AGM (21st); BSEC (Tk 138,500,000, 2023-01-17)): AGM approved repayment of partial short-term loan of Tk 354,932,100 from IPO proceeds (BSE [announcement 68481; INDEXAGRO_PSI_2023_3] | CHG 2023-07-20 (EGM (20 July 2023)): EGM approved use of unspent IPO proceeds Tk 268,795,244 for building & civil construction [INDEXAGRO_PSI_2023_5] | ipo_stats.csv listing_date | — | 1 | 1 | 1 | — | — |
| LOVELLO | 44,237 | 2,021 | 300,000,000 | 182,000,000 | 90,000,000 | 0 | 0 | 28,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | LOVELLO_PROSPECTUS_2021 p.152 | — | 44,957 | — | 44,957 | 45,581 | — | 0 | Y | 45,581 | stated completion date | LOVELLO_ANNUAL_2025 p.61 | completed after deadline | 20 | 3 | 2 | 2 | EXT 2022-12-26: Company applied to BSEC for 1st extension of 12 months up to 31 Jan 2024 and to use Tk 65 [LOVELLO_ANNUAL_2025 p.63] | EXT 2023-12-30: 12th AGM approved extension of one year from Feb 2024 to Jan 2025 for utilizing rest of IP [announcement 40315 (2024-01-01)] | EXT None: Company applied to BSEC for 2nd extension of 12 months up to 31 Jan 2025; not approved by [LOVELLO_ANNUAL_2025 p.63] | CHG 2021-12-28 (AGM (10th AGM, 28 Dec 2021)): Plant & Machinery: instead of Cone Baking Machine, procure Rollo Stick Ice-cream Machine a [announcement 67926] | CHG 2022-12-26 (not approved by BSEC per auditor): Tk 65 lac to be used for vehicle purchase instead of Investment in depot (applied to BSEC; [LOVELLO_ANNUAL_2025 p.63] | ipo_stats.csv listing_date | completion: statement up to 16 Oct 2024; printed deadline: LOVELLO_ANNUAL_2025 p.63 | 1 | 1 | 0 | 20 | — |
| LRBDL | 44,264 | 2,021 | 1,500,000,000 | 980,000,000 | 460,430,282 | 0 | 0 | 59,569,718 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | LRBDL_PROSPECTUS_2021 p.193 | 24 | — | — | 44,994 | 45,838 | — | 131,000,000 | N | — | — | LRBDL_ANNUAL_2025_2 p.2 (auditor's report) | unspent after deadline | 28 | 0 | 2 | 1 | CHG 2021-10-21 (BSEC (relocation permission)): BMRE project revised to BDT 996,396,045 funded by IPO proceeds plus interest income (16,39 [announcement 71585; LRBDL_PSI_2023 p.1] | CHG 2026-06-10 (EGM proposed (BSEC approval requested)): Proposed use of about Tk 20 crore idle IPO fund: LC/payment USD 364,811 (BDT 45,601,375) f [announcement 6621] | ipo_stats.csv listing_date | Unspent 13.10 crore converted to 131,000,000 BDT (1 crore = 10,000,000). Latest statement is an auditor qualified opinion, not a table. | 1 | 1 | 0 | — | 28 |
| MIRAKHTER | 44,229 | 2,021 | 1,250,000,000 | 815,000,000 | 400,000,000 | 0 | 0 | 35,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | MIRAKHTER_PROSPECTUS_2021 p.188 | — | — | — | — | 45,260 | — | 0 | Y | 45,260 | stated completion date | MIRAKHTER_PSI_2023 p.2,7 | completed, timing not measurable | — | 0 | 2 | 0 | CHG 2022-03-10 (EGM 10 Mar 2022 and BSEC consent (letter May 18, 2022)): Amendment/re-allocation of unspent IPO proceeds (heavy equipment/aggregate plant to other [MIRAKHTER_PSI_2023 p.2; announcement 66883] | CHG 2022-11-14 (Board; AGM/BSEC pending): Board decided to further amend use of IPO proceeds subject to 42nd AGM and BSEC approval [announcement 56447] | ipo_stats.csv listing_date | completion: auditor 14 Dec 2023; Amount strings from OCR; 1,250,029,598 total utilised printed by auditor (exceeds 1,250,000,000 by interest/own source). | 1 | 1 | 0 | — | — |
| NRBCBANK | 44,277 | 2,021 | 1,200,000,000 | 0 | 0 | 0 | 1,160,523,624 | 39,476,376 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | NRBCBANK_PROSPECTUS_2021 p.313 and p.312 (printed page 296) | 6 | — | — | 44,461 | 44,408 | — | 0 | Y | 44,408 | stated completion date | NRBCBANK_DOC_2021_2 p.2,3 | completed by deadline | — | 0 | 0 | 1 | — | ipo_stats.csv listing_date | completion: completed up to 31 Jul 2021 | 1 | 1 | 0 | — | — |
| SBACBANK | 44,419 | 2,021 | 1,000,000,000 | 0 | 0 | 0 | 951,854,136 | 48,145,864 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | SBACBANK_PROSPECTUS_2021 p.371 and p.373 | 3 | — | — | 44,511 | 44,561 | — | 0 | Y | 44,561 | report date only | SBACBANK_ANNUAL_2021 p.105 and p.288 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: FY2021: 100% | 1 | 1 | 0 | — | — |
| SIPLC | 44,507 | 2,021 | 160,000,000 | 0 | 0 | 0 | 149,000,000 | 11,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | SIPLC_PROSPECTUS_2021 p.224 (printed page 210) and p.220 | 6 | — | — | 44,688 | 45,657 | — | — | Y | 44,926 | stated completion date | SIPLC_ANNUAL_2024_2 p.10 | completed after deadline | 8 | 0 | 2 | 1 | CHG 2022-07-26 (BSEC): BSEC consented to utilise the remaining IPO expenses fund of BDT 4,725,424 (47,25,424) to [announcement 61138] | CHG 2023-03-15 (AGM approval to be taken): Auditor emphasis of matter: use of IPO funds as consented by BSEC for which the company wi [announcement 51553] | ipo_stats.csv listing_date | completion: 'fully utilized in 2022'; Insurer; announcements titled SKICL. | 1 | 1 | — | 8 | — |
| SONALILIFE | 44,377 | 2,021 | 190,000,000 | 0 | 0 | 0 | 178,000,000 | 12,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | SONALILIFE_PROSPECTUS_2021 p.207 and p.208 | 1 | — | — | 44,407 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported hits are only audit-committee compliance rows ("Oversee whether IPO proceeds utilized as per the published Prospectus"); no utilisation statement in packet. | 1 | 0 | — | — | — |
| BDTHAIFOOD | 44,585 | 2,022 | 150,000,000 | 139,000,000 | 0 | 0 | 0 | 11,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | BDTHAIFOOD_PROSPECTUS_2022 p.279 | 24 | — | — | 45,315 | 45,838 | — | — | Y | 45,838 | report date only | BDTHAIFOOD_ANNUAL_2025_2 p.17 | completed after deadline | 17 | 1 | 3 | 0 | EXT 2024-05-27: Board decided 4th EGM (14 July 2024) for changes in use of IPO proceeds and extension of t [announcement 35152; BDTHAIFOOD_ANNUAL_2024 p.17] | CHG 2022-03-20 (EGM (2nd, 9 May 2022); BSEC approved alteration (announcement 2022-07-03)): Tunnel oven worth BDT 28,475,000 in prospectus to be replaced: rotary oven and packing mac [announcements 65159, 65157, 61652] | CHG 2022-10-27 (EGM (3rd, 14 Dec 2022)): Further EGM for changing use of IPO proceeds because machinery prices rose ~35%; 3rd EGM 1 [announcement 57919; BDTHAIFOOD_ANNUAL_2024 p.17] | CHG 2024-07-14 (EGM (4th)): Shareholders revised unutilised amount Tk 39,982,049 and extended time [BDTHAIFOOD_ANNUAL_2024 p.17] | ipo_stats.csv listing_date | completion: FY2025: total IPO fund utilised | 1 | 1 | — | 17 | — |
| CLICL | 44,864 | 2,022 | 150,000,000 | 0 | 0 | 0 | 139,000,000 | 11,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | CLICL_PROSPECTUS_2022 p.272, p.273 | 9 | — | — | 45,137 | 45,107 | — | 0 | Y | 45,107 | stated completion date | CLICL_PSI_Q3_2023 p.2 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: auditor status at 30 Jun 2023; Insurance company (life). | 1 | 1 | 0 | — | — |
| GIB | 44,881 | 2,022 | 4,250,000,000 | 0 | 0 | 0 | 4,185,000,000 | 65,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | GIB_PROSPECTUS_2022 p.323, p.326 | 24 | — | — | 45,612 | 45,838 | — | 738,198,032 | N | — | — | announcement 20006 (statement for quarter ended 30 June 2025) | unspent after deadline | 7 | 3 | 1 | 0 | EXT 2024-04-29: Board decided to extend additional 24 months for utilisation of remaining IPO proceeds til [announcement 36262] | EXT 2025-07-09: Board decided again to extend 24 months to November 09, 2026 and to transfer remaining IPO [announcement 21454] | EXT 2025-10-19: BSEC approved modification of use of IPO proceeds with time extension till November 09, 20 [announcement 18230] | CHG 2025-08-19 (AGM; BSEC approval 2025-10-19): Shareholders (AGM 19 Aug 2025, date corrected in announcement 20005) approved transfer of [announcements 20006, 20005, 18230] | ipo_stats.csv listing_date | Bank. Timing of the first extension announcement (2024-04-29 vs 2025-07-09) may reflect repetition; both state the same new deadline. | 1 | 1 | 0 | — | 7 |
| ICICL | 44,913 | 2,022 | 202,611,060 | 0 | 0 | 0 | 193,283,373 | 9,327,687 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | ICICL_PROSPECTUS_2022 p.259, p.264 | 3 | — | — | 45,003 | 44,926 | — | — | Y | 44,926 | report date only | ICICL_ANNUAL_2022 p.27 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: FY2022: 'fully utilized'; Insurance company; annual text prints prospectus IPO expense as 9,327,684 vs 9,327,687 in table. | 1 | 1 | — | — | — |
| JHRML | 44,651 | 2,022 | 750,000,000 | 458,700,000 | 250,000,000 | 0 | 0 | 41,300,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | JHRML_PROSPECTUS_2022 p.211 (in BDT crore; also amounts as per prospectus column in JHRML_ANNUAL_2025 p.43) | 12 | — | — | 45,016 | 45,930 | — | 1,728,441 | N | — | — | JHRML_ANNUAL_2025 p.43 | unspent after deadline | 30 | 4 | 3 | 0 | EXT 2023-12-31: Revised timeline within 2 years i.e. 31 March 2024 (14th AGM 2023) [JHRML_ANNUAL_2025 p.43] | EXT 2024-01-22: 15th AGM approved revised use of IPO proceeds and revised timeline to 31 March 2026 [announcement 39709; JHRML_ANNUAL_2025 p.43] | EXT 2025-10-27: Board recommended revision of IPO proceeds utilisation and extension of time up to 31 Dece [announcement 17789] | EXT 2026-01-22: 17th AGM approved revision of IPO proceeds utilisation and extension of time up to Decembe [announcement 12709] | CHG 2022-04-27 (Board): Board approved cost of BDT 42,500,000 to acquire 34 decimal land (adjacent site, Vitikandi [announcement 63722] | CHG 2022-10-26 (AGM (14th), BSEC): Board recommended revising use of IPO proceeds (Covid-19, exchange rate, Russia-Ukraine wa [announcement 58080; JHRML_ANNUAL_2025 p.43] | CHG 2023-10-19 (AGM (15th, 22 Jan 2024), BSEC): Board recommended further revision of use of IPO proceeds (Covid-19, dollar crisis, Russia [announcement 44163, 39709] | ipo_stats.csv listing_date | — | 1 | 1 | 0 | — | 30 |
| MEGHNAINS | 44,720 | 2,022 | 160,000,000 | 0 | 0 | 0 | 151,250,000 | 8,750,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | MEGHNAINS_PROSPECTUS_2022 p.272 | 6 | — | — | 44,903 | 44,834 | — | 0 | Y | 44,834 | stated completion date | MEGHNAINS_DOC_Q3_2022 p.1,2,4 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: auditor certificate Jul-Sep 2022 | 1 | 1 | 0 | — | — |
| NAVANAPHAR | 44,852 | 2,022 | 750,000,000 | 508,200,000 | 211,800,000 | 0 | 0 | 30,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | NAVANAPHAR_PROSPECTUS_2022 p.415 and p.424 | 24 | — | — | 45,583 | 45,838 | 727,487,988 | 22,342,657 | N | — | — | NAVANAPHAR_ANNUAL_2025_3 p.235 | unspent after deadline | 8 | 1 | 1 | 0 | EXT 2024-05-07: EGM approved extension of time for full utilization of IPO proceeds to within 36 months af [announcements 35713, 35712] | CHG 2024-05-07 (EGM (7th EGM, 7 May 2024)): Change use of BDT 13.12 crore (17.49% of IPO proceeds of BDT 75 crore) earmarked for Moder [announcements 35713; NAVANAPHAR_PSI_2024_2 p.1] | ipo_stats.csv listing_date | The 13.12 crore printed in crore; revised IPO-funded project 131,185,000 per EGM notice. Quarterly auditor reports on utilisation filed through Sep 2025 (announcement 17311) but numbers not in packet. | 1 | 1 | 0 | — | 8 |
| UNIONBANK | 44,587 | 2,022 | 4,280,000,000 | 0 | 0 | 0 | 4,215,000,000 | 65,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | UNIONBANK_ANNUAL_2023 p.86 (prospectus page not in packet) | 12 | — | — | 44,952 | 45,291 | 3,671,020,658 | 608,979,342 | N | — | — | UNIONBANK_ANNUAL_2023 p.86 | unspent after deadline | 11 | 2 | 1 | 1 | EXT 2023-06-15: 10th AGM approved extension of time for utilizing IPO fund till June 30, 2024, subject to [announcement 47956; UNIONBANK_PSI_2023_3 p.1] | EXT 2024-06-27: Board recommended extension of full utilization of IPO fund till June 30, 2025 for approva [announcement 34235; UNIONBANK_ANNUAL_2023 p.8] | CHG 2023-06-15 (10th AGM 15 June 2023): Modification of use of proceeds: unutilised amount allocated to IPO Expense can be transfe [UNIONBANK_PSI_2023_3 p.1; UNIONBANK_ANNUAL_2023 p.86] | ipo_stats.csv listing_date | Promised table taken from annual report (no prospectus pages in packet). Bank; 1 crore = 10,000,000. | 1 | 1 | 0 | — | 11 |
| UNIONINS | 44,577 | 2,022 | 193,609,040 | 40,000,000 | 0 | 0 | 141,981,319 | 11,627,721 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | UNIONINS_PROSPECTUS_2022 p.219 and p.220 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | No reported utilisation or announcements in packet; implementation schedule text not captured. | 1 | 0 | — | — | — |
| MIDLANDBNK | 45,012 | 2,023 | 700,000,000 | 0 | 0 | 0 | 661,101,545 | 38,898,455 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | MIDLANDBNK_PROSPECTUS_2023 p.245 | 6 | — | — | 45,196 | 45,291 | — | 0 | Y | 45,291 | stated completion date | MIDLANDBNK_QUARTERLY_Q4_2023 p.2 | completed after deadline | 3 | 0 | 1 | 0 | CHG 2023-10-29 (EGM 29 Oct 2023 (subject to regulatory approvals)): Transfer of unutilized Tk 4,673,976 under IPO Expenses to Investment in Government Securit [announcements 45769, 42331] | ipo_stats.csv listing_date | completion: Q4 2023 auditor certificate | 1 | 1 | 0 | 3 | — |
| TILIL | 45,057 | 2,023 | 160,000,000 | 0 | 0 | 0 | 152,000,000 | 8,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | TILIL_DOC_Q1_2023 p.3 (auditor certificate "Allotment as per Prospectus"); prospectus p.165 table not captured | — | — | — | — | 45,107 | — | 0 | Y | 45,107 | stated completion date | TILIL_DOC_Q1_2023 p.3,4,5 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: completed in quarter to 30 Jun 2023 | 1 | 1 | 0 | — | — |
| ASIATICLAB | 45,357 | 2,024 | 950,000,000 | 641,965,856 | 280,000,000 | 0 | 0 | 28,034,144 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ASIATICLAB_PROSPECTUS_2024 p.182, p.190 | 24 | — | — | 46,087 | 46,327 | — | 649,382,529 | N | — | — | DSE post id 6171 (1-Nov-2026) | unspent after deadline | 8 | 1 | 0 | 0 | EXT 2026-11-01: Board proposed time extension of at least 18 months from 06 March 2026 to utilise unutilis [announcement 6171] | ipo_stats.csv listing_date | Totals utilised/unutilised as of 30 June 2025 not read; BSEC IPO approval letter dated 21 Sep 2022. | 1 | 1 | 1 | — | 8 |
| BESTHLDNG | 45,328 | 2,024 | 3,500,000,000 | 2,210,923,539 | 1,156,076,461 | 0 | 0 | 133,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | BESTHLDNG_PROSPECTUS_2024 p.265, p.268 | 3 | — | — | 45,418 | 45,473 | — | — | N | — | — | BESTHLDNG_ANNUAL_2024 p.49 | unspent after deadline | 2 | 0 | 0 | 0 | — | ipo_stats.csv listing_date | 7 announcements are routine auditor reports (not shown). | 1 | 1 | — | — | 2 |
| NRBBANK | 45,349 | 2,024 | 1,000,000,000 | 0 | 0 | 0 | 961,700,000 | 38,300,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | NRBBANK_PROSPECTUS_2023 p.370 and p.375 | 12 | — | — | 45,715 | 45,382 | — | 0 | Y | 45,382 | stated completion date | NRBBANK_QUARTERLY_Q1_2024 p.2,3,5 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 100% within 31 Mar 2024 | 1 | 1 | 0 | — | — |
| SICL | 45,315 | 2,024 | 160,000,000 | 60,871,500 | 0 | 0 | 88,000,000 | 11,128,500 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | SICL_PROSPECTUS_2024 p.156 and p.157 | 3 | — | — | 45,406 | 46,022 | — | — | N | — | — | SICL_ANNUAL_2025 p.3 (auditor Other matter) | unspent after deadline | 20 | 0 | 0 | 1 | — | ipo_stats.csv listing_date | Insurer IPO; capital-market portion (48,000,000) unutilised beyond 3-month deadline per auditor; quotation is OCR-garbled. | 1 | 1 | — | — | 20 |
| TECHNODRUG | 45,487 | 2,024 | 1,000,000,000 | 670,000,000 | 300,000,000 | 0 | 0 | 30,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | TECHNODRUG_PROSPECTUS_2024 p.272 | 24 | — | — | 46,217 | 45,838 | 644,620,905 | 355,379,095 | N | — | — | TECHNODRUG_ANNUAL_2025 p.100 and p.68 | unspent, deadline not yet passed at statement | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | — | 1 | 1 | 0 | — | — |
From the IPOs tab of the model.
| Measure | Value |
|---|---|
| IPOs listed 2010-2024 in scope (prospectus in corpus) | 128 |
| With promised use-of-proceeds split | 115 |
| With a reported utilisation statement | 77 |
| With both promised split and reported statement | 74 |
| Promised total, IPOs with split (BDT) | 85,644,220,640 |
| Capex share of promised money | 52.8% |
| Loan repayment share | 20.7% |
| Working capital share | 1.9% |
| Investments share | 19.4% |
| IPO costs share | 3.2% |
| Reported fully utilised (Y) | 50 |
| Reported not fully utilised at latest statement (N) | 27 |
| Completed by deadline (evidence date on or before deadline) | 14 |
| Completed after deadline | 11 |
| Unspent at a statement dated after the deadline | 18 |
| Unspent, deadline not yet passed at statement | 4 |
| Timing measurable (sum of the four rows above) | 47 |
| Share completed by deadline, of IPOs whose deadline had passed (rows 14-16) | 32.6% |
| Median months late: completed after deadline | 16.8 |
| Median months past deadline: unspent at latest statement | 11.8 |
| IPOs with at least one extension decision recorded | 27 |
| IPOs with at least one change of purpose recorded | 41 |
| Unspent money at latest statements, IPOs not fully utilised (BDT) | 5,188,399,482 |
| IPOs with an unspent amount printed | 21 |
| Unspent printed at statements dated 2025 or later (BDT) | 2,643,711,729 |
| IPOs in that row | 8 |
| Median capex share per IPO | 63.2% |
| Median loan repayment share per IPO | 11.4% |
| IPOs promising any loan repayment | 64 |
| IPOs with timing not measurable or no statement | 81 |
From the Summary tab of the model.
| Rule | Text (verbatim) | Source |
|---|---|---|
| 2025 Rules, rule 4(1)(t): quarterly audited report | it has declared that the issuer shall be responsible for submitting a report to the Commission on utilization of public issue proceeds duly audited by a panel of auditors of the Commission within 10 (ten) days of the end of each quarter with a confirmation to the effect that the public issue proceeds has been utilized according to the use of proceeds mentioned in the prospectus | BSEC (Public Offer of Equity Securities) Rules, 2025, gazette 30-Dec-2025, PDF p.10 |
| 2015 Rules, Annexure (prospectus contents): schedule | A schedule mentioning the stages of implementation and utilization of funds received through public offer | BSEC (Public Issue) Rules, 2015 (consolidated 4-Apr-2022), use of proceeds section, PDF p.57 |
| 2015 Rules: auditor certificate on earlier issues | The issuer shall submit auditor's certificate on utilization of the fund raised through issue of capital earlier. | BSEC (Public Issue) Rules, 2015 (consolidated), item (27), PDF p.65 |
From the Rules tab of the model.
The model
IPOs
| IPO (DSE code) | Listing date | Listing year | Promised total (BDT) | Capex (machinery, buildings, expansion) (BDT) | Loan repayment (BDT) | Working capital (BDT) | Investments (securities, FDRs, lending) (BDT) | IPO costs (BDT) | Other (BDT) | Not itemised on the page (BDT) | Items check (sum less total) | Capex share | Loan repayment share | Working capital share | Investments share | Promised source | Promised window (months) | Printed deadline (company/auditor) | Auditor says deadline missed (Y) | Deadline (listing + window, or printed) | Latest statement date | Utilised at latest statement (BDT) | Unspent at latest statement (BDT) | Fully utilised (Y/N) | Completion evidence date | Completion evidence type | Reported source | Status vs deadline | Months late (completion or latest statement) | Extension decisions recorded | Changes of purpose recorded | Auditor/BSEC remarks recorded | Extensions and changes: sources | Listing date source | Note | Has promised split (1/0) | Has reported data (1/0) | Unspent share of promised | Helper: months late, completed after deadline | Helper: months past deadline, unspent |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ACTIVEFINE | 40,504 | 2,010 | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Packet has no prospectus pages and no reported hits (docs list empty); nothing extractable. | 0 | 0 | — | — | — |
| BEACONPHAR | 40,402 | 2,010 | 300,000,000 | 0 | 0 | 283,966,500 | 0 | 0 | 0 | 16,033,500 | 0 | 0 | 0 | 1 | 0 | BEACONPHAR_PROSPECTUS_2010 p.26 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs. | 1 | 0 | — | — | — |
| DHAKAINS | 40,227 | 2,010 | 108,000,000 | — | — | — | — | — | — | — | — | — | — | — | — | DHAKAINS_PROSPECTUS_2009 p.14 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs. | 0 | 0 | — | — | — |
| MALEKSPIN | 40,392 | 2,010 | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 1 | 0 | CHG 2010-12-27 (AGM 27 Dec 2010): Shareholders approved revised investment programme in lieu of IPO proceeds investment in N [announcements 140896, 140892 (2011-04-04)] | first DSE trading day in day-end prices | Only prospectus page 36 (financial discussion) in packet, not the use-of-proceeds table; prospectus says capex only via equity subscription in subsidiary NewAsia Synthetics Ltd per use of proceeds (investment). No reported-utilisation reports in packet. | 0 | 0 | — | — | — |
| PROVATIINS | 40,196 | 2,010 | 90,000,000 | 0 | 0 | 0 | 90,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | PROVATIINS_PROSPECTUS_2009 p.14 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No itemised use of proceeds, no reported utilisation or announcements in packet. | 1 | 0 | — | — | — |
| RAKCERAMIC | 40,342 | 2,010 | — | — | — | — | — | — | — | — | — | — | — | — | — | RAKCERAMIC_PROSPECTUS_2010 p.56 | 3 | — | — | 40,434 | — | — | — | — | — | — | — | no statement found | — | 0 | 1 | 0 | CHG 2011-01-30 (Board; subject to shareholders approval (AGM 20.03.11)): Board decided to invest unutilized IPO proceeds of Tk. 1,328.93 million (=1,328,930,000) i [announcement 142300] | first DSE trading day in day-end prices | IPO size not printed in packet; unutilised proceeds 1,328.93 million after IPO per announcement suggests proceeds were not applied to loans as planned. | 0 | 0 | — | — | — |
| CROWNCEMNT | — | 2,011 | — | — | — | — | — | — | — | — | — | — | — | — | — | CROWNCEMNT_PROSPECTUS_DRAFT_2011 p.14 | — | — | — | — | 45,107 | — | 0 | Y | — | — | CROWNCEMNT_ANNUAL_2023 p.97 | completed, timing not measurable | — | 0 | 0 | 0 | — | approximate: prospectus year (eod code history starts later) | Draft prospectus; final IPO amount not stated in the packet page (project cost, not necessarily IPO amount). Many PSIs/annual reports exist (22 docs) that may carry utilisation statements. | 0 | 1 | — | — | — |
| MJLBD | 40,720 | 2,011 | — | — | — | — | — | — | — | — | — | — | — | — | — | MJLBD_PROSPECTUS_2011 p.20 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Only one page in packet; no use-of-proceeds allocation table or total; no reported utilisation/announcements. | 0 | 0 | — | — | — |
| RDFOOD | 40,875 | 2,011 | 294,140,000 | 224,440,000 | 50,200,000 | 19,500,000 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | RDFOOD_PROSPECTUS_2011 p.16 | 7 | — | — | 41,088 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Total 294.14 million exceeds face-value amount 163,414,000, implying premium; IPO expenses not listed. No reported/announcements in packet. | 1 | 0 | — | — | — |
| AAMRATECH | 41,094 | 2,012 | 517,728,000 | 128,750,000 | 358,519,000 | 0 | 0 | 30,459,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | AAMRATECH_PROSPECTUS_2012 p.17 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Later reports in packet (2024 annual) only show compliance 5(5)(m) 'Not applicable'; no utilisation statement. | 1 | 0 | — | — | — |
| BSCPLC | — | 2,012 | 1,085,000,000 | 0 | 783,400,000 | 244,600,000 | 0 | 57,000,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | BSCPLC_PROSPECTUS_2012 p.17 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | approximate: prospectus year (eod code history starts later) | No reported docs in packet. | 1 | 0 | — | — | — |
| ENVOYTEX | 41,252 | 2,012 | 900,000,000 | — | — | — | — | — | — | — | — | — | — | — | — | ENVOYTEX_PROSPECTUS_2012 p.20, p.21 | 9 | — | — | 41,526 | 41,455 | — | 0 | Y | 41,394 | stated completion date | ENVOYTEX_ANNUAL_2013 p.37 | completed by deadline | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | completion: 'November 2012 to April 2013' | 0 | 1 | 0 | — | — |
| GBBPOWER | 41,073 | 2,012 | 820,000,000 | 0 | 770,000,000 | 11,399,000 | 0 | 38,601,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | GBBPOWER_PROSPECTUS_2012 p.26 (page image) | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Garbled table; loan amount unreliable. No reported docs. | 1 | 0 | — | — | — |
| GENNEXT | 41,248 | 2,012 | 300,000,000 | 0 | 300,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | GENNEXT_PROSPECTUS_2012 p.20 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs. | 1 | 0 | — | — | — |
| GPHISPAT | 41,018 | 2,012 | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No prospectus pages in packet (0 candidate pages out of 90); reported hits are only compliance checklists (no utilisation statement). Nothing extractable. | 0 | 0 | — | — | — |
| GSPFINANCE | 41,008 | 2,012 | 500,000,000 | 0 | 0 | 0 | 500,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | GSPFINANCE_PROSPECTUS_2012 p.21 | 12 | — | — | 41,373 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Reported hits only mention audit committee declaration item 3.3(x); no utilisation figures. Financial institution. | 1 | 0 | — | — | — |
| PADMALIFE | 41,017 | 2,012 | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Packet has no prospectus pages, no reported hits and no announcements for PADMALIFE_PROSPECTUS_2012. | 0 | 0 | — | — | — |
| SAIHAMCOT | 41,084 | 2,012 | 950,000,000 | 950,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SAIHAMCOT_PROSPECTUS_2012 p.17 | 12 | — | — | 41,449 | 45,838 | — | — | — | — | — | SAIHAMCOT_ANNUAL_2025 p.25 | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | — | 1 | 0 | — | — | — |
| UNIQUEHRL | 41,092 | 2,012 | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | — | 43,646 | — | — | Y | 42,855 | stated completion date | UNIQUEHRL_ANNUAL_2019 p.109 | completed, timing not measurable | — | 1 | 1 | 0 | EXT 2014-04-08: EGM (with AGM 08.04.2014) to extend time for implementation/utilization schedule of IPO fu [announcement 113677 (2014-03-09)] | CHG 2016-12-22 (15th AGM 22.12.2016 (Extra Ordinary resolution)): Resolution at 15th AGM: purchase about 2,04,494 sft of floor space of the Acropolis projec [announcement 95275] | first DSE trading day in day-end prices | completion: 'fully utilized on 30 April 2017'; No prospectus pages in packet (use-of-proceeds table missing); reported only one-line statement. | 0 | 1 | — | — | — |
| APOLOISPAT | 41,632 | 2,013 | 2,167,646,500 | 636,000,000 | 1,531,646,500 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | APOLOISPAT_PROSPECTUS_2013 p.22, p.26 | 6 | — | — | 41,814 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs in packet. | 1 | 0 | — | — | — |
| ARGONDENIM | 41,324 | 2,013 | 1,050,000,000 | 848,000,000 | 164,000,000 | 0 | 0 | 38,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ARGONDENIM_PROSPECTUS_2012 p.19 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 1 | — | first DSE trading day in day-end prices | No reported utilisation statement docs in packet; auditor emphasis of matter FY2013 only. | 1 | 0 | — | — | — |
| BENGALWTL | 41,380 | 2,013 | 400,000,000 | 194,741,719 | 100,000,000 | 81,704,781 | 0 | 23,553,500 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | BENGALWTL_PROSPECTUS_2013 p.24 | 9 | — | — | 41,655 | 41,547 | 284,515,678 | 115,484,322 | N | — | — | BENGALWTL_PSI_2013 p.13 | unspent, deadline not yet passed at statement | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | — | 1 | 1 | 0 | — | — |
| FAMILYTEX | 41,443 | 2,013 | 340,000,000 | 0 | 332,120,565 | 0 | 0 | 7,879,435 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | FAMILYTEX_PROSPECTUS_2013 p.26 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 1 | 0 | CHG 2013-12-09 (Board proposal; EGM 10.01.2014 and BSEC pending): Board proposed approval of deviation of utilisation of IPO fund between prospectus estimat [announcement 115332] | first DSE trading day in day-end prices | No reported docs in packet. | 1 | 0 | — | — | — |
| FAREASTFIN | 41,534 | 2,013 | 450,000,000 | 0 | 0 | 0 | 450,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | FAREASTFIN_PROSPECTUS_2013 p.30 | 12 | — | — | 41,899 | 43,465 | — | — | Y | 42,004 | report date only | FAREASTFIN_ANNUAL_2018 p.27 | completed, timing not measurable | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | completion: 'completed ... in the year 2014'; Financial institution; no item amounts. | 1 | 1 | — | — | — |
| GHAIL | 41,337 | 2,013 | 750,000,000 | 388,135,297 | 338,478,703 | 0 | 0 | 0 | 0 | 23,386,000 | 0 | 1 | 0 | 0 | 0 | GHAIL_PROSPECTUS_2012 p.30 | 12 | — | — | 41,702 | — | — | — | — | — | — | — | no statement found | — | 1 | 1 | 0 | EXT 2014-10-28: Board decided to hold EGM (15.12.2014) to approve excess IPO expenses, extended time for I [announcement 109239] | CHG 2014-10-28 (EGM 15.12.2014 (proposed)): Proposal for investment of IPO fund in its subsidiary company and excess IPO expenses (det [announcement 109239] | first DSE trading day in day-end prices | No reported docs in packet. Later (2025-2026) announcements are about Rights Share issue proceeds utilisation, not the IPO. | 1 | 0 | — | — | — |
| GHCL | 41,339 | 2,013 | 240,000,000 | 220,455,500 | 0 | 0 | 0 | 19,544,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | GHCL_PROSPECTUS_2012 p.21 | — | — | — | — | — | — | — | Y | — | — | GHCL_ANNUAL_2022 p.26 | completed, timing not measurable | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No amounts in reported hits. | 1 | 1 | — | — | — |
| ORIONPHARM | 41,353 | 2,013 | 2,400,000,000 | 2,306,986,500 | 0 | 0 | 0 | 93,013,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ORIONPHARM_PROSPECTUS_2014 p.20 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Itemised table likely on adjacent page not in packet. No reported/announcements in packet. | 1 | 0 | — | — | — |
| PREMIERCEM | 41,336 | 2,013 | — | — | — | — | — | — | — | — | — | — | — | — | — | PREMIERCEM_PROSPECTUS_2012 p.21 | — | — | — | — | 41,820 | — | — | — | — | — | PREMIERCEM_ANNUAL_2014_4 p.28 | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Promised table is a project fund-requirement table (IPO only pays part of LC value of 4th unit). IPO amount not printed. | 0 | 0 | — | — | — |
| PTL | 41,597 | 2,013 | 840,000,000 | 0 | 730,000,000 | 87,041,781 | 0 | 22,958,219 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | PTL_PROSPECTUS_2013 p.27 | 6 | — | — | 41,778 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported utilisation/announcements in packet. | 1 | 0 | — | — | — |
| SUNLIFEINS | 41,305 | 2,013 | 120,000,000 | 0 | 0 | 0 | 115,066,500 | 4,933,500 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | SUNLIFEINS_PROSPECTUS_2012 p.21 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported utilisation or announcements in packet. | 1 | 0 | — | — | — |
| AFCAGRO | 41,643 | 2,014 | 109,041,500 | 109,041,500 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | AFCAGRO_PROSPECTUS_2013 p.22 | 6 | — | — | 41,824 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs in packet. Total gross IPO 120,000,000. | 1 | 0 | — | — | — |
| EMERALDOIL | 41,643 | 2,014 | 200,000,000 | 0 | 120,000,000 | 65,000,000 | 0 | 15,000,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | EMERALDOIL_PROSPECTUS_2014 p.19 | 4 | — | — | 41,763 | 41,820 | — | 0 | Y | 41,820 | stated completion date | EMERALDOIL_ANNUAL_2014 p.17 | completed after deadline | 2 | 0 | 0 | 0 | — | first DSE trading day in day-end prices | completion: table to 30 Jun 2014 | 1 | 1 | 0 | 2 | — |
| FARCHEM | 41,648 | 2,014 | 120,000,000 | 106,790,553 | 0 | 0 | 0 | 13,209,447 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | FARCHEM_PROSPECTUS_2014 p.27 | 13 | — | — | 42,044 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs in packet. | 1 | 0 | — | — | — |
| FEKDIL | 41,648 | 2,014 | 675,000,000 | 106,549,298 | 540,292,599 | 0 | 0 | 28,158,103 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | FEKDIL_PROSPECTUS_2014 p.25 | 6 | — | — | 41,829 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported docs. | 1 | 0 | — | — | — |
| HFL | 41,977 | 2,014 | 1,050,000,000 | 722,000,000 | 303,490,000 | 0 | 0 | 24,510,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | HFL_PROSPECTUS_2014 p.22 | 12 | — | — | 42,342 | 43,281 | — | — | Y | — | — | HFL_ANNUAL_2018 p.13; HFL_ANNUAL_2017 p.10 | completed, timing not measurable | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | — | 1 | 1 | — | — | — |
| HWAWELLTEX | 41,645 | 2,014 | 215,000,000 | 200,000,000 | 0 | 0 | 0 | 15,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | HWAWELLTEX_PROSPECTUS_2014 p.21 | — | — | — | — | 45,838 | — | — | Y | 42,308 | stated completion date | HWAWELLTEX_ANNUAL_2025 p.27 | completed, timing not measurable | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | completion: 'fully utilized by October 2015'; Printed prospectus total 215,000,000 vs 'Tk. 20 crore' IPO in annual reports. | 1 | 1 | — | — | — |
| KBPPWBIL | 41,961 | 2,014 | 200,000,000 | 152,051,500 | 19,634,950 | 15,365,050 | 0 | 12,948,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | KBPPWBIL_PROSPECTUS_2014 p.25 | 7 | — | — | 42,173 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Reported hits (annual 2019-2025) only mention audit committee reviewing IPO proceeds utilisation; no statement. | 1 | 0 | — | — | — |
| KPPL | 41,648 | 2,014 | 105,000,000 | 0 | 0 | 87,164,500 | 0 | 17,835,500 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | KPPL_PROSPECTUS_2014 p.20 | 6 | — | — | 41,829 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Reported: later annual reports (2018-2022) only say IPO fund utilization was presented in relevant years; no statement in packet. Auditor qualified opinion on going concern mentioned in FY2021/22 reports (not IPO-specific). | 1 | 0 | — | — | — |
| MATINSPINN | 41,645 | 2,014 | 1,261,700,000 | 1,230,257,270 | 0 | 0 | 0 | 31,442,730 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | MATINSPINN_PROSPECTUS_2014 p.29 | — | — | — | — | 43,281 | — | 0 | Y | 43,281 | report date only | MATINSPINN_ANNUAL_2018 p.55 | completed, timing not measurable | — | 0 | 1 | 1 | CHG 2017-11 (AGM (agenda item 7, FY2017 notice)): AGM agenda: approve utilization of interest income from IPO Fund of Tk. 9,282,690 as Worki [MATINSPINN_ANNUAL_2017 p.8] | first DSE trading day in day-end prices | completion: balance nil at 30 Jun 2018; Announcement 94860 emphasis of matter also covers non-installation of some fixed assets purchased with IPO fund (in CWIP at 30 June 2016). | 1 | 1 | 0 | — | — |
| MHSML | 41,643 | 2,014 | 275,000,000 | 0 | 261,495,000 | 0 | 0 | 13,505,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | MHSML_PROSPECTUS_2013 p.19 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported utilisation/announcements in packet. | 1 | 0 | — | — | — |
| PENINSULA | 41,648 | 2,014 | 1,650,000,000 | 1,480,526,766 | 132,973,234 | 0 | 0 | 36,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | PENINSULA_PROSPECTUS_2014 p.19 (page image) | — | — | — | — | 45,838 | — | — | Y | 45,260 | stated completion date | PENINSULA_ANNUAL_2025 p.24; PENINSULA_ANNUAL_2023 p.22 | completed, timing not measurable | — | 0 | 5 | 0 | CHG 2015-03-02 (EGM (2 Mar 2015; board decision)): EGM to change mode of utilization of IPO proceeds and implementation schedule [announcement 107672] | CHG 2016-12-04 (EGM 4 Dec 2016 (board decision; subject to shareholder approval)): EGM/AGM to change mode of utilization of IPO proceeds and implementation schedule [announcement 96832] | CHG 2018-10-30 (EGM 30 Oct 2018 (board decision)): EGM to change mode of utilization of IPO proceeds and its implementation schedule [announcement 82117] | CHG 2020-12-14 (EGM 14 Dec 2020 (board decision)): 8th EGM called for changes in the mode of utilization of IPO proceeds and its implementati [announcement 172354] | CHG 2022-06-23 (EGM 23 Jun 2022 (board decision)): EGM for approval of changes in the mode of utilization of IPO Proceeds and its implementat [announcement 63076] | first DSE trading day in day-end prices | completion: fully utilised as on 30 Nov 2023; Prospectus table garbled; repeated board/EGM decisions to change use and schedule (outcomes/approval not in packet). | 1 | 1 | — | — | — |
| RSRMSTEEL | 41,649 | 2,014 | 1,000,000,000 | 0 | 750,000,000 | 230,000,000 | 0 | 20,000,000 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | RSRMSTEEL_PROSPECTUS_2014 p.23 | 3 | — | — | 41,739 | 44,377 | — | 0 | Y | 44,012 | report date only | RSRMSTEEL_ANNUAL_2021 p.35 | completed, timing not measurable | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | completion: same statement in FY2020 report | 1 | 1 | 0 | — | — |
| SAIFPOWER | 41,649 | 2,014 | 360,000,000 | 280,752,465 | 0 | 66,163,215 | 0 | 13,084,320 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SAIFPOWER_PROSPECTUS_2014 p.16-17 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Only FY2017 audit-committee boilerplate in reported hits; no utilisation statement or announcements in packet. | 1 | 0 | — | — | — |
| SHURWID | 41,649 | 2,014 | 140,000,000 | 85,798,334 | 43,768,166 | 0 | 0 | 10,433,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SHURWID_PROSPECTUS_2014 pp.17-18 (page image) | 12 | — | — | 42,014 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | Prospectus table incomplete/scrambled; no reported/announcements in packet. | 1 | 0 | — | — | — |
| SPCL | 41,681 | 2,014 | 317,000,000 | 0 | 317,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | SPCL_PROSPECTUS_2014 p.15 | 1 | — | — | 41,709 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported utilisation or announcements in packet. | 1 | 0 | — | — | — |
| TUNGHAI | 41,648 | 2,014 | 350,000,000 | 115,500,000 | 160,000,000 | 53,690,000 | 0 | 20,810,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | TUNGHAI_PROSPECTUS_2014 p.22 | 6 | — | — | 41,829 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | first DSE trading day in day-end prices | No reported utilisation or announcements in packet. | 1 | 0 | — | — | — |
| AMANFEED | 42,248 | 2,015 | 720,000,000 | 350,000,000 | 50,538,633 | 299,176,867 | 0 | 20,284,500 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | AMANFEED_PROSPECTUS_2015 p.24 | — | — | — | — | — | — | — | N | — | — | AMANFEED_ANNUAL_2016 p.66 | unspent, deadline not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | No utilisation figures in packet hits. | 1 | 1 | — | — | — |
| BSRMLTD | 42,121 | 2,015 | 612,500,000 | 387,510,000 | 204,000,000 | 0 | 0 | 20,990,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | BSRMLTD_PROSPECTUS_2015 p.23 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported doc BSRMLTD_ANNUAL_2017 p.53 only lists heading 'Use of IPO Proceeds & Stages of Utilization' without numbers in the hit. | 1 | 0 | — | — | — |
| CNATEX | 42,025 | 2,015 | 450,000,000 | 123,147,996 | 308,762,254 | 0 | 0 | 18,089,750 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | CNATEX_PROSPECTUS_2015 p.24 | 18 | — | — | 42,572 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported hit (annual 2016 p.14) is unrelated risk text; no utilisation statement. | 1 | 0 | — | — | — |
| IFADAUTOS | 42,040 | 2,015 | 637,500,000 | 506,780,031 | 93,283,969 | 0 | 0 | 37,436,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | IFADAUTOS_PROSPECTUS_2015 p.25 | 12 | — | — | 42,405 | 42,916 | — | — | Y | 42,916 | stated completion date | IFADAUTOS_ANNUAL_2017 p.37; IFADAUTOS_ANNUAL_2016 p.38 | completed after deadline | 17 | 1 | 1 | 0 | EXT 2015-12-07: Extension of time period of utilisation of IPO proceeds approved with the re-allotment (wi [IFADAUTOS_ANNUAL_2016 p.38] | CHG 2015-12-07 (AGM (27th, 7 Dec 2015)): Re-allotment of IPO proceeds among Land Development, Building & Structure (Body Fabricatio [IFADAUTOS_ANNUAL_2016 p.38] | ipo_stats.csv listing_date | completion: FY2017: 'fully completed'; Revised-plan table is column-misaligned in OCR; revised amounts approximate. | 1 | 1 | — | 17 | — |
| KDSALTD | 42,292 | 2,015 | 240,000,000 | 150,000,000 | 70,000,000 | 0 | 0 | 20,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | KDSALTD_PROSPECTUS_2015 p.24 | — | — | — | — | 42,916 | — | — | Y | 42,621 | stated completion date | KDSALTD_ANNUAL_2017_DUP6594 p.6 | completed, timing not measurable | — | 0 | 1 | 0 | CHG 2016-09-01 (AGM (25th, 1 Sep 2016)): Remaining IPO account balance Tk 5,266,533 used to pay off bank liabilities (to reduce fin [KDSALTD_ANNUAL_2017_DUP6594 p.6] | ipo_stats.csv listing_date | completion: balance used 08 Sep 2016 | 1 | 1 | — | — | — |
| NFML | 42,023 | 2,015 | 180,000,000 | 81,790,000 | 71,262,811 | 9,408,689 | 0 | 17,538,500 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NFML_PROSPECTUS_2015 p.24 | — | — | — | — | 42,551 | — | 0 | Y | 42,551 | stated completion date | NFML_ANNUAL_2016 p.12; NFML_ANNUAL_2024_7 p.28 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 100% at 30 Jun 2016 | 1 | 1 | 0 | — | — |
| OAL | 42,180 | 2,015 | 200,000,000 | 185,500,000 | 0 | 0 | 0 | 14,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | OAL_PROSPECTUS_2015 p.25 | 18 | — | — | 42,729 | 42,643 | — | 0 | Y | 42,643 | stated completion date | OAL_ANNUAL_2016 p.13; OAL_ANNUAL_2017 p.13 | completed by deadline | — | 0 | 1 | 0 | CHG None (12th AGM): Revised allocation: construction of building Tk 154.28 million, machinery & equipment Tk 3 [OAL_ANNUAL_2016 p.13] | ipo_stats.csv listing_date | completion: fully utilised by 30 Sep 2016 | 1 | 1 | 0 | — | — |
| REGENTTEX | 42,352 | 2,015 | 1,250,000,000 | 1,223,183,482 | 0 | 0 | 0 | 26,816,518 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | REGENTTEX_PROSPECTUS_2015 p.20 | 18 | — | — | 42,900 | 44,012 | — | 0 | Y | 44,377 | report date only | REGENTTEX_ANNUAL_2020 p.58 (Annexure-M) | completed after deadline | 48 | 4 | 0 | 0 | EXT 2017-11-01: Board decided special resolution to extend IPO fund utilization time for BMRE up to Octobe [announcement 88705] | EXT 2018-11-04: Board decided special resolution to extend IPO fund utilization time up to June 2019 with [announcement 80416] | EXT 2019-07-02: Board decided EGM (29.08.2019) to revise and extend IPO proceeds utilization time up to De [announcement 181626] | EXT 2020-07-12: Board decided EGM (27.08.2020) special resolution to revise and extend IPO proceeds utiliz [announcement 174665] | ipo_stats.csv listing_date | completion: FY2021 report: fund utilised; Extensions are board decisions put to EGM; shareholder/BSEC approval outcomes not in packet. | 1 | 1 | 0 | 48 | — |
| SHASHADNIM | 42,068 | 2,015 | 1,750,000,000 | 1,540,000,000 | 182,290,000 | 0 | 0 | 27,710,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SHASHADNIM_PROSPECTUS_2015 p.23 | — | — | — | — | 45,838 | — | — | Y | — | — | SHASHADNIM_ANNUAL_2025 p.98 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported utilisation is a one-line compliance remark; no extensions/changes in packet. | 1 | 1 | — | — | — |
| SIMTEX | 42,331 | 2,015 | 600,000,000 | 316,229,000 | 200,000,000 | 65,271,000 | 0 | 18,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SIMTEX_PROSPECTUS_2015 p.26 | 12 | — | — | 42,697 | 43,281 | — | — | Y | 43,281 | stated completion date | SIMTEX_ANNUAL_2019 p.33; SIMTEX_ANNUAL_2018 p.13 | completed after deadline | 19 | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'utilized within 30.06.2018' | 1 | 1 | — | 19 | — |
| TOSRIFA | 42,172 | 2,015 | 638,721,200 | 598,999,481 | 0 | 0 | 0 | 19,931,719 | 19,790,000 | 0 | 0 | 1 | 0 | 0 | 0 | TOSRIFA_PROSPECTUS_2015 p.28 | — | — | — | — | 42,674 | — | 0 | Y | 43,010 | stated completion date | TOSRIFA_ANNUAL_2016_2 p.33 | completed, timing not measurable | — | 0 | 1 | 0 | CHG None (14th AGM): Utilisation by proper expense heads as per 14th AGM approved agenda (details not in packet [announcement 89902 / TOSRIFA_PSI_2017 p.1] | ipo_stats.csv listing_date | completion: board 2 Oct 2017: 'already utilized'; Total utilised figure stale (Oct 2016); full utilisation by Oct 2017 stated by company. | 1 | 1 | 0 | — | — |
| UPGDCL | 42,099 | 2,015 | 2,376,000,000 | 0 | 792,000,000 | 27,908,238 | 0 | 66,091,762 | 1,490,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | UPGDCL_PROSPECTUS_2014 p.28 | 3 | — | — | 42,190 | 42,551 | 2,044,922,352 | 331,077,648 | N | — | — | UPGDCL_ANNUAL_2016_2 p.43 | unspent after deadline | 12 | 0 | 1 | 0 | CHG 2016-12 (AGM special resolution (notice in FY2016 annual report, special business item 5)): Special resolution: unutilised IPO proceeds of Tk 331,077,648 to be used for financing wor [UPGDCL_ANNUAL_2016_2 p.93] | ipo_stats.csv listing_date | AGM resolution outcome/BSEC approval not in packet. | 1 | 1 | 0 | — | 12 |
| ACMELAB | 42,528 | 2,016 | 4,312,800,000 | 4,244,500,000 | 0 | 0 | 0 | 68,300,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ACMELAB_PROSPECTUS_2016 p.270 | 24 | — | — | 43,258 | 45,107 | — | — | Y | 44,592 | stated completion date | ACMELAB_ANNUAL_2023_2 p.52, p.63 | completed after deadline | 44 | 1 | 1 | 0 | EXT None: 46th AGM approved API project completion within June 2024 (originally June 2022) [ACMELAB_ANNUAL_2023_2 p.63] | CHG None (AGM (44th)): BDT 606,132,545 of IPO proceeds allocated only for civil construction of Active Pharmaceut [ACMELAB_ANNUAL_2023_2 p.63] | ipo_stats.csv listing_date | completion: 'entire fund duly utilized within January 2022'; Prospectus use-of-proceeds is for three pharma projects; later reallocated to API park per annual report. Item-level utilisation not extracted. | 1 | 1 | — | 44 | — |
| BNICL | 42,481 | 2,016 | 177,000,000 | 0 | 0 | 0 | 172,466,000 | 4,534,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | BNICL_PROSPECTUS_2016 p.22 | 3 | — | — | 42,572 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Prospectus identical for BNICL and BNIPLC (same document, duplicate key; ticker likely renamed). No reported docs in packet. Insurance company. | 1 | 0 | — | — | — |
| DOREENPWR | 42,466 | 2,016 | 558,980,000 | — | — | — | — | — | — | — | — | — | — | — | — | DOREENPWR_PROSPECTUS_2016 p.25, p.27 (also DOREENPWR_DOC_2024 p.25) | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Head-wise table not in packet pages; reported hits are the same prospectus text found in DOREENPWR_DOC_2024 (not utilisation statements). 9 PSI/annual docs listed but no statements extracted. | 0 | 0 | — | — | — |
| DSSL | 42,452 | 2,016 | 400,000,000 | — | — | — | — | — | — | — | — | — | — | — | — | DSSL_PROSPECTUS_2016 p.23, p.26 | 11 | — | — | 42,789 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 1 | — | ipo_stats.csv listing_date | Head-wise amounts missing from packet; no reported docs. Page-image check of prospectus pp.24-25 recommended. | 0 | 0 | — | — | — |
| ETL | 42,568 | 2,016 | 170,000,000 | 139,871,846 | 0 | 15,427,654 | 0 | 14,700,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ETL_PROSPECTUS_2016 p.137, p.143 | 18 | — | — | 43,117 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported hits (ETL annual 2017/2018) are unrelated notes; no utilisation statement. | 1 | 0 | — | — | — |
| FORTUNE | 42,663 | 2,016 | 220,000,000 | 202,340,000 | 0 | 0 | 0 | 17,660,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | FORTUNE_PROSPECTUS_2016 p.139 | 18 | — | — | 43,210 | 43,281 | — | — | Y | 43,281 | stated completion date | FORTUNE_ANNUAL_2018 p.13, p.62 | completed after deadline | 2 | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'completed in 2018'; reports till 30 Jun 2018; Reported amounts garbled; page-image check of FORTUNE_ANNUAL_2018 p.62 if figures needed. | 1 | 1 | — | 2 | — |
| ITC | 42,379 | 2,016 | 120,000,000 | 69,538,250 | 40,000,000 | 0 | 0 | 10,461,750 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ITC_PROSPECTUS_2016 p.25 | — | — | — | — | 45,838 | — | — | Y | — | — | ITC_ANNUAL_2025 p.87 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | — | 1 | 1 | — | — | — |
| AAMRANET | 43,010 | 2,017 | 562,500,000 | 346,874,345 | 185,921,482 | 0 | 0 | 29,704,173 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | AAMRANET_PROSPECTUS_2017 p.170 (text; image font unreadable) | 12 | — | — | 43,375 | 43,008 | — | — | — | — | — | AAMRANET_ANNUAL_2017 p.34 | no statement found | — | 0 | 2 | 0 | CHG 2018-10-24 (Board (AGM/BSEC pending)): Board decided to freeze unutilised Tk 3,952,298 (Tk 1,512,298 saved in BMRE/Data Center/Wi [announcement 80953] | CHG 2019-02-12 (BSEC): BSEC approved transfer of unutilised Tk 3,952,298 of IPO proceeds to head 'BMRE for infras [announcement 184184] | ipo_stats.csv listing_date | Digit-dropped OCR in proceeds table; reported statement is only the first-month (Sep 2017) one in packet. | 1 | 0 | — | — | — |
| BBSCABLES | 42,947 | 2,017 | 200,000,000 | 142,610,000 | 40,000,000 | 0 | 0 | 0 | 0 | 17,390,000 | 0 | 1 | 0 | 0 | 0 | BBSCABLES_PROSPECTUS_2017 p.160 | — | — | — | — | — | — | — | Y | — | — | BBSCABLES_ANNUAL_2024_3 p.44 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | — | 1 | 1 | — | — | — |
| NAHEEACP | 43,093 | 2,017 | 150,000,000 | 97,762,000 | 40,000,000 | 0 | 0 | 12,238,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | NAHEEACP_PROSPECTUS_2017 p.165 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported: FY2017 annual says IPO allotment 23 Oct 2017, fund not utilised at 30 Jun 2017; FY2024/2025 reports say no IPO fund for utilisation during the year. No utilisation statement in packet. Announcement 185104 (2019-01-14): company says it raised Tk 15.00 crore in 2017 for term loan repayment, | 1 | 0 | — | — | — |
| NURANI | 42,887 | 2,017 | 430,000,000 | 293,345,000 | 118,000,000 | 0 | 0 | 18,655,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | NURANI_PROSPECTUS_2017 p.147 (printed page 128) | — | — | — | — | 43,404 | — | — | Y | 43,404 | stated completion date | NURANI_ANNUAL_2020 p.12 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: by 31 Oct 2018 | 1 | 1 | — | — | — |
| OIMEX | 43,045 | 2,017 | 150,000,000 | 85,000,000 | 50,000,000 | 0 | 0 | 15,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | OIMEX_PROSPECTUS_2017 p.111 | 6 | — | — | 43,226 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported: FY2018/2019 annual reports only say IPO fund was utilised ("after proper utilization of IPO fund"); no numbers/dates in packet. | 1 | 0 | — | — | — |
| PDL | 42,773 | 2,017 | 750,000,000 | 479,380,000 | 250,000,000 | 0 | 0 | 20,620,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | PDL_ANNUAL_2017 p.57 (prospectus table not in packet) | — | — | — | — | 44,012 | — | 0 | Y | 44,012 | stated completion date | PDL_ANNUAL_2020 p.26 | completed, timing not measurable | — | 0 | 0 | 1 | — | ipo_stats.csv listing_date | completion: utilised up to 30 Jun 2020 per auditor; Machinery vs building split differs from prospectus-based promised (utilised 200,178,553 machinery vs 181,006,277; building 279,201,447 vs 298,373,723): possible reallocation, no approval documented in packet. | 1 | 1 | 0 | — | — |
| SHEPHERD | 42,802 | 2,017 | 200,000,000 | 140,535,766 | 44,464,234 | 0 | 0 | 15,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SHEPHERD_PROSPECTUS_2017 p.161 | 18 | — | — | 43,351 | 43,524 | 199,740,000 | 260,000 | N | — | — | SHEPHERD_DOC_2019_2 p.1,3 (auditor report Ahmed Zaker & Co.) | unspent after deadline | 6 | 1 | 1 | 1 | EXT 2018-12-19: 17th AGM approved revised IPO utilization plan with full-utilisation deadline extended to [SHEPHERD_DOC_2019_3 p.2; DOC_2019_2 p.3] | CHG 2017-11-07 (Board proposal; shareholders in general meeting (17th AGM 19 Dec 2018) and BSEC): Board proposed revised use of unutilised IPO funds Tk 114,576,375 (building 28,140,524; ET [announcement 88526] | ipo_stats.csv listing_date | 65 reported hits (monthly auditor reports); latest in packet is Feb 2019 statement. | 1 | 1 | 0 | — | 6 |
| ACFL | 43,318 | 2,018 | 800,000,000 | 663,375,000 | 101,625,000 | 0 | 0 | 35,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ACFL_PROSPECTUS_2018 p.173 | 6 | — | — | 43,502 | 45,838 | — | 717,498,337 | N | — | — | ACFL_ANNUAL_2025 p.66 | unspent after deadline | 77 | 3 | 0 | 2 | EXT 2021-11-16: Shareholders approved revised timeline for utilisation of IPO proceeds up to 31 August 202 [announcement 168401 / 55869] | EXT None: Shareholders approved extension of time for utilisation of unutilised fund to AGM of 2028 [ACFL_ANNUAL_2025 p.63] | EXT 2025-06-30: Shareholders approved revised timeline for fund utilisation up to 31 December 2028 [ACFL_ANNUAL_2025 p.66] | ipo_stats.csv listing_date | Earlier extension chain (to Aug 2023, then to Dec 2028) from announcements; qualified opinion on FDR pledge from IPO proceeds. | 1 | 1 | 1 | — | 77 |
| ADVENT | 43,202 | 2,018 | 200,000,000 | 181,500,000 | 0 | 0 | 0 | 18,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ADVENT_ANNUAL_2021 p.18 (as per prospectus; prospectus p.189 has only the schedule) | 18 | — | — | 43,750 | 44,377 | — | 0 | Y | 44,012 | stated completion date | ADVENT_ANNUAL_2021 p.18, p.77 | completed after deadline | 9 | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: utilised in full up to 30 Jun 2020 per auditor | 1 | 1 | 0 | 9 | — |
| BPML | 43,283 | 2,018 | 2,000,000,000 | 1,350,000,000 | 600,000,000 | 0 | 0 | 50,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | BPML_ANNUAL_2019 p.34 (schedule as in Prospectus dated 01/04/2018 p.211; prospectus page not in packet) | 24 | — | — | 44,014 | 43,343 | — | 0 | Y | 43,343 | stated completion date | BPML_ANNUAL_2019 p.34; BPML_PSI_2019 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 100% by August 2018 | 1 | 1 | 0 | — | — |
| IBP | 43,391 | 2,018 | 200,000,000 | 183,300,000 | 0 | 0 | 0 | 16,700,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | IBP_PROSPECTUS_2018 p.173 | 24 | — | — | 44,122 | 44,012 | — | 0 | Y | 44,012 | stated completion date | IBP_ANNUAL_2020 p.39, p.90 | completed by deadline | — | 1 | 1 | 0 | EXT None: Fund utilisation period for construction and other civil works extended from 18 to 24 mont [IBP_ANNUAL_2020 p.39] | CHG 2020-01-06 (AGM (5th)): Proposal at 5th AGM to use Tk 58,580,000 of IPO proceeds to purchase machineries instead o [announcement 177127] | ipo_stats.csv listing_date | completion: 'fully utilized ... up to June 30, 2020' | 1 | 1 | 0 | — | — |
| INTRACO | 43,237 | 2,018 | 300,000,000 | 279,600,000 | 0 | 0 | 0 | 20,400,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | INTRACO_PROSPECTUS_2018 p.198 (item amounts from INTRACO_DOC_2020 p.21 'as per prospectus') | — | — | — | — | 44,104 | 341,759,160 | — | — | — | — | INTRACO_DOC_2020 p.21 | no statement found | — | 0 | 2 | 1 | CHG 2018-10-29 (Board; AGM 23.12.2018): Change of project location: LPG bottling plant at Patenga, Chittagong instead of Gojaria, [announcement 80648] | CHG 2019-10-28 (AGM (12th, 24.12.2019)): Board changed earlier decision (Patenga bottling plant) and decided to purchase a newly bu [announcement 179185] | ipo_stats.csv listing_date | Many INTRACO docs; later (2021+) utilisation statement not in packet hits. Prospectus head-wise table page not in packet pages. | 1 | 0 | — | — | — |
| KTL | 43,416 | 2,018 | 340,000,000 | 295,876,000 | 25,000,000 | 0 | 0 | 19,124,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | KTL_PROSPECTUS_2018 p.141 | 24 | — | — | 44,147 | 44,377 | 126,063,875 | 213,936,125 | N | — | — | KTL_ANNUAL_2021 p.15 | unspent after deadline | 8 | 1 | 0 | 1 | EXT 2021-11-23: Board decided to apply to BSEC for time extension of IPO fund utilization; shareholder app [announcement 69072] | ipo_stats.csv listing_date | — | 1 | 1 | 1 | — | 8 |
| MLDYEING | 43,360 | 2,018 | 200,000,000 | 178,300,000 | 0 | 0 | 0 | 21,700,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | MLDYEING_PROSPECTUS_2018 p.173 (printed page 158) | — | — | — | — | 45,838 | — | 0 | Y | 44,194 | stated completion date | MLDYEING_ANNUAL_2025 p.23 | completed, timing not measurable | — | 0 | 1 | 1 | CHG None (AGM (18th)): Revised utilization of IPO fund approved at 18th AGM (details not in packet) [announcement 77526] | ipo_stats.csv listing_date | completion: DSE post 29 Dec 2020: rest utilised; Announcement amounts (69,602,488 / 130,397,512) differ slightly from annual report (69,587,488 / 130,412,512) due to LC refund treatment. | 1 | 1 | 0 | — | — |
| QUEENSOUTH | 43,172 | 2,018 | 150,000,000 | 130,656,084 | 6,343,916 | 0 | 0 | 13,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | QUEENSOUTH_PROSPECTUS_2018 p.193 | 12 | — | — | 43,537 | 43,890 | 69,371,787 | 80,628,213 | N | — | — | QUEENSOUTH_DOC_2020_4 p.1,2 and DOC_2020_3 p.3 | unspent after deadline | 12 | 2 | 1 | 2 | EXT 2018-12-27: Time frame for utilization of IPO proceeds extended (1st time) up to 31 October 2019 [QUEENSOUTH_DOC_2020_4 p.2 (16th AGM 27 Dec 2018)] | EXT 2019-12-22: Time frame extended (2nd time) up to 30 June 2020 [QUEENSOUTH_DOC_2020_4 p.2 (17th AGM)] | CHG 2019-12-22 (17th AGM 22 Dec 2019; BSEC approval pending per auditor): Revised IPO utilization plan: purchased natural gas engine generator set instead of 1 set [announcements 174349, 179108; QUEENSOUTH_DOC_2020_4 p.2] | ipo_stats.csv listing_date | — | 1 | 1 | 1 | — | 12 |
| SILVAPHL | 43,383 | 2,018 | 300,000,000 | 178,500,000 | 99,000,000 | 0 | 0 | 22,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SILVAPHL_PROSPECTUS_2018 p.235 (printed page 218) | — | — | — | — | 45,838 | 271,817,362 | 28,182,638 | N | — | — | SILVAPHL_ANNUAL_2025 p.44,45 | unspent, deadline not measurable | — | 3 | 2 | 0 | EXT 2022-12-29: 21st AGM approved extension of IPO proceeds utilization up to December 31, 2023 (reason CO [announcement 54139] | EXT 2023-12-28: Board (13 Nov 2023) decided to extend utilization time up to December 31, 2024, subject to [announcements 41982, 41981] | EXT 2024-12: 23rd AGM extended time for utilization of IPO proceeds up to December 31, 2025 [announcement 27383 (2025-01-01)] | CHG 2025-11-16 (EGM 30.12.2025 and BSEC (proposed)): Board decisions subject to EGM 30.12.2025 and BSEC: change of company name, post-facto app [announcement 16471; SILVAPHL_ANNUAL_2025 p.45] | CHG None (18th AGM): Revised estimated amounts per 18th AGM: civil construction 58,058,526; IPO expenses 20,441 [SILVAPHL_ANNUAL_2025 p.44] | ipo_stats.csv listing_date | Company later renamed (EGM 30.12.2025). | 1 | 1 | 0 | — | — |
| SKTRIMS | 43,296 | 2,018 | 300,000,000 | 276,180,000 | 0 | 0 | 0 | 23,820,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SKTRIMS_PROSPECTUS_2018 p.200 (printed page 183) | 18 | 44,087 | Y | 44,087 | 44,012 | 147,889,570 | 152,110,430 | N | — | — | SKTRIMS_ANNUAL_2020 p.20,50 | unspent after deadline | — | 2 | 1 | 1 | EXT 2019-12-29: First revision at 5th AGM: last date reset from December 13, 2019 to September 13, 2020 (2 [SKTRIMS_ANNUAL_2020 p.51] | EXT 2020-09-13: Board decided to extend IPO fund utilization period up to 30 June 2021 (deadline of 13 Sep [SKTRIMS_ANNUAL_2020 p.20] | CHG 2020-11-30 (Board; subject to AGM approval): Tk. 127,267,972 under Acquisition of machineries and equipment to be used for capital mach [announcement 77658; SKTRIMS_ANNUAL_2020 p.20] | ipo_stats.csv listing_date | printed deadline: SKTRIMS_ANNUAL_2020 pp.20, 50; deadline missed per auditor: SKTRIMS_ANNUAL_2020 p.50 | 1 | 1 | 1 | — | — |
| VFSTDL | 43,352 | 2,018 | 220,000,000 | 177,403,108 | 25,092,728 | 0 | 0 | 17,504,164 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | VFSTDL_PROSPECTUS_2018 p.146 (printed page 130) and p.154 | 18 | — | — | 43,899 | 45,838 | — | 0 | Y | 43,465 | stated completion date | VFSTDL_ANNUAL_2025 p.19 (same in FY2018-FY2024 reports) | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'started and completed in 2018' | 1 | 1 | 0 | — | — |
| COPPERTECH | 43,682 | 2,019 | 200,000,000 | 120,000,000 | 65,000,000 | 0 | 0 | 0 | 0 | 15,000,000 | 0 | 1 | 0 | 0 | 0 | COPPERTECH_PROSPECTUS_2019 p.110 | 12 | — | — | 44,048 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported hits (2021-2025 annuals) only show compliance checklist 5(5)(m) 'Not applicable'; no utilisation statement. | 1 | 0 | — | — | — |
| ESQUIRENIT | 43,564 | 2,019 | 1,500,000,000 | 1,435,611,500 | 0 | 0 | 0 | 64,388,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ESQUIRENIT_PROSPECTUS_2019 p.249, p.227 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 1 | 0 | 0 | EXT 2020-07-30: Board decided EGM (14.09.2020) to enhance IPO fund utilisation schedule time and amend fun [announcement 174121] | ipo_stats.csv listing_date | Annual report utilisation statement not in packet hits. | 1 | 0 | — | — | — |
| GENEXIL | 43,502 | 2,019 | 200,000,000 | 123,000,000 | 60,000,000 | 0 | 0 | 17,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | GENEXIL_PROSPECTUS_2019 p.181 | — | — | — | — | 44,012 | — | — | Y | 43,646 | report date only | GENEXIL_ANNUAL_2020 p.56; GENEXIL_ANNUAL_2019 p.57 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'fully utilized in the previous year' (FY2019) | 1 | 1 | — | — | — |
| NEWLINE | 43,612 | 2,019 | 300,000,000 | 194,065,650 | 90,000,000 | 0 | 0 | 15,934,350 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | NEWLINE_PROSPECTUS_2019 p.159 | — | — | — | — | 44,377 | 208,672,547 | 91,327,453 | N | — | — | NEWLINE_ANNUAL_2021 p.27 | unspent, deadline not measurable | — | 0 | 1 | 0 | CHG 2019-12-10 (AGM 30 Dec 2019 and BSEC letter BSEC/CFD/95/2020/64 dated July 05, 2020): Revised IPO utilization plan (details not in packet); board 10 Dec 2019, shareholders appr [NEWLINE_ANNUAL_2021 p.26] | ipo_stats.csv listing_date | Delays attributed by company to Covid lockdowns. | 1 | 1 | 0 | — | — |
| RINGSHINE | 43,811 | 2,019 | 1,500,000,000 | 964,000,000 | 500,000,000 | 0 | 0 | 36,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | RINGSHINE_PROSPECTUS_2019 p.275 (printed page 260) | — | 44,291 | — | 44,291 | 45,473 | 1,219,397,757 | 280,602,243 | N | — | — | RINGSHINE_DOC_2024_12 p.2,3,5 (auditor yearly certificate Jul 2023-Jun 2024) | unspent after deadline | 39 | 1 | 4 | 2 | EXT 2024-12-18: 27th AGM accorded extension of time of 1 more year for utilizing the IPO fund from date of [RINGSHINE_DOC_2024_8 p.1] | CHG 2021-05-20 (BSEC (letter 20 May 2021); AGM post-facto approval): BSEC approved withdrawal of BDT 40 crore of IPO proceeds from BRAC Bank PLC for amended pu [announcement 74783; RINGSHINE_DOC_2024_7 p.1; RINGSHINE_DOC_2024_12 p.3] | CHG 2023-04-18 (BSEC letter BSEC/SRMIC/153/2019/108 to BRAC Bank PLC dated April 18, 2023): BSEC allowed withdrawal of BDT 18.40 crore of remaining IPO fund (fourth approval) [RINGSHINE_DOC_2024_12 p.3] | CHG 2024-12-18 (27th AGM 18 Dec 2024): AGM approved changed/amended purposes for withdrawing USD 3.6 Million from BRAC Bank PLC w [RINGSHINE_DOC_2024_8 p.1] | CHG 2025-07-20 (BSEC (rejection)): BSEC rejected the application for releasing IPO fund of USD 1.00 Million [announcement 21162] | ipo_stats.csv listing_date | printed deadline: RINGSHINE_DOC_2024_12 p.3; Large packet (74 hits). Latest statement used is the Jul 2023-Jun 2024 yearly certificate; later quarterly reports not examined in detail. One point: the auditor wording says the company failed to provide copy of an application/approval letter for one approval. | 1 | 1 | 0 | — | 39 |
| RUNNERAUTO | 43,606 | 2,019 | 1,000,000,000 | 630,000,000 | 330,000,000 | 0 | 0 | 40,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | RUNNERAUTO_PROSPECTUS_2019 p.212 | — | — | — | — | 44,012 | — | — | — | — | — | RUNNERAUTO_ANNUAL_2020 p.86; RUNNERAUTO_ANNUAL_2019 p.139 | no statement found | — | 1 | 1 | 1 | EXT 2021-11-11: Board (163rd meeting) decided to extend time for utilization of IPO proceeds up to Decembe [announcement 70134] | CHG 2019-12-17 (Board 28 Oct 2019; 6th EGM 17 Dec 2019; BSEC approval 24 Feb 2020): Revised use of IPO proceeds BDT 63 crore (chassis welding line 12.18 crore, body welding l [announcements 179111, 176047, 173284] | ipo_stats.csv listing_date | Promised table amounts (330m loan + 40m expenses + 630m expansion) consistent with auditors. Conversion: 63 crore = 630,000,000. | 1 | 0 | — | — | — |
| SEAPEARL | 43,662 | 2,019 | 150,000,000 | 133,487,300 | 0 | 0 | 0 | 16,512,700 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SEAPEARL_PROSPECTUS_2019 p.187 | — | — | — | — | 44,027 | — | 0 | Y | 44,027 | stated completion date | SEAPEARL_ANNUAL_2021 p.37,133; SEAPEARL_ANNUAL_2022 p.41 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: completed by 15 Jul 2020 | 1 | 1 | 0 | — | — |
| SILCOPHL | 43,629 | 2,019 | 300,000,000 | 278,321,552 | 0 | 0 | 0 | 21,678,448 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SILCOPHL_PROSPECTUS_2019 p.178 (printed page 165) | 20 | — | — | 44,240 | 44,377 | — | 0 | Y | 44,196 | stated completion date | SILCOPHL_ANNUAL_2021 p.18 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'completed in the year of 2020'; Inconsistency: FY2020 says utilisation completed in 2020 but only 60.9m utilised at 30 Jun 2020; FY2021 says full 300m utilised by 30 Jun 2021; FY2022 says nearly completed. | 1 | 1 | 0 | — | — |
| SSSTEEL | 43,482 | 2,019 | 250,000,000 | 229,432,500 | 0 | 0 | 0 | 20,567,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | SSSTEEL_PROSPECTUS_2018 p.240 | — | — | — | — | 44,592 | 71,627,824 | 178,372,176 | N | — | — | SSSTEEL_DOC_2022_14 p.4,5 (auditor Shiraz Khan Basak & Co, 17 Feb 2022); Feb 2022 certificate SSSTEEL_DOC_2022_15 p.4 shows same IPO expenses and building figures | unspent, deadline not measurable | — | 2 | 1 | 0 | EXT 2020-09-06: Board proposed extension of IPO proceeds utilization/implementation schedule up to April 2 [announcement 173458] | EXT 2021-06-20: Board resolution extended utilization time to October 2021 (per auditor) [SSSTEEL_DOC_2022_14 p.5] | CHG 2022-07-12 (EGM proposed 3 Sep 2022): Board decided EGM (03.09.2022) for proposed revision of utilization plan of unutilized IPO [announcement 61535] | ipo_stats.csv listing_date | Packet for SSSTEEL_PROSPECTUS_2018 and SSSTEEL_PROSPECTUS_2019 are identical (95 reported hits); unutilised funds remained large at Feb 2022, later annual reports (FY2022-2024) not examined in detail. | 1 | 1 | 1 | — | — |
| ADNTEL | 43,836 | 2,020 | 570,000,000 | 419,896,627 | 120,603,373 | 0 | 0 | 29,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ADNTEL_PROSPECTUS_2019 p.209 | 12 | — | — | 44,202 | 44,742 | 385,036,911 | 184,963,089 | N | — | — | ADNTEL_ANNUAL_2022 p.8, p.42 | unspent after deadline | 18 | 3 | 1 | 0 | EXT 2020-10-28: Board decided to hold EGM to extend IPO fund utilisation timeline (EGM/AGM 24.12.2020) [announcement 172276] | EXT 2021-04-13: BSEC approved alteration of use and time extension: Data Center balance BDT 32,632,813 ext [announcement 75795; ADNTEL_ANNUAL_2022 p.42] | EXT 2022-12-07: 19th AGM approved extension of BMRE-related unutilised IPO proceeds to 31 December 2023 [announcements 54756/54757] | CHG 2022-12-07 (AGM (19th, 7 Dec 2022), subject to BSEC): Unutilised BMRE allocation rearranged from BDT 184,963,089 to BDT 84,963,089; of remaining [announcements 54757, 54756, 57381] | ipo_stats.csv listing_date | — | 1 | 1 | 0 | — | 18 |
| AOL | 44,129 | 2,020 | 150,000,000 | 110,556,500 | 20,000,000 | 0 | 0 | 19,443,500 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | AOL_PROSPECTUS_2020 p.141, p.144 | 24 | — | — | 44,859 | 44,742 | 111,848,532 | 38,151,468 | N | — | — | AOL_ANNUAL_2022 p.80 (Annexure-03) | unspent, deadline not yet passed at statement | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | 16 announcements in packet are routine auditor-report notices (no extension/change news). | 1 | 1 | 0 | — | — |
| CRYSTALINS | 44,186 | 2,020 | 160,000,000 | 0 | 0 | 0 | 149,271,500 | 10,728,500 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | CRYSTALINS_PROSPECTUS_2020 p.219, p.221 | 3 | — | — | 44,276 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | No reported docs in packet. Insurance company. | 1 | 0 | — | — | — |
| DOMINAGE | 44,167 | 2,020 | 300,000,000 | 280,424,000 | 0 | 0 | 0 | 0 | 0 | 19,576,000 | 0 | 1 | 0 | 0 | 0 | DOMINAGE_PROSPECTUS_2020 p.148, p.152 | 24 | — | Y | 44,897 | 45,473 | 164,406,000 | — | N | — | — | DOMINAGE_ANNUAL_2024 p.2 (auditor: 'not utilized within the stipulated time'); last figures DOMINAGE_PSI_2022 p.1 (BDT 138,663,251 unspent at 31-Oct-2022) | unspent after deadline | — | 2 | 1 | 2 | EXT 2022-11-19: Company applied to BSEC for 15 months extension (to March 2024) for utilisation of remaini [DOMINAGE_PSI_2022 p.1-2] | EXT 2023-06-30: Further time extension taken from BSEC (per auditor); by FY2024 audit report company appli [DOMINAGE_ANNUAL_2023 p.2; DOMINAGE_ANNUAL_2024 p.2] | CHG 2021-12-23 (AGM (15th) and concerned authorities, subject to approval): Change of use of net IPO proceeds: total changed from BDT 280,424,000 to BDT 285,493,250; [announcement 68061] | first DSE trading day in day-end prices | deadline missed per auditor: DOMINAGE_ANNUAL_2024 p.2; Reported 'promised' amounts are rescheduled (not original prospectus). | 1 | 1 | — | — | — |
| EIL | 44,067 | 2,020 | 260,790,000 | 0 | 0 | 0 | 245,790,000 | 15,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | EIL_PROSPECTUS_2020 p.179, p.181 | 9 | — | — | 44,340 | 44,196 | — | — | Y | 44,196 | report date only | EIL_ANNUAL_2020 p.28 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 'within the scheduled time'; Annual 2020 p.27 vs p.28 mildly contradictory on utilisation. Insurance company. | 1 | 1 | — | — | — |
| ROBI | 44,189 | 2,020 | 5,237,933,340 | 5,157,723,574 | 0 | 0 | 0 | 80,209,766 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ROBI_PROSPECTUS_2020 p.247 (printed page 230) | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 1 | 0 | CHG 2021-12-09 (EGM proposed (24 Jan 2022)): Board decided to hold EGM (24.01.2022) for approval of amendment of IPO proceeds utilizati [announcement 68488] | ipo_stats.csv listing_date | Reported: FY2021/2023 reports say Audit Committee reviewed utilisation of IPO proceeds; no amounts in packet. Prospectus timeline not in packet. | 1 | 0 | — | — | — |
| WALTONHIL | 44,097 | 2,020 | 1,000,000,000 | 625,000,000 | 330,000,000 | 0 | 0 | 45,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | WALTONHIL_PROSPECTUS_2020 p.406 | 24 | — | — | 44,827 | 45,838 | — | — | Y | — | — | WALTONHIL_ANNUAL_2025 p.315 (also FY2024 p.285) | completed, timing not measurable | — | 0 | 1 | 0 | CHG 2021-07-14 (EGM 14 July 2021 (shareholders), BSEC letter dated May 11, 2021): Rearrangement of BMRE use of IPO proceeds: new machinery list (Annexure-B); BMRE funds 625 [announcements 74201, 169290; WALTONHIL_DOC_2021 p.2] | ipo_stats.csv listing_date | — | 1 | 1 | — | — | — |
| ACMEPL | 44,514 | 2,021 | 300,000,000 | 226,499,000 | 55,000,000 | 0 | 0 | 18,501,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ACMEPL_PROSPECTUS_2021 p.145 | 24 | — | — | 45,244 | 46,112 | — | — | N | — | — | ACMEPL_QUARTERLY_Q3_2026 p.27 | unspent after deadline | 28 | 3 | 0 | 0 | EXT 2024-06-06: Board decided to extend time of utilisation of IPO proceeds up to June 30, 2025 subject to [announcement 34751 (2024-06-09)] | EXT 2025-06-23: Board to consider BSEC consent letter extending time for IPO proceeds utilisation from 1 J [announcement 21876] | EXT 2025-12-22: Company submitted PSI with EGM resolution regarding further extension of time for utilisat [announcement 14155] | ipo_stats.csv listing_date | Reported utilised amounts not cleanly readable (garbled table) in packet. | 1 | 1 | — | — | 28 |
| BPPL | 44,392 | 2,021 | 2,250,000,000 | 0 | 748,725,000 | 0 | 1,443,300,000 | 57,975,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | BPPL_PROSPECTUS_2021 p.166 | 6 | — | — | 44,576 | 44,469 | — | 0 | Y | 44,469 | stated completion date | BPPL_DOC_2021_12 p.1 | completed by deadline | — | 0 | 0 | 1 | — | ipo_stats.csv listing_date | completion: auditor statement to 30 Sep 2021 | 1 | 1 | 0 | — | — |
| DGIC | 44,284 | 2,021 | 160,000,000 | 0 | 0 | 0 | 150,433,500 | 9,566,500 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | DGIC_PROSPECTUS_2021 p.231, p.232 | 3 | — | — | 44,376 | 45,291 | — | — | Y | 45,291 | report date only | DGIC_ANNUAL_2023 p.50 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: FY2023: 'fully utilized'; Insurance company. | 1 | 1 | — | — | — |
| EGEN | 44,250 | 2,021 | 150,000,000 | 98,389,000 | 34,000,000 | 0 | 0 | 17,611,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | EGEN_PROSPECTUS_2021 p.177, p.181 | 24 | — | — | 44,980 | 44,377 | 51,427,663 | — | N | — | — | EGEN_ANNUAL_2021 p.88 | unspent, deadline not yet passed at statement | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | — | 1 | 1 | — | — | — |
| EPGL | 44,215 | 2,021 | 1,500,000,000 | 959,868,493 | 500,000,000 | 0 | 0 | 40,131,508 | 0 | 0 | 1 | 1 | 0 | 0 | 0 | EPGL_PROSPECTUS_2021 p.243, p.247 | 18 | — | — | 44,761 | 44,592 | — | — | Y | 44,592 | stated completion date | EPGL_ANNUAL_2025 p.39 (same table repeated in annual 2024 p.35) | completed by deadline | — | 0 | 1 | 0 | CHG 2021-07-15 (Board; subject to BSEC approval (final approval not in packet)): Board agreed to import readily available empty LPG cylinders with standard valve instead o [announcement 168669] | ipo_stats.csv listing_date | completion: table as on 31 Jan 2022; Reported statement is dated Jan 2022 but printed in annual 2024/2025; the unit is overall fully utilised. | 1 | 1 | — | — | — |
| INDEXAGRO | 44,293 | 2,021 | 500,000,000 | 475,000,000 | 0 | 0 | 0 | 25,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | INDEXAGRO_PROSPECTUS_2021 p.178 | — | — | — | — | 45,127 | — | 268,795,244 | N | — | — | INDEXAGRO_PSI_2023_3 / PSI_2023_5 | unspent, deadline not measurable | — | 1 | 2 | 0 | EXT 2023-05-25: Board decided to extend 12 more months from current expiry for utilising unspent IPO proce [announcement 48558; INDEXAGRO_PSI_2023_5] | CHG 2021-12-09 (AGM (21st); BSEC (Tk 138,500,000, 2023-01-17)): AGM approved repayment of partial short-term loan of Tk 354,932,100 from IPO proceeds (BSE [announcement 68481; INDEXAGRO_PSI_2023_3] | CHG 2023-07-20 (EGM (20 July 2023)): EGM approved use of unspent IPO proceeds Tk 268,795,244 for building & civil construction [INDEXAGRO_PSI_2023_5] | ipo_stats.csv listing_date | — | 1 | 1 | 1 | — | — |
| LOVELLO | 44,237 | 2,021 | 300,000,000 | 182,000,000 | 90,000,000 | 0 | 0 | 28,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | LOVELLO_PROSPECTUS_2021 p.152 | — | 44,957 | — | 44,957 | 45,581 | — | 0 | Y | 45,581 | stated completion date | LOVELLO_ANNUAL_2025 p.61 | completed after deadline | 20 | 3 | 2 | 2 | EXT 2022-12-26: Company applied to BSEC for 1st extension of 12 months up to 31 Jan 2024 and to use Tk 65 [LOVELLO_ANNUAL_2025 p.63] | EXT 2023-12-30: 12th AGM approved extension of one year from Feb 2024 to Jan 2025 for utilizing rest of IP [announcement 40315 (2024-01-01)] | EXT None: Company applied to BSEC for 2nd extension of 12 months up to 31 Jan 2025; not approved by [LOVELLO_ANNUAL_2025 p.63] | CHG 2021-12-28 (AGM (10th AGM, 28 Dec 2021)): Plant & Machinery: instead of Cone Baking Machine, procure Rollo Stick Ice-cream Machine a [announcement 67926] | CHG 2022-12-26 (not approved by BSEC per auditor): Tk 65 lac to be used for vehicle purchase instead of Investment in depot (applied to BSEC; [LOVELLO_ANNUAL_2025 p.63] | ipo_stats.csv listing_date | completion: statement up to 16 Oct 2024; printed deadline: LOVELLO_ANNUAL_2025 p.63 | 1 | 1 | 0 | 20 | — |
| LRBDL | 44,264 | 2,021 | 1,500,000,000 | 980,000,000 | 460,430,282 | 0 | 0 | 59,569,718 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | LRBDL_PROSPECTUS_2021 p.193 | 24 | — | — | 44,994 | 45,838 | — | 131,000,000 | N | — | — | LRBDL_ANNUAL_2025_2 p.2 (auditor's report) | unspent after deadline | 28 | 0 | 2 | 1 | CHG 2021-10-21 (BSEC (relocation permission)): BMRE project revised to BDT 996,396,045 funded by IPO proceeds plus interest income (16,39 [announcement 71585; LRBDL_PSI_2023 p.1] | CHG 2026-06-10 (EGM proposed (BSEC approval requested)): Proposed use of about Tk 20 crore idle IPO fund: LC/payment USD 364,811 (BDT 45,601,375) f [announcement 6621] | ipo_stats.csv listing_date | Unspent 13.10 crore converted to 131,000,000 BDT (1 crore = 10,000,000). Latest statement is an auditor qualified opinion, not a table. | 1 | 1 | 0 | — | 28 |
| MIRAKHTER | 44,229 | 2,021 | 1,250,000,000 | 815,000,000 | 400,000,000 | 0 | 0 | 35,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | MIRAKHTER_PROSPECTUS_2021 p.188 | — | — | — | — | 45,260 | — | 0 | Y | 45,260 | stated completion date | MIRAKHTER_PSI_2023 p.2,7 | completed, timing not measurable | — | 0 | 2 | 0 | CHG 2022-03-10 (EGM 10 Mar 2022 and BSEC consent (letter May 18, 2022)): Amendment/re-allocation of unspent IPO proceeds (heavy equipment/aggregate plant to other [MIRAKHTER_PSI_2023 p.2; announcement 66883] | CHG 2022-11-14 (Board; AGM/BSEC pending): Board decided to further amend use of IPO proceeds subject to 42nd AGM and BSEC approval [announcement 56447] | ipo_stats.csv listing_date | completion: auditor 14 Dec 2023; Amount strings from OCR; 1,250,029,598 total utilised printed by auditor (exceeds 1,250,000,000 by interest/own source). | 1 | 1 | 0 | — | — |
| NRBCBANK | 44,277 | 2,021 | 1,200,000,000 | 0 | 0 | 0 | 1,160,523,624 | 39,476,376 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | NRBCBANK_PROSPECTUS_2021 p.313 and p.312 (printed page 296) | 6 | — | — | 44,461 | 44,408 | — | 0 | Y | 44,408 | stated completion date | NRBCBANK_DOC_2021_2 p.2,3 | completed by deadline | — | 0 | 0 | 1 | — | ipo_stats.csv listing_date | completion: completed up to 31 Jul 2021 | 1 | 1 | 0 | — | — |
| SBACBANK | 44,419 | 2,021 | 1,000,000,000 | 0 | 0 | 0 | 951,854,136 | 48,145,864 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | SBACBANK_PROSPECTUS_2021 p.371 and p.373 | 3 | — | — | 44,511 | 44,561 | — | 0 | Y | 44,561 | report date only | SBACBANK_ANNUAL_2021 p.105 and p.288 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: FY2021: 100% | 1 | 1 | 0 | — | — |
| SIPLC | 44,507 | 2,021 | 160,000,000 | 0 | 0 | 0 | 149,000,000 | 11,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | SIPLC_PROSPECTUS_2021 p.224 (printed page 210) and p.220 | 6 | — | — | 44,688 | 45,657 | — | — | Y | 44,926 | stated completion date | SIPLC_ANNUAL_2024_2 p.10 | completed after deadline | 8 | 0 | 2 | 1 | CHG 2022-07-26 (BSEC): BSEC consented to utilise the remaining IPO expenses fund of BDT 4,725,424 (47,25,424) to [announcement 61138] | CHG 2023-03-15 (AGM approval to be taken): Auditor emphasis of matter: use of IPO funds as consented by BSEC for which the company wi [announcement 51553] | ipo_stats.csv listing_date | completion: 'fully utilized in 2022'; Insurer; announcements titled SKICL. | 1 | 1 | — | 8 | — |
| SONALILIFE | 44,377 | 2,021 | 190,000,000 | 0 | 0 | 0 | 178,000,000 | 12,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | SONALILIFE_PROSPECTUS_2021 p.207 and p.208 | 1 | — | — | 44,407 | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | Reported hits are only audit-committee compliance rows ("Oversee whether IPO proceeds utilized as per the published Prospectus"); no utilisation statement in packet. | 1 | 0 | — | — | — |
| BDTHAIFOOD | 44,585 | 2,022 | 150,000,000 | 139,000,000 | 0 | 0 | 0 | 11,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | BDTHAIFOOD_PROSPECTUS_2022 p.279 | 24 | — | — | 45,315 | 45,838 | — | — | Y | 45,838 | report date only | BDTHAIFOOD_ANNUAL_2025_2 p.17 | completed after deadline | 17 | 1 | 3 | 0 | EXT 2024-05-27: Board decided 4th EGM (14 July 2024) for changes in use of IPO proceeds and extension of t [announcement 35152; BDTHAIFOOD_ANNUAL_2024 p.17] | CHG 2022-03-20 (EGM (2nd, 9 May 2022); BSEC approved alteration (announcement 2022-07-03)): Tunnel oven worth BDT 28,475,000 in prospectus to be replaced: rotary oven and packing mac [announcements 65159, 65157, 61652] | CHG 2022-10-27 (EGM (3rd, 14 Dec 2022)): Further EGM for changing use of IPO proceeds because machinery prices rose ~35%; 3rd EGM 1 [announcement 57919; BDTHAIFOOD_ANNUAL_2024 p.17] | CHG 2024-07-14 (EGM (4th)): Shareholders revised unutilised amount Tk 39,982,049 and extended time [BDTHAIFOOD_ANNUAL_2024 p.17] | ipo_stats.csv listing_date | completion: FY2025: total IPO fund utilised | 1 | 1 | — | 17 | — |
| CLICL | 44,864 | 2,022 | 150,000,000 | 0 | 0 | 0 | 139,000,000 | 11,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | CLICL_PROSPECTUS_2022 p.272, p.273 | 9 | — | — | 45,137 | 45,107 | — | 0 | Y | 45,107 | stated completion date | CLICL_PSI_Q3_2023 p.2 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: auditor status at 30 Jun 2023; Insurance company (life). | 1 | 1 | 0 | — | — |
| GIB | 44,881 | 2,022 | 4,250,000,000 | 0 | 0 | 0 | 4,185,000,000 | 65,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | GIB_PROSPECTUS_2022 p.323, p.326 | 24 | — | — | 45,612 | 45,838 | — | 738,198,032 | N | — | — | announcement 20006 (statement for quarter ended 30 June 2025) | unspent after deadline | 7 | 3 | 1 | 0 | EXT 2024-04-29: Board decided to extend additional 24 months for utilisation of remaining IPO proceeds til [announcement 36262] | EXT 2025-07-09: Board decided again to extend 24 months to November 09, 2026 and to transfer remaining IPO [announcement 21454] | EXT 2025-10-19: BSEC approved modification of use of IPO proceeds with time extension till November 09, 20 [announcement 18230] | CHG 2025-08-19 (AGM; BSEC approval 2025-10-19): Shareholders (AGM 19 Aug 2025, date corrected in announcement 20005) approved transfer of [announcements 20006, 20005, 18230] | ipo_stats.csv listing_date | Bank. Timing of the first extension announcement (2024-04-29 vs 2025-07-09) may reflect repetition; both state the same new deadline. | 1 | 1 | 0 | — | 7 |
| ICICL | 44,913 | 2,022 | 202,611,060 | 0 | 0 | 0 | 193,283,373 | 9,327,687 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | ICICL_PROSPECTUS_2022 p.259, p.264 | 3 | — | — | 45,003 | 44,926 | — | — | Y | 44,926 | report date only | ICICL_ANNUAL_2022 p.27 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: FY2022: 'fully utilized'; Insurance company; annual text prints prospectus IPO expense as 9,327,684 vs 9,327,687 in table. | 1 | 1 | — | — | — |
| JHRML | 44,651 | 2,022 | 750,000,000 | 458,700,000 | 250,000,000 | 0 | 0 | 41,300,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | JHRML_PROSPECTUS_2022 p.211 (in BDT crore; also amounts as per prospectus column in JHRML_ANNUAL_2025 p.43) | 12 | — | — | 45,016 | 45,930 | — | 1,728,441 | N | — | — | JHRML_ANNUAL_2025 p.43 | unspent after deadline | 30 | 4 | 3 | 0 | EXT 2023-12-31: Revised timeline within 2 years i.e. 31 March 2024 (14th AGM 2023) [JHRML_ANNUAL_2025 p.43] | EXT 2024-01-22: 15th AGM approved revised use of IPO proceeds and revised timeline to 31 March 2026 [announcement 39709; JHRML_ANNUAL_2025 p.43] | EXT 2025-10-27: Board recommended revision of IPO proceeds utilisation and extension of time up to 31 Dece [announcement 17789] | EXT 2026-01-22: 17th AGM approved revision of IPO proceeds utilisation and extension of time up to Decembe [announcement 12709] | CHG 2022-04-27 (Board): Board approved cost of BDT 42,500,000 to acquire 34 decimal land (adjacent site, Vitikandi [announcement 63722] | CHG 2022-10-26 (AGM (14th), BSEC): Board recommended revising use of IPO proceeds (Covid-19, exchange rate, Russia-Ukraine wa [announcement 58080; JHRML_ANNUAL_2025 p.43] | CHG 2023-10-19 (AGM (15th, 22 Jan 2024), BSEC): Board recommended further revision of use of IPO proceeds (Covid-19, dollar crisis, Russia [announcement 44163, 39709] | ipo_stats.csv listing_date | — | 1 | 1 | 0 | — | 30 |
| MEGHNAINS | 44,720 | 2,022 | 160,000,000 | 0 | 0 | 0 | 151,250,000 | 8,750,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | MEGHNAINS_PROSPECTUS_2022 p.272 | 6 | — | — | 44,903 | 44,834 | — | 0 | Y | 44,834 | stated completion date | MEGHNAINS_DOC_Q3_2022 p.1,2,4 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: auditor certificate Jul-Sep 2022 | 1 | 1 | 0 | — | — |
| NAVANAPHAR | 44,852 | 2,022 | 750,000,000 | 508,200,000 | 211,800,000 | 0 | 0 | 30,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | NAVANAPHAR_PROSPECTUS_2022 p.415 and p.424 | 24 | — | — | 45,583 | 45,838 | 727,487,988 | 22,342,657 | N | — | — | NAVANAPHAR_ANNUAL_2025_3 p.235 | unspent after deadline | 8 | 1 | 1 | 0 | EXT 2024-05-07: EGM approved extension of time for full utilization of IPO proceeds to within 36 months af [announcements 35713, 35712] | CHG 2024-05-07 (EGM (7th EGM, 7 May 2024)): Change use of BDT 13.12 crore (17.49% of IPO proceeds of BDT 75 crore) earmarked for Moder [announcements 35713; NAVANAPHAR_PSI_2024_2 p.1] | ipo_stats.csv listing_date | The 13.12 crore printed in crore; revised IPO-funded project 131,185,000 per EGM notice. Quarterly auditor reports on utilisation filed through Sep 2025 (announcement 17311) but numbers not in packet. | 1 | 1 | 0 | — | 8 |
| UNIONBANK | 44,587 | 2,022 | 4,280,000,000 | 0 | 0 | 0 | 4,215,000,000 | 65,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | UNIONBANK_ANNUAL_2023 p.86 (prospectus page not in packet) | 12 | — | — | 44,952 | 45,291 | 3,671,020,658 | 608,979,342 | N | — | — | UNIONBANK_ANNUAL_2023 p.86 | unspent after deadline | 11 | 2 | 1 | 1 | EXT 2023-06-15: 10th AGM approved extension of time for utilizing IPO fund till June 30, 2024, subject to [announcement 47956; UNIONBANK_PSI_2023_3 p.1] | EXT 2024-06-27: Board recommended extension of full utilization of IPO fund till June 30, 2025 for approva [announcement 34235; UNIONBANK_ANNUAL_2023 p.8] | CHG 2023-06-15 (10th AGM 15 June 2023): Modification of use of proceeds: unutilised amount allocated to IPO Expense can be transfe [UNIONBANK_PSI_2023_3 p.1; UNIONBANK_ANNUAL_2023 p.86] | ipo_stats.csv listing_date | Promised table taken from annual report (no prospectus pages in packet). Bank; 1 crore = 10,000,000. | 1 | 1 | 0 | — | 11 |
| UNIONINS | 44,577 | 2,022 | 193,609,040 | 40,000,000 | 0 | 0 | 141,981,319 | 11,627,721 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | UNIONINS_PROSPECTUS_2022 p.219 and p.220 | — | — | — | — | — | — | — | — | — | — | — | no statement found | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | No reported utilisation or announcements in packet; implementation schedule text not captured. | 1 | 0 | — | — | — |
| MIDLANDBNK | 45,012 | 2,023 | 700,000,000 | 0 | 0 | 0 | 661,101,545 | 38,898,455 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | MIDLANDBNK_PROSPECTUS_2023 p.245 | 6 | — | — | 45,196 | 45,291 | — | 0 | Y | 45,291 | stated completion date | MIDLANDBNK_QUARTERLY_Q4_2023 p.2 | completed after deadline | 3 | 0 | 1 | 0 | CHG 2023-10-29 (EGM 29 Oct 2023 (subject to regulatory approvals)): Transfer of unutilized Tk 4,673,976 under IPO Expenses to Investment in Government Securit [announcements 45769, 42331] | ipo_stats.csv listing_date | completion: Q4 2023 auditor certificate | 1 | 1 | 0 | 3 | — |
| TILIL | 45,057 | 2,023 | 160,000,000 | 0 | 0 | 0 | 152,000,000 | 8,000,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | TILIL_DOC_Q1_2023 p.3 (auditor certificate "Allotment as per Prospectus"); prospectus p.165 table not captured | — | — | — | — | 45,107 | — | 0 | Y | 45,107 | stated completion date | TILIL_DOC_Q1_2023 p.3,4,5 | completed, timing not measurable | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: completed in quarter to 30 Jun 2023 | 1 | 1 | 0 | — | — |
| ASIATICLAB | 45,357 | 2,024 | 950,000,000 | 641,965,856 | 280,000,000 | 0 | 0 | 28,034,144 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | ASIATICLAB_PROSPECTUS_2024 p.182, p.190 | 24 | — | — | 46,087 | 46,327 | — | 649,382,529 | N | — | — | DSE post id 6171 (1-Nov-2026) | unspent after deadline | 8 | 1 | 0 | 0 | EXT 2026-11-01: Board proposed time extension of at least 18 months from 06 March 2026 to utilise unutilis [announcement 6171] | ipo_stats.csv listing_date | Totals utilised/unutilised as of 30 June 2025 not read; BSEC IPO approval letter dated 21 Sep 2022. | 1 | 1 | 1 | — | 8 |
| BESTHLDNG | 45,328 | 2,024 | 3,500,000,000 | 2,210,923,539 | 1,156,076,461 | 0 | 0 | 133,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | BESTHLDNG_PROSPECTUS_2024 p.265, p.268 | 3 | — | — | 45,418 | 45,473 | — | — | N | — | — | BESTHLDNG_ANNUAL_2024 p.49 | unspent after deadline | 2 | 0 | 0 | 0 | — | ipo_stats.csv listing_date | 7 announcements are routine auditor reports (not shown). | 1 | 1 | — | — | 2 |
| NRBBANK | 45,349 | 2,024 | 1,000,000,000 | 0 | 0 | 0 | 961,700,000 | 38,300,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | NRBBANK_PROSPECTUS_2023 p.370 and p.375 | 12 | — | — | 45,715 | 45,382 | — | 0 | Y | 45,382 | stated completion date | NRBBANK_QUARTERLY_Q1_2024 p.2,3,5 | completed by deadline | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | completion: 100% within 31 Mar 2024 | 1 | 1 | 0 | — | — |
| SICL | 45,315 | 2,024 | 160,000,000 | 60,871,500 | 0 | 0 | 88,000,000 | 11,128,500 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | SICL_PROSPECTUS_2024 p.156 and p.157 | 3 | — | — | 45,406 | 46,022 | — | — | N | — | — | SICL_ANNUAL_2025 p.3 (auditor Other matter) | unspent after deadline | 20 | 0 | 0 | 1 | — | ipo_stats.csv listing_date | Insurer IPO; capital-market portion (48,000,000) unutilised beyond 3-month deadline per auditor; quotation is OCR-garbled. | 1 | 1 | — | — | 20 |
| TECHNODRUG | 45,487 | 2,024 | 1,000,000,000 | 670,000,000 | 300,000,000 | 0 | 0 | 30,000,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | TECHNODRUG_PROSPECTUS_2024 p.272 | 24 | — | — | 46,217 | 45,838 | 644,620,905 | 355,379,095 | N | — | — | TECHNODRUG_ANNUAL_2025 p.100 and p.68 | unspent, deadline not yet passed at statement | — | 0 | 0 | 0 | — | ipo_stats.csv listing_date | — | 1 | 1 | 0 | — | — |
By year
| Listing year | IPOs in scope | With promised split | Promised total, split IPOs (BDT) | Capex (BDT) | Loan repayment (BDT) | Working capital (BDT) | Investments (BDT) | IPO costs (BDT) | Other + not itemised (BDT) | Capex share | Loan repayment share | Working capital share | Investments share | IPO costs share | With reported data |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2010 | 6 | 2 | 390,000,000 | 0 | 0 | 283,966,500 | 90,000,000 | 0 | 16,033,500 | 0 | 0 | 1 | 0 | 0 | 0 |
| 2011 | 3 | 1 | 294,140,000 | 224,440,000 | 50,200,000 | 19,500,000 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | 0 | 1 |
| 2012 | 10 | 6 | 4,172,728,000 | 1,078,750,000 | 2,211,919,000 | 255,999,000 | 500,000,000 | 126,060,000 | 0 | 0 | 1 | 0 | 0 | 0 | 2 |
| 2013 | 11 | 10 | 8,757,646,500 | 4,594,319,016 | 3,196,245,768 | 168,746,562 | 565,066,500 | 209,882,654 | 23,386,000 | 1 | 0 | 0 | 0 | 0 | 3 |
| 2014 | 16 | 16 | 8,027,741,500 | 4,589,267,686 | 2,648,653,949 | 517,382,765 | 0 | 272,437,100 | 0 | 1 | 0 | 0 | 0 | 0 | 6 |
| 2015 | 12 | 12 | 9,654,721,200 | 5,463,139,990 | 1,972,137,667 | 401,764,794 | 0 | 307,888,749 | 1,509,790,000 | 1 | 0 | 0 | 0 | 0 | 10 |
| 2016 | 7 | 5 | 4,999,800,000 | 4,656,250,096 | 40,000,000 | 15,427,654 | 172,466,000 | 115,656,250 | 0 | 1 | 0 | 0 | 0 | 0 | 3 |
| 2017 | 7 | 7 | 2,442,500,000 | 1,585,507,111 | 728,385,716 | 0 | 0 | 111,217,173 | 17,390,000 | 1 | 0 | 0 | 0 | 0 | 4 |
| 2018 | 11 | 11 | 5,010,000,000 | 3,894,690,192 | 857,061,644 | 0 | 0 | 258,248,164 | 0 | 1 | 0 | 0 | 0 | 0 | 10 |
| 2019 | 9 | 9 | 5,400,000,000 | 4,107,918,502 | 1,045,000,000 | 0 | 0 | 232,081,498 | 15,000,000 | 1 | 0 | 0 | 0 | 0 | 6 |
| 2020 | 7 | 7 | 7,678,723,340 | 6,593,600,701 | 470,603,373 | 0 | 395,061,500 | 199,881,766 | 19,576,000 | 1 | 0 | 0 | 0 | 0 | 5 |
| 2021 | 13 | 13 | 10,460,000,000 | 3,736,756,493 | 2,288,155,282 | 0 | 4,033,111,260 | 401,976,966 | 0 | 0 | 0 | 0 | 0 | 0 | 12 |
| 2022 | 9 | 9 | 10,886,220,100 | 1,145,900,000 | 461,800,000 | 0 | 9,025,514,692 | 253,005,408 | 0 | 0 | 0 | 0 | 1 | 0 | 8 |
| 2023 | 2 | 2 | 860,000,000 | 0 | 0 | 0 | 813,101,545 | 46,898,455 | 0 | 0 | 0 | 0 | 1 | 0 | 2 |
| 2024 | 5 | 5 | 6,610,000,000 | 3,583,760,895 | 1,736,076,461 | 0 | 1,049,700,000 | 240,462,644 | 0 | 1 | 0 | 0 | 0 | 0 | 5 |
| 2010-2024 | 128 | 115 | 85,644,220,640 | 45,254,300,682 | 17,706,238,860 | 1,662,787,275 | 16,644,021,497 | 2,775,696,827 | 1,601,175,500 | 1 | 0 | 0 | 0 | 0 | 77 |
| 2010-2014 | 46 | 35 | 21,642,256,000 | 10,486,776,702 | 8,107,018,717 | 1,245,594,827 | 1,155,066,500 | 608,379,754 | 39,419,500 | 0 | 0 | 0 | 0 | 0 | 12 |
| 2015-2019 | 46 | 44 | 27,507,021,200 | 19,707,505,891 | 4,642,585,027 | 417,192,448 | 172,466,000 | 1,025,091,834 | 1,542,180,000 | 1 | 0 | 0 | 0 | 0 | 33 |
| 2020-2024 | 36 | 36 | 36,494,943,440 | 15,060,018,089 | 4,956,635,116 | 0 | 15,316,488,997 | 1,142,225,239 | 19,576,000 | 0 | 0 | 0 | 0 | 0 | 32 |
Summary
| Measure | Value |
|---|---|
| IPOs listed 2010-2024 in scope (prospectus in corpus) | 128 |
| With promised use-of-proceeds split | 115 |
| With a reported utilisation statement | 77 |
| With both promised split and reported statement | 74 |
| Promised total, IPOs with split (BDT) | 85,644,220,640 |
| Capex share of promised money | 52.8% |
| Loan repayment share | 20.7% |
| Working capital share | 1.9% |
| Investments share | 19.4% |
| IPO costs share | 3.2% |
| Reported fully utilised (Y) | 50 |
| Reported not fully utilised at latest statement (N) | 27 |
| Completed by deadline (evidence date on or before deadline) | 14 |
| Completed after deadline | 11 |
| Unspent at a statement dated after the deadline | 18 |
| Unspent, deadline not yet passed at statement | 4 |
| Timing measurable (sum of the four rows above) | 47 |
| Share completed by deadline, of IPOs whose deadline had passed (rows 14-16) | 32.6% |
| Median months late: completed after deadline | 16.8 |
| Median months past deadline: unspent at latest statement | 11.8 |
| IPOs with at least one extension decision recorded | 27 |
| IPOs with at least one change of purpose recorded | 41 |
| Unspent money at latest statements, IPOs not fully utilised (BDT) | 5,188,399,482 |
| IPOs with an unspent amount printed | 21 |
| Unspent printed at statements dated 2025 or later (BDT) | 2,643,711,729 |
| IPOs in that row | 8 |
| Median capex share per IPO | 63.2% |
| Median loan repayment share per IPO | 11.4% |
| IPOs promising any loan repayment | 64 |
| IPOs with timing not measurable or no statement | 81 |
Remarks
| IPO (DSE code) | By | Quote (verbatim) | Source |
|---|---|---|---|
| ARGONDENIM | auditor | a) We observed over adjustment of short term loan from IPO proceeds beyond the prospectus amount. We observed excess payment of IPO related expenses. c) Liabilities from IPO fund found adjusted against bridge finance and short term loan earlier undisclosed in the prospectus. d) We also observed that significant amount was made to various suppliers and contractors against purchase of construction materials from IPO proceeds for expansion project in cash instead of cheque. | announcements 111723/111721/111722 (2014-05-12, emphasis of matter, year ended 31 Dec 2013, note 36.1) |
| MATINSPINN | auditor | In Note: 4 to the financial statements, management explains about the use of two diesel generators which were purchased with the fund from IPO proceeds for the MÂlange unit of the company. | announcement 94860 (2017-01-01), Emphasis of Matter FY2016 |
| DSSL | BSEC | BSEC has imposed fine of Tk. 5.00 lac each to the following Sponsors & Directors of the Company namely Mr. Mostafa Quamrus Sobhan (Chairman), Mr. Mostafa Golam Quddus (Managing Director), Mrs. Fazlutun Nessa (Director), Mrs. Fauzia Quamrun Tania (Director), Mrs. Tasnia Quamrun Anika (Director) and Mrs. Shafia Sobhan Chowdhury (Director) for noncompliance of Securities laws in connection with utilization of IPO proceeds. | announcement 85733 (2018-03-11, DSE news citing BSEC) |
| PDL | BSEC | BSEC has imposed penalty of Tk. 3.00 lac each of the following Directors of the Company; namely Mr. Md. Shadequl Alam (Yeasin), Chairman; Mr. Shafiul Azam (Mohsin), Managing Director; Mr. Md. Sohel Khan, Director and Mr. M. A. Kamal Bhuiyan (nominated Director from Disney Properties Ltd.) for noncompliance with Securities laws in connection with utilization of IPO proceeds. | announcement 185197 (2019-01-08) |
| SHEPHERD | auditor | IPO proceeds have been utilized in line with the conditions as stipulated in the BSEC’s Consent letter for the IPO and revised IPO Utilization plan as approved in the 17 AGM which is yet to be approved by the Bangladesh Securities and Exchange Commission (BSEC) | SHEPHERD_DOC_2019_3 p.2 |
| ACFL | auditor | According to IPO Utilization Audit Reports as of June 30 2025, the company has Un- utilized IPO proceeds amounting BDT. 717,498,337 and the shareholders of Aman Cotton Fibrous PLC has approved the revised time line for fund utilization of IPO proceed up to 31 December 2028. | ACFL_ANNUAL_2025 p.66 |
| ACFL | auditor | FDR of Tk. 73 crore made from IPO Proceeds is pledged as security for credit facilities enjoyed by other entities. | announcement 172877 (2020-10-13, Qualified Opinion on Utilization of IPO Fund, month of Aug 2020) |
| INTRACO | auditor | We draw attention to note # 33 of the financial statements, which describes the utilization of IPO proceeds up to 30 June 2020 as certified by independent auditor, Shiraz Khan Basak & Co, Chartered Accountants. Our opinion is not modified in respect of this matter. | announcement 171098 (2020-11-24, Emphasis of Matter) |
| KTL | BSEC | BSEC has imposed penalty of Tk. 50.00 lac each of the following Directors of the Company; namely Mr. Md. Anwarul Haque Chowdhury (Director), Mr. Md. Mokarrom Anwar Chowdhury (Director), Eian Apparels Ltd. (Director) Lucky Corner (Director), Ms. Nasreen Hoque (Chairman) and Tk. 1.00 crore on Mr. Md. Emdadul Hoque Chowdhury (Managing Director) for noncompliance with Securities laws in connection with utilization of IPO proceeds. | announcement 78315 (2020-08-25) |
| MLDYEING | DSE | Rest amount BDT. 130,397,512 of IPO fund has been utilized according to the decided purpose exceeding the time duration of IPO declaration due to the global impact of COVID-19 Pandemic. | announcement 77525 (2020-12-29, company statement) |
| QUEENSOUTH | auditor | The revised IPO Utilization plan is yet to be approved by the Bangladesh Securities and Exchange Commission (BSEC) | QUEENSOUTH_DOC_2020_4 p.2 |
| QUEENSOUTH | auditor | The company has purchased natural gas engine generator set instead of purchasing 1 set of Yarn Package Drying Machine | announcement 174349 (2020-07-23, Qualified Opinion) |
| SKTRIMS | auditor | The company should have utilized Tk.300, 000,000 but as per evidence collected, the company utilizes Tk.147, 889,570(49.29%). | SKTRIMS_ANNUAL_2020 p.50 |
| RINGSHINE | auditor | the company has surpassed its deadline of full utilization of IPO funds as per the approved Prospectus on April 05, 2021. | RINGSHINE_DOC_2024_12 p.3 |
| RINGSHINE | auditor | Management has changed the purposes of use of funds but the approval form the shareholders in AGM is yet to be received. | RINGSHINE_DOC_2024_12 p.3 |
| RUNNERAUTO | BSEC | the company shall not issue any bonus share prior to proper utilization of IPO proceeds in accordance with revised utilization plan. | announcement 176047 (2020-02-25) |
| DOMINAGE | auditor | The total IPO Fund was not utilized within the stipulated time and the company has taken further time extension from Bangladesh securities exchange commission. | DOMINAGE_ANNUAL_2023 p.2 (Emphasis of Matter 2) |
| DOMINAGE | auditor | The tetal IPO Fund was not utilized within the stipulated time and the company has applied further time extension to Bangladesh securities exchange commission up to December 2024. | DOMINAGE_ANNUAL_2024 p.2 (Emphasis of Matter; OCR typo 'tetal' as printed) |
| BPPL | auditor | IPO Expenses includes Tk. 7,877,215 that has been utilized for normal course of business which remained un-utilized for IPO expenses due to change of IPO process like, allocation of share by pro-rata basis instead of conducting lottery and others as estimated while preparing published prospectus. | BPPL_DOC_2021_12 p.1 |
| LOVELLO | auditor | BSEC has not approved the rectification and extension of time till to date | LOVELLO_ANNUAL_2025 p.63 |
| LOVELLO | auditor | The expenses/utilization has been made in line with the provision of Initial Public Offering (IPO) documents except Tk. 10,337,854 | LOVELLO_ANNUAL_2025 p.63 |
| LRBDL | auditor | As on date an amount of 13.10 Crore from the IPO proceeds remains unspent and held in Social Islami Bank PLC which has outstanding balance of 19.87 Crore including profit accrued thereon. This non-utilization of funds is a material non-compliance with the stated purpose of the IPO as disclosed in Paragraph- a of chapter-XXII of the said prospectus. | LRBDL_ANNUAL_2025_2 p.2 |
| NRBCBANK | auditor | IFO Tk. 8,845,414 higher than proposed expenses mentioned in the documents due to processing of more than expected application cost, Eligible Investor Data processing cost by DSE and additional CDBL Charge | NRBCBANK_DOC_2021_2 p.3 (OCR) |
| SIPLC | auditor | using the proceeds of the IPO funds as consented by the BSEC, for which the company will take approval in the Annual General Meeting (AGM). However, our opinion is not modified in respect of these matters. | announcement 51553 (2023-03-15, Emphasis of Matter, partial text) |
| UNIONBANK | DSE | Due to unavoidable circumstances the remaining amount of Investment in Capital Market could not be properly utilized within the timeline as per Prospectus. | announcement 34235 (2024-06-30, company statement) |
| SICL | auditor | The company took IPO fund from the share market previous year and it was given 03 months to utilized this fund which yet to be done. | SICL_ANNUAL_2025 p.3 (read from page image) |
Rules
| Rule | Text (verbatim) | Source |
|---|---|---|
| 2025 Rules, rule 4(1)(t): quarterly audited report | it has declared that the issuer shall be responsible for submitting a report to the Commission on utilization of public issue proceeds duly audited by a panel of auditors of the Commission within 10 (ten) days of the end of each quarter with a confirmation to the effect that the public issue proceeds has been utilized according to the use of proceeds mentioned in the prospectus | BSEC (Public Offer of Equity Securities) Rules, 2025, gazette 30-Dec-2025, PDF p.10 |
| 2015 Rules, Annexure (prospectus contents): schedule | A schedule mentioning the stages of implementation and utilization of funds received through public offer | BSEC (Public Issue) Rules, 2015 (consolidated 4-Apr-2022), use of proceeds section, PDF p.57 |
| 2015 Rules: auditor certificate on earlier issues | The issuer shall submit auditor's certificate on utilization of the fund raised through issue of capital earlier. | BSEC (Public Issue) Rules, 2015 (consolidated), item (27), PDF p.65 |
FAQ
- How do Bangladeshi companies use IPO money?
- In 115 prospectuses of 2010-2024 IPOs, 52.8% of the money was promised to machinery, buildings and expansion, 20.7% to loan repayment, 19.4% to investments (mostly banks and insurers), 1.9% to working capital and 3.2% to IPO costs.
- How long do companies have to spend IPO money?
- The prospectus sets the schedule, typically from one month for loan repayment to 24 months for new plants. Changing the time or the purpose needs shareholder approval and BSEC consent. Under the 2025 Rules, issuers report utilisation to BSEC each quarter, audited by a BSEC-panel auditor, within 10 days of the quarter end.
- Do companies spend IPO money on time?
- Of 43 IPOs whose deadline had passed and whose timing we could measure, 14 (32.6%) spent the money by the deadline. 11 finished late (median 16.8 months) and 18 still had money unspent after the deadline. 27 IPOs recorded at least one extension.
- How much IPO money is still unspent?
- 8 IPOs reported BDT 2.64bn unspent in statements dated 2025 or 2026; the largest were Global Islami Bank (BDT 738.2m), Aman Cotton Fibrous (BDT 717.5m) and Asiatic Laboratories (BDT 649.4m).
- Has BSEC fined anyone over the use of IPO money?
- BSEC fined directors of Dragon Sweater and Spinning (2018), Pacific Denims (2019) and Kattali Textile (2020) for non-compliance with securities laws 'in connection with utilization of IPO proceeds'. Auditors also qualified or flagged IPO-fund use at Aman Cotton Fibrous, Queen South Textile, Lub-rref, Ring Shine and others.
- Where can I see a company's IPO proceeds utilisation?
- In its quarterly or monthly auditor-certified utilisation statements filed with BSEC and the exchanges, in the notes of its annual report, and in DSE news posts. Our model lists the prospectus page and the latest statement page for each IPO.
Sources
- AnalystBro model for this article (model.xlsx: IPOs, By year, Summary, Remarks, Rules), 16-Nov-2026 · link · accessed 2026-11-16
- IPO prospectuses of DSE-listed companies (use of proceeds and implementation schedule pages), AnalystBro filings corpus; doc_key and page per IPO in model sheet IPOs · link · accessed 2026-11-16
- Annual, quarterly and price-sensitive reports and auditors' IPO-utilisation certificates of the same companies, AnalystBro filings corpus; doc_key and page per IPO in model sheet IPOs · link · accessed 2026-11-16
- Dhaka Stock Exchange news posts on IPO proceeds (extensions, changes of use, auditor opinions, BSEC penalties), 2008-2026; post id per item in model sheets IPOs and Remarks · link · accessed 2026-11-16
- BSEC (Public Offer of Equity Securities) Rules, 2025: notification dated 28-Dec-2025, gazette 30-Dec-2025, rule 4(1)(t) · link · accessed 2026-11-16
- BSEC (Public Issue) Rules, 2015, consolidated to the amendment of 24-Aug-2021 (posted 4-Apr-2022) · link · accessed 2026-11-16
- Aman Cotton Fibrous annual report FY2025, p.66 (unutilised IPO proceeds); DSE post 13-Oct-2020 (qualified opinion on utilisation of IPO fund) · link · accessed 2026-11-16
- Global Islami Bank: DSE posts 29-Apr-2024, 9-Jul-2025, 20-Aug-2025 and 19-Oct-2025 (extensions, unutilised amount, BSEC approval) · link · accessed 2026-11-16
- Asiatic Laboratories: DSE post 1-Nov-2026, board proposal for extension of time for utilisation of IPO proceeds · link · accessed 2026-11-16
- Ring Shine Textiles: auditor's IPO-utilisation certificate for July 2023-June 2024 (RINGSHINE_DOC_2024_12 p.3); DSE post 20-Jul-2025 (BSEC rejection) · link · accessed 2026-11-16
- Lub-rref (Bangladesh) annual report FY2025, auditor's report p.2 · link · accessed 2026-11-16
- DSE posts on BSEC penalties: Dragon Sweater and Spinning 11-Mar-2018, Pacific Denims 8-Jan-2019, Kattali Textile 25-Aug-2020 · link · accessed 2026-11-16
- Queen South Textile Mills: DSE post 23-Jul-2020 (qualified opinion); auditor's certificate 12-Mar-2020 (QUEENSOUTH_DOC_2020_4 p.2) · link · accessed 2026-11-16
- S.K. Trims & Industries annual report FY2020, pp.20 and 50 · link · accessed 2026-11-16
- Lovello Ice-cream annual report FY2025, p.63 (auditor's report on IPO utilisation) · link · accessed 2026-11-16
- Runner Automobiles: DSE post 25-Feb-2020 (BSEC approval of revised utilisation plan, with condition) · link · accessed 2026-11-16
- Technodrugs annual report FY2025, pp.68 and 100; Navana Pharmaceuticals annual report FY2025 p.235; Silva Pharmaceuticals annual report FY2025 pp.44-45; JHRML annual report FY2025 p.43 · link · accessed 2026-11-16
Disclaimer
This article is published by AnalystBro for information and education only. It is not investment, financial, legal or tax advice, not an offer or solicitation to buy or sell any security, and not a recommendation. It is based on company filings, official statistics and the sources cited, and was independently reviewed before publishing; it may still contain errors or omissions, and the data and estimates can be out of date. Fair values, forecasts and the model are estimates under stated assumptions, not predictions; past results don't indicate future returns.
AnalystBro, its owners and staff accept no responsibility or liability for any loss or damage arising from the use of, or reliance on, this article, its model or its data. Do your own research and consult a licensed adviser before making investment decisions. Any changes you make in the spreadsheet view stay in your browser and are your own.